Beruflich Dokumente
Kultur Dokumente
Midas Gen One Stop Solution for Building and General Structures
ColumnShortening
Contents
I. Introduction in Column Shortening II. Column Shortening of Lotte World Tower III. midas Gen Introduction
m Introduction
midas Gen Introduction
Works Tree (Input summary with powerful modeling capabilities) Models created and changed with ease Floor Loads defined by area and on inclined plane Built-in Section property Calculator Tekla Structures, Revit Structures & STAAD interfaces
RC Design: ACI318, Eurocode 2 & 8, BS8110, IS:456 & 13920, CSA-A23.3, GB50010, AIJ-WSD, TWN-USD, Steel Design: AISC-ASD & LRFD, AISI-CFSD, Eurocode 3, BS5950, IS:800, CSA-S16, GBJ17 & GB50017, AIJ-ASD, TWN-ASD & LSD, SRC Design: SSRC, JGJ138, CECS28, AIJ-SRC, TWN-SRC Footing Design: ACI381, BS8110 Slab & Wall Design: Eurocode 2 Capacity Design: Eurocode 8, NTC2008 3-D Column Shortening Reflecting change in Modulus, Creep and Shrinkage Construction Stage Analysis accounting for change in geometry, supports and loadings Building model generation wizard Automatic mass conversion Material stiffness changes for cracked section
Comprehensive Design
Introduction
multi-storey reinforced concrete structure
ColumnShortening
Contents
I. Introduction in Column Shortening II. Column Shortening of Lotte World Tower III. midas Gen Introduction
ColumnShortening
ColumnShortening
19.6 19.6
Usability aspects
Safety of Elevator operation due to tower tilt Deformation and failure of curtain wall and exterior materials Deformation and failure of Vertical piping Reverse Inclination of Drainage Piping System Serviceability problems due to slope on the slab Breakage of finishes
ColumnShortening
ColumnShortening
Tower Deformation
Column Shortening in Concrete Structures = Elastic Deformation 1 + Inelastic Deformation 2 Inelastic Shortening: 1 ~ 3 times of Elastic Shortening Types of Inelastic Shortening: Shrinkage, Creep
Deferential Shortening
1
Conc Vertical Member
With Time
1 2
Core Shortening
Core wall
<Inelastic>
Initial Curing
<Elastic>
ColumnShortening
Steel Structures
- Linear elastic Behavior
Nonlinear Inelastic Behavior But in general Analysis and design behavior of concrete is treated as linear elastic material
Nor Strain is constant for a given Stress During loading & unloading
E = ( / ) L = (PL/A E)
10
ColumnShortening
Column Shortening
Elastic and Inelastic Column Shortening
Two basic prerequisites for accurately and efficiently predicting these effects are Reliable Data for the creep and shrinkage characteristics of the particular concrete mix Analytical procedures for the inclusion of these time effects in the design of structure. Some of the popular predictive methods for predicting creep and shrinkage strains are Eurocode ACI 209 -92 Bazant Bewaja B3 CEB FIP (1978, 1990) PCA Method (Mark Fintel) GL 2000 (Gardner and Lockman)
11
ColumnShortening
Column Shortening
Elastic and Inelastic Column Shortening
The total strain at any time t may be expressed as the sum of the instantaneous, creep and shrinkage components:
Where, e (t) = Instantaneous strain at time t, c (t) = Creep strain at time t, sh (t) = Shrinkage strain at time t.
12
ColumnShortening
Column Shortening
Elastic and Inelastic Column Shortening
Ecm: Secant modulus of elasticity of concrete at an age of 28 days fcm(t): Mean value of concrete cylinder compressive strength at an age of t days fcm: Mean value of concrete cylinder compressive strength at an age of 28 days
cc(t): Coefficient which depends on the age of the concrete t s: Coefficient which depends on the type of cement, 0,20 or 0,25 or 0,38
13
ColumnShortening
Column Shortening
Elastic and Inelastic Column Shortening
Shrinkage
As per EN1992-1-1:2004, the total shrinkage strain is composed of two components, the drying shrinkage strain and the autogenous shrinkage strain. Drying Shrinkage(cd) is due to moisture loss in concrete. Autogenous Shrinkage(ca) is caused by hydration of cement.
Where, kh = coefficient depending on the notional size h0 t = age of the concrete at the moment considered ts = age of the concrete (days) at the beginning of drying shrinkage
14
ColumnShortening
Concrete Composition
Curing Member Geometry and Environment Variable (Creep & Shrinkage) Loading (Creep Only) Environment Geometry Loading History Stress Conditions
Required to monitor during construction by material test and measuring in the field.
