Sie sind auf Seite 1von 6

PROJECT

CONTRACTOR
CLIENT

: DESIGN AND BUILD MAKMAL SAINTIFIK DAN MAKMAL KESIHATAN AWAM


: UNICORP SENDIRIAN BERHAD
: MINISTRY OF HEALTH, BRUNEI DARUSSALAM

Planned
Actual

FINANCIAL S-CURVE (PERIOD: 20 MONTHS)


ITEM

ACTIVITIES

No. of days

Per Month

MONTHS

AMOUNT
Mar

1.0

PRELIMINARIES

2.0

DESIGN, PRESENTATION & APPROVAL

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

15,000.00

15,000.00

15,000.00

15,000.00

15,000.00

15,000.00

15,000.00

15,000.00

15,000.00

15,000.00

15,000.00

15,000.00

15,000.00

15,000.00

15,000.00

15,000.00

15,000.00

510

15,000.00

300,000.00

15,000.00

15,000.00

15,000.00

90

133,333.33

400,000.00

133,333.33

133,333.33

133,333.33

90

40,370.67

121,112.00

40,370.67

40,370.67

40,370.67

3.2. Foundation

165

36,259.75

145,039.00

18,129.88

36,259.75

36,259.75

36,259.75

18,129.88

3.3. Column Stump

135

2,515.50

10,062.00

2,515.50

2,515.50

2,515.50

2,515.50

3.4. Ground Beam

127

7,867.50

31,470.00

3,933.75

7,867.50

7,867.50

7,867.50

3,933.75

3.5. Ground Slab

122

21,649.00

64,947.00

10,824.50

21,649.00

21,649.00

10,824.50

4.1. Frame

250

14,277.50

114,220.00

14,277.50

14,277.50

14,277.50

14,277.50

14,277.50

14,277.50

14,277.50

14,277.50

4.2. Upper Floor Slab

290

34,142.20

341,422.00

34,142.20

34,142.20

34,142.20

34,142.20

34,142.20

34,142.20

34,142.20

34,142.20

34,142.20

34,142.20

4.3. Roof Beam

210

3,376.80

16,884.00

3,376.80

3,376.80

3,376.80

3,376.80

3,376.80

4.4. Roof Trusses and Sheeting

120

21,720.13

86,880.50

21,720.13

21,720.13

21,720.13

4.5. Staircase

110

8,013.25

32,053.00

4.6. External Walls

270

11,146.89

100,322.00

4.7. Internal Walls

255

29,255.56

263,300.00

5.0

PERIMETER DRAIN& SUNDRIES

152

17,875.00

89,375.00

6.0

FINISHES
6.1. Doors & Windows

160

43,482.00

217,410.00

6.2. Internal Wall Finishes

223

12,228.57

85,600.00

6.3. Internal Floor Finishes

210

30,121.14

210,848.00

6.4. Internal Ceiling Finishes

120

14,181.38

56,725.50

6.5. External Wall Finishes

300

13,791.70

137,917.00

73

4,400.00

13,200.00

60

14,006.30

140,063.00

BUILDING WORKS
3.0

SUBSTRUCTURE
3.1 . Piling Works

4.0

SUPERSTRUCTURE

6.7. External Ceiling Finishes


7.0

8,013.25

8,013.25

5,573.44 11.146.89

8,013.25

21,720.13

8,013.25

11,146.89

11,146.89

11,146.89

11,146.89

11,146.89

11,146.89

11,146.89

5,573.44

29,255.56

29,255.56

29,255.56

29,255.56

29,255.56

29,255.56

29,255.56

29,255.56

29,255.56

17,875.00

17,875.00

17,875.00

17,875.00

43,482.00

43,482.00

43,482.00

43,482.00

43,482.00

12,228.57

13,791.70

17,875.00

12,228.57

12,228.57

12,228.57

12,228.57

12,228.57

12,228.57

30,121.14

30,121.14

30,121.14

30,121.14

30,121.14

30,121.14

30,121.14

14,181.38

14,181.38

14,181.38

14,181.38

13,791.70

13,791.70

13,791.70

13,791.70

13,791.70

13,791.70

2,200.00

4,400.00

4,400.00

2,200.00

14,006.30

14,006.30

14,006.30

14,006.30

14,006.30

27,770.25

27,770.25

13,791.70

13,791.70

13,791.70

SERVICES
7.1. Sanitary Appliances/Plumbing Works

14,006.30

14,006.30

14,006.30

14,006.30

14,006.30

3,026.33

3,026.33

3,026.33

3,026.33

3,026.33

61,537.50

61,537.50

61,537.50

61,537.50

