KHADI & VILLAGE INDUSTRIES COMMISSION PROJECT PROFILE FOR GRAMODYOG ROZGAR YOJANA TINY UNIT FOR PLASTIC BOTTLES
Since the aerated water (cold drinks) and mineral water industries have increased manifold. The demand for the plastic bottles have increased considerably. A simple blow mould machine which can be easily operated, generate sufficient profit. Not only cold drinks, mineral water, but oils, fruit, syrups and variety of industries are using bottles as packing material. The demand for the bottles are increasing day-by-day. 1. Name of the Product 2. Project Cost (a) Capital Expenditure Land Building Shed 600 sq.ft. Equipment (Moulding M/c, Handling tool, Furnace, etc.) Total Capital Expenditure (b) Working Capital TOTAL PROJECT COST : : : : : Own Rs. Rs. 120000.00 280000.00 Plastic Bottles

: : :

Rs. Rs. Rs.

400000.00 149000.00 549000.00

3. Estimated Annual Production of Plastic Bottles : (Value in 000) Sl. No. 1. Particulars Plastic Bottles Capacity 250000.00 Bottles 250000.00 Bottles : : : 125 Rs. Rs. Rs. Rate Total Value 749.00

TOTAL

749.00

4. 5. 6.

Raw Material Labels and Packing Material Wages (Skilled & Unskilled)

400000.00 2000.00 120000.00

7. 8. 9. 10. 11. 12. 13.

Salaries Administrative Expenses Overheads Miscellaneous Expenses Depreciation Insurance Interest (As per the PLR) (a) Capital Expenditure Loan (b) Working Capital Loan Total Interest

: : : : : : : : :

Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

72000.00 25000.00 50000.00 5000.00 34000.00 4000.00 52000.00 19370.00 71370.00

14.

Working Capital Requirement Fixed Cost Variable Cost Requirement of Working Capital per Cycle : : : Rs. Rs. Rs. 158000.00 591370.00 149874.00

15. Sl. No. 1. 2. 3. 4. 5. 6.

Estimated Cost Analysis Particulars Capacity Utilization (Rs. in 000) 100% Fixed Cost Variable Cost Cost of Production Projected Sales Gross Surplus Expected Net Surplus 158.00 591.00 749.00 900.00 151.00 117.00 60% 94.80 354.60 449.40 540.00 90.60 57.00 70% 110.60 413.70 524.30 630.00 105.70 72.00 80% 126.40 472.80 599.20 720.00 120.80 87.00

Note: 1. All figures mentioned above are only indicative and may vary from place to place. 2. If the investment on Building is replaced by Rental Premises(a) (b) (c) Total Cost of Project will be reduced. Profitability will be increased. Interest on Capital Expenditure will be reduced.