15
ColumnShortening
Pre-Analysis
Material Experiment
Compressive strength Modulus of elasticity Creep & Shrinkage
Main analysis
Updating material properties from experiments Construction sequence considering the field condition
Main Analysis,
Construction
& Re-Analysis
Measurement
Measurement of strain for Column & Wall
Final Report
4.0E-04
Back Analysis Output (103-1F-01) Strain Gauge Output (103-1F-01)
3.0E-04
2.0E-04
0.0E+00
Strain
1.0E-04
16
ColumnShortening
Variables of Shortening
(30~40%) Environment Condition
Temperature Relative Humidity
Material Properties
Elastic Modulus, Conc. Strength Mix ratio(W/C, S/A ), Amount of air Volume vs Surface ratio, Rebar ratio Curing condition
18 16 14
3 ) Creep Deformation(x10 (x103 )
construction schedule, material properties, and environment condition. For the safety factor, conservative results will be obtained. Serviceability problems can occur due to the over-estimated compensation. 2) Accurate shortening must be calculated during construction by
(PCA) Pre-analysis
17
ColumnShortening
Compressive strength / modulus of elasticity / drying shrinkage / creep experiments Generate formulations based on the test and update the model Need on-site materials testing according to the construction progress Reflect Site Conditions at a given time
Elastic Modulus
Primary Modulus test Secondary Modulus test Third order Modulus test
Measure Deformation
<Loading of Specimens>
18
ColumnShortening
Using Software or Manual Calculation Shortening analysis based on the predictive equations Apply material test results Consider construction schedule Difference in field environmental condition (temperature, humidity) Difference in initial curing condition Difference in loading history Difference in material composition
5.0E-04 4.5E-04 4.0E-04 3.5E-04 3.0E-04
Strain
Field Measurements Installing gages in major structural members Measuring deformations in accordance with construction field condition Considering accurate loading time Considering field condition and variables Apply for the compensation
2.5E-04 2.0E-04 1.5E-04 1.0E-04 5.0E-05 0.0E+00 0 50 100 150 200 250 300 Date 350 400 450 500 550
19
ColumnShortening
Installation of Gauge
After Installation
20
ColumnShortening
Compensation at Site
Pre-slab installation shortenings Shortenings taking place up to the time of slab installation
Post-slab installation shortenings Shortenings taking place after the time of slab installation
Reinforced Concrete Structure Pre-slab installation shortenings has no importance Compensation by leveling the forms Post-slab installation shortenings due to subsequent loads and creep/shrinkage :Compensation
Steel Structure Columns are fabricated to exact length. Attachments to support the slabs Pre-slab installation shortenings need to be known.
21
ColumnShortening
Compensation at Site
1st correction
Column Column
22
ColumnShortening
Contents
I. Introduction in Column Shortening II. Column Shortening of Lotte World Tower III. midas Gen Introduction
23
Overview
24
Overview
25
Overview
26
Pre-Analysis - Deformations
Lantern & Core
Horizontal deformation Vertical deformation
Top of tower Steel Frame: 368.7 mm Core wall: 314.0 mm Top of mega column Mega Col: 297.8 mm Core wall: 232.8 mm
Prediction
OW4 OW3
Y-Dir
OW2
OW1
A BOVE
OW11
OW6
X-Dir
X dir: 27.2mm Y dir: 115.5mm Safety check Elevators rails Vertical Pipes
OW4
OW7
OW7
OW8
OW9
OW10
Differential settlement
<initial>
MEGA COL. CORE WALL MEGA COL.