6,265.00

6,265.00

6,265.00

GENERATOR AND WATER TANK


9.0

SUBSTRUCTURE

120

14,995.00

59,980.00

10.0

SUPERSTRUCTURE/FINISHES

180

3,026.33

18,158.00

11.0

LOOSE FURNITURE
120

61,537.50

246,150.00

90

6,265.00

25,060.00

30

130,682.00

1,045,456.00

14.1. Main and General items

510

27,770.25

444,324.00

27,770.25

27,770.25

27,770.25

27,770.25

14.2. Electrical Installation

240

6,352.54

82,583.00

6,352.54

6,352.54

6,352.54

14.3. Telephone System Installation

210

9,200.71

128,810.00

9,200.71

9,200.71

9,200.71

14.4. Air-Conditioning System

225

101,811.43

712,680.00

14.5. Testing and Commissioning

210

15.0

LABORATORY EQUIPMENTS

240

205,295.78

1,847,662.00

16.0

TIDY UP AND HANDOVER


TOTAL AMOUNT

150

12.1 Loose Furniture, High and low cabinets


11.2Vertical Blinds and Signages
12.0

14,995.00

14,995.00

14,995.00
3,026.33

6,265.00

FURNISHING
12.1.Lab Benches

14.0

14,995.00

130,682.00

130,682.00

130,682.00

130,682.00

130,682.00

130,682.00

130,682.00

130,682.00

27,770.25

27,770.25

27,770.25

27,770.25

27,770.25

27,770.25

27,770.25

27,770.25

27,770.25

6,352.54

6,352.54

6,352.54

6,352.54

6,352.54

6,352.54

6,352.54

6,352.54

6,352.54

6,352.54

9,200.71

9,200.71

9,200.71

9,200.71

9,200.71

9,200.71

9,200.71

9,200.71

9,200.71

9,200.71

9,200.71

101,811.43

101,811.43

101,811.43

101,811.43

101,811.43

101,811.43

101,811.43

205,295.78

205,295.78

205,295.78

205,295.78

205,295.78

205,295.78

205,295.78

205,295.78

205,295.78

556,297.47
2,534,538.95
7.00%
33.00%
308,652.57
4,793,542.29
4.07%
63.16%

661,485.70
3,196,024.65
9.00%
42.00%
704,362.32
5,497,904.61
9.28%
72.44%

774,518.45
3,970,543.10
10.00%
52.00%
639,319.39
6,137,224.00
8.42%
80.86%

812,269.20
4,782,812.30
11.00%
63.00%
399,850.30
6,537,074.30
5.27%
86.13%

803,669.42
5,586,481.72
11.00%
74.00%

800,295.98
6,386,777.70
11.00%
84.00%

524,920.82
6,911,698.52
7.00%
91.00%

399,950.46
7,311,648.98
5.00%
96.00%

278,064.03
7,589,713.01
4.00%
100.00%

MECHANICAL AND ELECTRICAL INSTALLATION


27,770.25

7,589,713.00
AMOUNT

PLANNED
%
AMOUNT
ACTUAL
%

MONTHLY
CUMULATIVE
MONTHLY
CUMULATIVE
MONTHLY
CUMULATIVE
MONTHLY
CUMULATIVE

148,333.33
148,333.33
2.00%
2.00%
198,090.00
198,090.00
2.61%
2.61%

148,333.33
296,666.67
2.00%
4.00%
125,935.00
324,025.00
1.66%
4.27%

148,333.33
445,000.00
2.00%
6.00%
258,702.69
582,727.69
3.41%
7.68%

73,500.54
518,500.54
1.00%
7.00%
132,794.93
715,522.62
1.75%
9.43%

141,403.17
659,903.71
2.00%
9.00%
428,080.39
1,143,603.01
5.64%
15.07%

156,161.42
816,065.13
2.00%
11.00%
265,369.25
1,408,972.26
3.50%
18.56%

169,474.44
985,539.57
2.00%
13.00%
396,508.39
1,805,480.65
5.22%
23.79%

183,046.97
1,168,586.54
2.00%
15.00%
326,432.64
2,131,913.29
4.30%
28.09%

184,912.15
1,353,498.69
2.00%
18.00%
540,986.81
2,672,900.10
7.13%
35.22%

295,848.98
1,649,347.67
4.00%
22.00%
626,790.72
3,299,690.82
8.26%
43.48%

328,893.80
1,978,241.47
4.00%
26.00%
1,185,198.90
4,484,889.72
15.62%
59.09%

Page 8

PROJECT
CONTRACTOR
CLIENT

: DESIGN AND BUILD MAKMAL SAINTIFIK DAN MAKMAL KESIHATAN AWAM


: UNICORP SENDIRIAN BERHAD
: MINISTRY OF HEALTH, BRUNEI DARUSSALAM

Planned

Actual
PHYSICAL S-CURVE (PERIOD: 20 MONTHS)
ITEM

ACTIVITIES

No. of days

MONTHS (Planned)