OW10
OW12
OW5
OW1
Differential Shortening
Deferential Shortening
Core Shortening Column Shortening
FOUNDATION
<Complete>
CORE WALL
Core wall
Column
27
Pre-Analysis - Stresses
Slabs additional stress Stress in Outrigger
L87~L103
Additional Stress without Delay Joint
Additional stress btw tower & podium Max 100 ton.m Require Settlement Joint & Safety check
L72~L75
2nd outrigger (L72~L75): 4,700 tons required a delay joint installation Additional Stress with Delay Joint 1st outrigger (L39~L43): 1,700 tons 2nd outrigger (L72~L75): 2,000 tons
L39~L43 Tower
Podium
B06~B01 28
Pre-Analysis Compensation
- Core wall: Absolute correction for securing design level - Column: Relative correction for deferential shortening
Lantern
F loor
Core
Column
L106-L123 +1mm Design level+1mm L106~L123 Steel columns L76-L105 L76~L105 Design level+2mm +2mm Steel columns Design level+2mm level+25mm +3mm +25mm Core 2nd O/R Design level+2mm +3mm +30mm Core level+30mm Design level+2mm +3mm +35mm Core level+35mm Design level+2mm +2mm +40mm Core level+40mm Design level+2mm +2mm +45mm Core level+45mm Design level+2mm +2mm +50mm Core level+50mm Design level+3mm +3mm +55mm Core level+55mm Design level+3mm +3mm +60mm Core 1st level+60mm O/R Design level+3mm +3mm +55mm Core level+55mm Design level+3mm +3mm +50mm Core level+50mm
+3mm +50mm Core level+50mm Design level+3mm +3mm +45mm Core level+45mm Design level+3mm +3mm +40mm Core level+40mm Design level+3mm +3mm +35mm Core level+35mm Design level+3mm +3mm +30mm Core level+30mm Design level+3mm +3mm +25mm Core level+25mm Design level+3mm +3mm +20mm Core level+20mm Design level+3mm +3mm +15mm Core level+15mm Design level+3mm +3mm +10mm Core level+10mm Design level+3mm +3mm +5mm Design level+3mm
2nd B/T
L72-L75 L72~L75 L69-L71 L69~L71 L66-L68 L66~L68 L63-L65 L63~L65 L60-L62 L60~L62 L57-L59 L57~L59 L37-L56 L54~L56 L54-L56 L37~L53 L34-L36 L34~L36 L31-L33 L31~L33
L28~L30 L28-L30 L25~L27 L25-L27
1st correction
1st O/R
L40
L30
2nd correction
L20 L10
L01 B06
Core level+5mm
29
: B006~L070 : B006~L050 A A
L38
L28
: Strain Gauge
L18 L10
Foundation settlement
30
Additional stress due to differential shortening between core and column Provide outrigger delay joint
Additional Stress 4700 kN 2nd Outrigger (L72~L75)
31
Additional stress due to differential shortening between core and column Additional reinforcement details are in each area
Slabs additional stress check
Reinforcement
STORY
Connecting member
Differential Shortening
Column
Core Wall
32
The Side of Tower
Jack Support
The Side of Podium
Settlement Joint
Control Joint
t
b
Detail of reinforcement
Elastic Modulus
Pre-analysis Re-analysis
Design Strength
Specific Creep
Design Strength
35
Re-analysis Results
Shortening Results 1-1. Mega Column Shortening (B06~L75) Target Period: 3years - 3 years was determined as the optimal time of target serviceability application. settlement shortening - Mega column: 21.2~25.5mm (B6) - Core wall: 23.6~29.1mm (B6)
MC2 137.2(L69)
Wall MAX
PW4 85.6(L71)
Col. MIN
PW15 79.6(L71)
PW14 77.4(L71)
IW1 75.5(L71)
IW2 83.0(L71)
PW13 79.5(L71)
IW3 77.9(L71)
IW4 77.5(L71)
PW6 77.4(L71)
PW5 83.4(L71)
MC7 131.4(L69)
Col. MAX
Maximum shortening of mega column - SubTo: 131.4~137.2mm (L65, L69) (80~83% of pre-analysis) - Total: 289.1~297.8mm (L76) (71~73 % of pre-analysis) Shortening of core walls - SubTo: 74.1~85.9mm (L71) (77~78% of pre-analysis) - Total: 153.0~169.8mm (L76) (67~70% of pre-analysis) Differential shortening between column-core - 53.1~60.9mm (L65)
PW12 77.1(L71)
MC6 132.2(L69)
PW7 75.1(L71)
PW11 76.8(L71)
PW10 75.0(L71)
PW9 74.1(L71)
PW8 75.3(L71)
MC3 135.6(L69)
Wall MIN
MC5 131.6(L69)
MC4 133.3(L69)
36
Re-analysis Results
Shortening Results 1-2. Steel Column Shortening(L76~L106)
SC6 115.1(L76) SC5 129.6(L76) SC4 132.6(L76) SC3 121.0(L76) Wall MAX PW2 73.9(L76) PW3 81.1(L76) SC2 136.9(L76) Col. MAX
SC7-1 128.8(L76)
SC8-1 130.0(L76)
PW15 74.4(L76)
PW4 80.9(L76)