AMOUNT
Mar

1.0
2.0

PRELIMINARIES

510

DESIGN, PRESENTATION & APPROVAL

8.01%

Apr

25.50
30.00

May

25.50
30.00

Jun

25.50

Jul

25.50

Aug

25.50

Sep

25.50

Oct

25.50

Nov

25.50

Dec

25.50

Jan

25.50

Feb

25.50

Mar

25.50

Apr

25.50

May

25.50

Jun

25.50

Jul

25.50

Aug

25.50

Sep

25.50

Oct

25.50

25.50

100%

90

1.41%

30.00

90

1.41%

30.00

30.00

30.00

3.2. Foundation

165

2.59%

33.00

33.00

33.00

33.00

33.00

3.3. Column Stump

135

2.12%

27.00

27.00

27.00

27.00

27.00

3.4. Ground Beam

127

1.99%

25.40

25.40

25.40

25.40

25.40

3.5. Ground Slab

122

1.92%

30.50

30.50

30.50

30.50

BUILDING WORKS
3.0

SUBSTRUCTURE
3.1 . Piling Works

4.0

90%

80%

SUPERSTRUCTURE
4.1. Frame

250

3.93%

4.2. Upper Floor Slab

290

4.55%

4.3. Roof Beam

210

3.30%

4.4. Roof Trusses and Sheeting

120

1.88%

4.5. Staircase

110

1.73%

13.75

13.75

13.75

13.75

13.75

13.75

13.75

13.75

4.6. External Walls

270

4.24%

27.00

27.00

27.00

27.00

27.00

27.00

27.00

4.7. Internal Walls

255

4.01%

25.50

25.50

25.50

25.50

25.50

5.0

PERIMETER DRAIN& SUNDRIES

152

2.39%

6.0

FINISHES
6.1. Doors & Windows

160

2.51%

6.2. Internal Wall Finishes

223

3.50%

6.3. Internal Floor Finishes

210

3.30%

6.4. Internal Ceiling Finishes

120

1.88%

6.5. External Wall Finishes

300

4.71%

73

1.15%

31.25

31.25

31.25

31.25

31.25

31.25

31.25

31.25

29.00

29.00

29.00

29.00

29.00

29.00

29.00

29.00

29.00

29.00

42.00

42.00

42.00

42.00

42.00

24.00

24.00

24.00

24.00

27.00

27.00

27.00

25.50

25.50

25.50

25.50

25.50

30.40

30.40

30.40

30.40

30.40

22.86

22.86

31.86

24.00

22.86

22.86

22.86

22.86

22.86

31.86

31.86

31.86

31.86

31.86

31.86

30.00

30.00

30.00

30.00

30.00

30.00

30.00

30.00

30.00

30.00

30.00

30.00

30.00

30.00

30.00

30.00

18.25

18.25

18.25

70%

60%

50%

6.7. External Ceiling Finishes

30.00

30.00

30.00

30.00

30.00
18.25

40%
7.0

SERVICES
7.1. Sanitary Appliances/Plumbing Works

60

0.94%

6.00

6.00

6.00

6.00

6.00

6.00

6.00

30.00

30.00

30.00

30.00

30.00

30.00

30.00

30.00

30.00

22.50

22.50

22.50

6.00

6.00

6.00

GENERATOR AND WATER TANK


9.0

SUBSTRUCTURE

120

1.88%

10.0

SUPERSTRUCTURE/FINISHES

180

2.83%

11.0

LOOSE FURNITURE
120

1.88%

90

1.41%

30

0.47%

14.1. Main and General items

510

8.01%

30.00

30.00

30.00

30.00

30.00

14.2. Electrical Installation

240

3.77%

16.00

16.00

16.00

16.00

14.3. Telephone System Installation

210

3.30%

15.00

15.00

15.00

14.4. Air-Conditioning System

225

3.53%

14.5. Testing and Commissioning

210

3.30%

15.0

LABORATORY EQUIPMENTS

240

3.77%

16.0

TIDY UP AND HANDOVER


TOTAL AMOUNT

150

2.36%

12.1 Loose Furniture, High and low cabinets


11.2Vertical Blinds and Signages
12.0

30.00

30.00

30.00
30.00

30%

22.50

20%

FURNISHING
12.1.Lab Benches

14.0

30.00

3.75

3.75

3.75

3.75

3.75

3.75

3.75

3.75

30.00

30.00

30.00

30.00

30.00

30.00

30.00

30.00

30.00

30.00

16.00

16.00

16.00

16.00

16.00

16.00

16.00

16.00

16.00

16.00

16.00

15.00

15.00

15.00

15.00

15.00

15.00

15.00

15.00

15.00

15.00

15.00

32.14

32.14

32.14

32.14

32.14

32.14

32.14

30.00

30.00

30.00

30.00

30.00

30.00

26.67

26.67

26.67

26.67

26.67

26.67

25.00

25.00

25.00

25.00

25.00

MECHANICAL AND ELECTRICAL INSTALLATION

PLANNED
ACTUAL

26.67

26.67

30.00

30.00

10%

30.00

0%

26.67
25.00

100.00%

%
%

MONTHLY

0.87%

0.87%

0.87%

2.11%

3.17%

3.65%

4.78%

5.24%

5.12%

4.35%

4.94%

5.83%

7.35%

8.30%

9.66%

9.19%

9.05%

6.91%

4.72%

3.01%

CUMULATIVE

0.87%

1.74%

2.62%

4.73%

7.90%

11.55%

16.33%

21.57%

26.68%

31.03%

35.97%

41.80%

49.16%

57.46%

67.12%

76.31%

85.36%

92.27%

96.99%

100.00%

MONTHLY

2.87%

2.87%

6.04%

6.33%

8.20%

4.75%

7.00%

5.00%

6.80%

8.00%

5.00%

5.00%

5.10%

5.00%

5.00%

CUMULATIVE

2.87%

5.75%

11.79%

18.12%

26.32%

31.07%

38.07%

43.07%

49.87%

57.87%

62.87%

67.87%

72.97%

77.97%

82.97%

Page 8

PROJECT
CONTRACTOR
CLIENT

: DESIGN AND BUILD MAKMAL SAINTIFIK DAN MAKMAL KESIHATAN AWAM


: UNICORP SENDIRIAN BERHAD
: MINISTRY OF HEALTH, BRUNEI DARUSSALAM
PROGRAMME OF WORKS
(PERIOD: 20 MONTHS)