Target Period: 3years - 3 years was determined as the optimal time of target serviceability application. Maximum shortening of steel column - SubTo: 110.4~136.9mm (L76) (80% of pre-analysis) - Total: 260.7~286.1mm (L76) (80% of pre-analysis) Shortening of core walls - SubTo: 67.8~81.0mm (L76) (65~70% of pre-analysis) - Total: 162.9~213.6mm (L76) (67~70% of pre-analysis) Differential shortening between Column-core - 40.1~44.5mm (L76)
37
SC1 121.2(L76)
PW14 71.6(L76)
IW1 71.2(L76)
IW2 78.5(L76)
PW5 78.3(L76)
SC22 133.1(L76)
PW6 72.0(L76)
SC10 124.0(L76)
PW13 74.4(L76)
IW3 73.7(L76)
IW4 72.3(L76)
SC21 130.1(L76)
PW12 71.5(L76)
PW7 69.3(L76)
SC11 126.5(L76)
SC12 115.0(L76)
PW11 71.1(L76)
PW10 68.9(L76)
PW8 69.4(L76)
SC18 128.0(L76)
SC19-1 130.4(L76)
SC13 130.0(L76)
SC17 111.9(L76)
SC18-1 126.5(L76)
L
nd
Re-analysis Results
Compensation due to core and column differential shortening
Lantern
- Core wall: Absolute compensation up to design level - Column: Absolute + Relative compensation due to differential shortening
+25mm +30mm +35mm +40mm +40mm +40mm +45mm +45mm +45mm +50mm +50mm +55mm +55mm +55mm +50mm +50mm +50mm +45mm +45mm +40mm +35mm +35mm +35mm +30mm +30mm +25mm +25mm +20mm +20mm +25mm +30mm +35mm +40mm +45mm +50mm +55mm +60mm +65mm +70mm +75mm +80mm +105mm +100mm +95mm +90mm +85mm +80mm +75mm +70mm +65mm +60mm +55mm +50mm +45mm +40mm +35mm +25mm +20mm L120 ~ L123 L113 ~ L119 L107 ~ L112 L103 ~ L106 L100 ~ L102 L99 ~ L99 L96 ~ L98 L91 ~ L95 L90 ~ L90 L88 ~ L89 L81 ~ L87 L77 ~ L80 L56 ~ L76 L52 ~ L55 L45 ~ L51 L37 ~ L44 L33 ~ L36 L30 ~ L32 L28 ~ L29 L23 ~ L27 L22 ~ L22 L19 ~ L21 L18 ~ L18 L14 ~ L17 L13 ~ L13 L10 ~ L12 L8 ~ L9
2 B/T
2 O/R 1 st B/T
nd
1st correction
1 st O/R
L40
2nd correction
L01 B06
L6 ~ L7 L5 ~ L5 B6 ~ L4
38
Contents
I. Introduction in Column Shortening II. Column Shortening of Lotte World Tower III. midas Gen Introduction
39
Tekla Structure
Revit Structure
midas Gen
[Tekla interface]
[Revit interface]
STAAD Import/Export SAP2000 Import AutoCAD DFX Import/Export IFC Export MSC.Nastran Import Drawing Module (midas Gen) Export Unit Member Design Module (Design+) Export
[MCAD 3D midas CAD]
40
Material Data
Material Data Definition
Database Code Name BS British Standards ASTM American Society for Testing Materials EN European Code DIN Deutshes Institut Fur Normung e.v CSA Canadian Standards Association IS Indian Standards JIS Japanese Industrial Standards KS Korean Industrial Standards GB Chinese National Standard JGJ Chinese Engineering Standard JTJ Chinese Transportation Department Standard *SRC and User Defined material properties can be defined
[Steel & Concrete Material Database]
Creep/Shrinkage - Eurocode, ACI, CEB-FIP, PCA Comp. Strength - Eurocode, ACI, CEB-FIP, Ohzagi
41
Section Data
Section Data Definition
Section Database AISC2K(US), AISC2K(SI), AISC, CISC02(US), CISC02(SI), BS, DIN Import data file already defined Input dimensions of typical sections Typical steel section (I, T, Channel, Angle, Pipe) Steel Concrete composite section (SRC) Tapered section Section Property Calculator tool
[Section Database]
42
m Loads
midas Gen Introduction
Self Weight Nodal Load Prescribed Displacement Elements Beam Load Line Beam Load Floor Load Prestress Beam Load Pretension Load Tendon Prestress Load Hydrostatic Pressure Load
midas Gen enables us to specify all types of nodal, element, point, surface, dynamic, prestressing and thermal loads encountered in practice. Load combination based on the various design codes Load group generation of load case from load combinations
Static Wind Load Static Seismic Load Construction Stage Load Initial Forces Time History Load Moving Load Pushover Loads Response Spectrum Function Ground Acceleration Dynamic Nodal Loads
[Floor Load]
43
m Boundary Conditions
midas Gen Introduction
[Floor Diaphragm]
Supports Point Spring Supports General Spring Supports Surface Spring Supports Pile Spring Supports
Elastic Link Nodal Coordinate System Beam End Release (Semi-rigid connection) Beam End Offset Release
Linear Constraints
Plate End
44
m Analysis
midas Gen Introduction
[Pushover analysis]
Static Analysis Dynamic Analysis Free Vibration Analysis Response Spectrum Analysis Time History Analysis Geometric Nonlinear Analysis P-Delta Analysis Large Displacement Analysis Material Nonlinear Analysis Structural Masonry Analysis Linear Buckling Analysis Lateral Torsional Buckling Heat Transfer Analysis Time Transient Analysis Heat of Hydration Analysis Thermo-elastic Analysis Maturity, Creep, Shrinkage, Pipe Cooling Construction Stage Analysis Time Dependent Material Column Shortening Analysis (Elastic/Inelastic) Pushover Analysis FEMA, Eurocode, Multi-linear hinge properties RC, Steel, SRC, Masonry material types Boundary Nonlinear Time History Analysis Damper, Isolator, Gap, Hook Inelastic Time History Analysis Other Analysis Unknown Forces by Optimization Moving load analysis Settlement analysis 45
m Results
midas Gen Introduction
Displacement Contour
46
m Results
midas Gen Introduction
Module 2 Module 1
Module 3 47
m Results
midas Gen Introduction
48
m Design
midas Gen Introduction
ACI318 Eurocode 2, Eurocode 8 BS8110 IS:456 & IS:13920 CSA-A23.3 GB50010 AIJ-WSD TWN-USD AIK-USD, WSD KSCE-USD KCI-USD Slab Design Eurocode 2 ACI 318
AISC-LRFD AISC-ASD AISI-CFSD Eurocode 3 BS5950 IS:800 (1984 & 2007) CSA-S16-01 GBJ17, GB50017 AIJ-ASD TWN-ASD, LSD AIK-ASD, LSD, CFSD KSCE-ASD KSSC-ASD
SSRC79 JGJ138 CECS28 AIJ-SRC TWN-SRC AIK-SRC KSSC-CFT Footing Design ACI318 BS8110
49
m Design
midas Gen Introduction
Material DB
Steel Material DB
Section DB
Load
Pushover Analysis
RC Pushover Steel Pushover Load Combination Concrete Frame Design (ULS & SLS)
Design
Concrete Capacity Design Steel Frame Design (ULS & SLS) Slab/Wall Design (ULS & SLS)
50
m Design
midas Gen Introduction
Wall design
51
The wizard readily allows us to define the timing of elements created and loadings applied in the construction stages during the erection of a building. You may find it more convenient to first click the [Automatic Generation] button to define the basic construction stages and modify them as necessary.
52
Define an analytical model for each construction stage by assigning activated or inactivated se ctions corresponding to each construction stage of a composite section. By using Composite Section for Construction Stage, we can consider the construction sequence with creep and shrinkage effect.
53
Specific stiffness of specific member types may be reduced such as the case where the flexural stiffness of lintel beams and walls may require reduction to reflect cracked sections of concrete. Section stiffness scale factors can be included in boundary groups for construction stage analysis. The scale factors are also applied to composite sections for construction stages
54
Point Spring Support (Linear, Comp.-only, Tens.-only, and Multi-linear type) Surface Spring Support (Nodal Spring, and Distributed Spring) Springs can be activated / deactivated during construction stage analysis.
55
Tendon Loss
Pre-stress load can be considered in construction stage analysis. Tendon primary / secondary forces are provided with pre-stress loss graph
56
m Project Applications
midas Gen Introduction
CS:30
Height No. of floors Location Function / Usage Designer Architect General Contractor
705 m 160 Dubai, United Arab Emirates Office Building & Residential Building Adrian D. Smith Skidmore, Owings & Merrill Samsung Development 57
overview
m Project Applications
midas Gen Introduction
Area No. of floors Location Function / Usage Structure Type Foundation Type Lateral load resisting system
39,600 m2 36 Seoul, Korea Office Building Composite Structure Mat Foundation RC Core + Steel + RC Composite Frame 58
overview
m Project Applications
midas Gen Introduction
Height No. of floors Location Function / Usage Structure Type Architect Contractor
345m 70 fl., 49 fl. Hanoi, Vietnam Hotel, Office, and Residential building Reinforced Concrete Structure Heerim, Samoo, Aum & Lee, Hellmuth Obata + Kassabaum Keangnam 59
overview
m Project Applications
midas Gen Introduction
60
m Project Applications
midas Gen Introduction
61
m Project Applications
midas Gen Introduction
62
m Project Applications
midas Gen Introduction
63
ColumnShortening
Thank You!
http://en.midasuser.com/ esupport@midasuser.com 64