ITEM

ACTIVITIES

2011

No. of days
Mar

1.0

PRELIMINARIES

2.0

DESIGN, PRESENTATION & APPROVAL

Apr

May

510

15,000.00

15,000.00

15,000.00

90

133,333.33

133,333.33

133,333.33

Jun

Jul

2012
Aug

15,000.00

15,000.00

15,000.00

90

40,370.67

40,370.67

40,370.67

3.2. Foundation

165

18,129.88

36,259.75

3.3. Column Stump

135

3.4. Ground Beam

127

3.5. Ground Slab

122

Sep

Oct

Nov

15,000.00

15,000.00

15,000.00

36,259.75

36,259.75

18,129.88

2,515.50

2,515.50

2,515.50

2,515.50

3,933.75

7,867.50

7,867.50

7,867.50

3,933.75

10,824.50

21,649.00

21,649.00

10,824.50

14,277.50

14,277.50

34,142.20

Dec

Jan

Feb

Mar

Apr

15,000.00

15,000.00

15,000.00

15,000.00

15,000.00

14,277.50

14,277.50

14,277.50

14,277.50

14,277.50

14,277.50

34,142.20

34,142.20

34,142.20

34,142.20

34,142.20

3,376.80

May

Jun

Jul

15,000.00

15,000.00

15,000.00

34,142.20

34,142.20

34,142.20

34,142.20

3,376.80

3,376.80

3,376.80

3,376.80

21,720.13

21,720.13

21,720.13

Aug
15,000.00

Sep
15,000.00

Oct
15,000.00

BUILDING WORKS
3.0

SUBSTRUCTURE
3.1 . Piling Works

4.0

SUPERSTRUCTURE
4.1. Frame

250

4.2. Upper Floor Slab

290

4.3. Roof Beam

210

4.4. Roof Trusses and Sheeting

120

4.5. Staircase

110

8,013.25

4.6. External Walls

270

5,573.44 11.146.89

4.7. Internal Walls

255

5.0

PERIMETER DRAIN& SUNDRIES

152

6.0

FINISHES
6.1. Doors & Windows

160

6.2. Internal Wall Finishes

223

6.3. Internal Floor Finishes

210

6.4. Internal Ceiling Finishes

120

6.5. External Wall Finishes

300

6.7. External Ceiling Finishes

7.0

8,013.25

8,013.25

21,720.13

8,013.25

11,146.89

11,146.89

11,146.89

11,146.89

11,146.89

11,146.89

11,146.89

5,573.44

29,255.56

29,255.56

29,255.56

29,255.56

29,255.56

29,255.56

29,255.56

29,255.56

29,255.56

17,875.00

17,875.00

17,875.00

17,875.00

43,482.00

43,482.00

43,482.00

43,482.00

43,482.00

12,228.57

13,791.70

17,875.00

12,228.57

12,228.57

12,228.57

12,228.57

12,228.57

12,228.57

30,121.14

30,121.14

30,121.14

30,121.14

30,121.14

30,121.14

30,121.14

14,181.38

14,181.38

14,181.38

14,181.38

13,791.70

13,791.70

13,791.70

13,791.70

13,791.70

13,791.70

2,200.00

4,400.00

4,400.00

2,200.00

14,006.30

14,006.30

14,006.30

14,006.30

14,006.30

27,770.25

27,770.25

13,791.70

13,791.70

13,791.70

73

SERVICES
7.1. Sanitary Appliances/Plumbing Works

60

14,006.30

14,006.30

14,006.30

14,006.30

14,006.30

3,026.33

3,026.33

3,026.33

3,026.33

3,026.33

61,537.50

61,537.50

61,537.50

61,537.50

6,265.00

6,265.00

6,265.00

GENERATOR AND WATER TANK


SUBSTRUCTURE

120

10.0

SUPERSTRUCTURE/FINISHES

180

11.0

LOOSE FURNITURE
11.1 Loose Furniture, High and low cabinets

14,995.00

14,995.00

3,026.33

90

6,265.00

FURNISHING
12.1.Lab Benches

14.0

14,995.00

120

11.2 Vertical Blinds and Signages


12.0

14,995.00

Axis Title

9.0

30

130,682.00

130,682.00

130,682.00

130,682.00

130,682.00

130,682.00

130,682.00

130,682.00

MECHANICAL & ELECTRICAL INSTALLATION


14.1. Main and General items

510

27,770.25

27,770.25

27,770.25

27,770.25

27,770.25

27,770.25

27,770.25

27,770.25

27,770.25

27,770.25

27,770.25

27,770.25

27,770.25

14.2. Electrical Installation

240

6,352.54

6,352.54

6,352.54

6,352.54

6,352.54

6,352.54

6,352.54

6,352.54

6,352.54

6,352.54

6,352.54

6,352.54

6,352.54

14.3. Telephone System Installation

210

9,200.71

9,200.71

9,200.71

9,200.71

9,200.71

9,200.71

9,200.71

9,200.71

9,200.71

9,200.71

9,200.71

9,200.71

9,200.71

9,200.71

14.4. Air-Conditioning System

225

101,811.43

101,811.43

101,811.43

101,811.43

101,811.43

101,811.43

101,811.43

205,295.78

205,295.78

205,295.78

205,295.78

205,295.78

205,295.78

205,295.78

205,295.78

205,295.78

556,297.47
2,534,538.95
7%
33%

661,485.70
3,196,024.65
9%
42%

774,518.45
3,970,543.10
10%
52%

812,269.20
4,782,812.30
11%
63%

803,669.42
5,586,481.72
11%
74%

800,295.98
6,386,777.70
11%
84%

524,920.82
6,911,698.52
7%
91%

399,950.46
7,311,648.98
5%
96%

278,064.03
7,589,713.01
4%
100%

14.5. Testing and Comissioning

210

15.0

LABORATORY EQUIPMENTS

240

16.0

TIDY UP AND HANDOVER

150

27,770.25

TOTAL AMOUNT
AMOUNT
PLANNED
%

148,333.33
148,333.33
2%
2%

148,333.33
296,666.67
2%
4%

148,333.33
445,000.00
2%
6%

73,500.54
518,500.54
1%
7%

141,403.17
659,903.71
2%
9%

156,161.42
816,065.13
2%
11%

169,474.44
985,539.57
2%
13%

183,046.97
1,168,586.54
2%
15%

184,912.15
1,353,498.69
2%
18%

295,848.98
1,649,347.67
4%
22%

328,893.80
1,978,241.47
4%
26%

0.4205
0.995
1.92
0.49125
0.379167
1.128
0.801
0.377
1.673

0.379167 4.170833
0.56875
1.1375

Physical Progress as August 30, 2011

Frame
Preliminaries
Upper Floor Slab
Main and General
Items
Substructures
Electrival
Perimeter drains
& sundries
Airconditioning system

Frame
3.93
8.01
4.55

0.49125

1.47375
0.4005
0.56875 1.327083

8.01
1.88
3.77
2.39

0.801
0.188 70 percent
0.377 20 percent

3.53

0.1765
19.52
4.743833

Physical Progress as September 30, 2011

Frame
Preliminaries
Upper Floor Slab
Staircase
External Walls
Internal Walls
Plumbing

3.93
8.01
4.55
1.73
4.24
4.01
0.94

Main and General


Items
Substructures
Electrival
Perimeter drains
& sundries

8.01
1.88
3.77
2.39

0.393
0.56875

1.179
0.4005
1.70625
1.038
0.1272
0.4812
0.188

0.801
0.188 70 percent
0.377 20 percent

Airconditioning system

3.53

0.706

Total

7.19215
Physical Progress as October 30, 2011

Frame
Preliminaries
Upper Floor Slab
Staircase
External Walls
Internal Walls
Plumbing

3.93
8.01
4.55
1.73
4.24
4.01
0.94

Main and General


Items
Substructures
Electrival
Perimeter drains
& sundries
Airconditioning system
Total

0.393
0.56875

1.179
0.4005
2.3745
1.038
0.1272
0.4812
0.188

8.01
1.88
3.77
2.39

0.801
0.188 70 percent
0.377 20 percent

3.53

0.706
7.8604

Das könnte Ihnen auch gefallen