Engineering Procedure

SAEP-381 Project Quality Issues Escalation Process 17 March 2013 Document Responsibility: Inspection Engineering Standards Committee

Saudi Aramco DeskTop Standards


Table of Contents 1 2 3 4 5 6 7 8 9 Scope... 2 Purpose 2 Conflicts and Deviations 2 Applicable Documents.. 3 Definitions 3 Violations Definitions. 4 Instructions.. 5 Responsibilities.. 8 Cancelled Quality Notifications.. 10

Appendix A - Quality Issues Reporting Process 11 Appendix B - Contractors Internal NCR. 12 Appendix C - Quality Issues Escalation Matrix.. 13 Appendix D - Examples of Violations and Escalation Steps... 14 Appendix E - Responsibilities for Quality Issue Notification... 16 Appendix F - Index.... 17

Previous Issue: 28 January 2012 Next Planned Update: 28 January 2017 Revised paragraphs are indicated in the right margin Primary contact: Kakpovbia, Anthony Eyankwiere on +966-3-8801772
CopyrightSaudi Aramco 2013. All rights reserved.

Page 1 of 17

Document Responsibility: Inspection Engineering Standards Committee SAEP-381 Issue Date: 17 March 2013 Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

Scope 1.1 1.2 This Procedure establishes instructions for escalation of unresolved quality issues in Saudi Aramco projects including delinquent quality concern notifications. This SAEP does not apply to:

Escalation of non-conformities identified by Operation Inspection Division (OID) during assessments of Operation Inspection Units (OIUs) in operating facilities. Deficiencies noted during internal assessments by the Inspection Department. Deficiencies noted during Health Checks conducted by APMID for Asset Performance Management (APM).

Purpose 2.1 The purpose of this SAEP is to: 2.1.1 Implement a consistent method for escalating quality issues including Logbook Entries (LBEs), Non-Conformance Reports (NCRs), Worksheets (WSs) and Delinquent Worksheets (DWSs), as defined in Appendix A, Quality Issues Reporting Process. Clearly define the corporate process for project quality issue escalation including its documentation, requirements and definition of violation categories, systems and procedures. Ensure roles and responsibilities for project quality issue escalation are well defined and auditable.

2.1.2

2.1.3 2.2

The intent of quality issue notification is to report and record quality or technical deficiencies, determine the root cause of the problem, record the actions taken to correct non-conformities, avoid recurrence and enhance overall project quality.

Conflicts and Deviations 3.1 Any conflict between this procedure and other applicable Mandatory Saudi Aramco Engineering Requirement (MSAER) shall be resolved in writing through the Chairman, Inspection Engineering Standards Committee (IESC). Direct all requests to deviate from this procedure in writing to the Manager, Inspection Department of Saudi Aramco, Dhahran.

3.2

Page 2 of 17

Document Responsibility: Inspection Engineering Standards Committee SAEP-381 Issue Date: 17 March 2013 Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

Applicable Documents The applicable requirements in the latest edition of the following Saudi Aramco Engineering Procedures, Schedule Q and General Instructions (GIs) shall be considered an integral part of this procedure. Saudi Aramco Engineering Procedures SAEP-301 SAEP-302 SAEP-379 SAEP-380 SAEP-1150 SAEP-1151 Contract Schedule Q Instruction for Establishing and Maintaining Saudi Aramco Engineering Requirements Instructions for Obtaining a Waiver of a Mandatory Saudi Aramco Engineering Requirement Quality Issues Notification Equipment Deficiency Report Inspection Coverage on Projects Inspection Requirements for Contractor Procured Materials and Equipment Quality Requirements

Saudi Aramco General Instruction GI-0400.001 GI-0002.710 Quality Management Roles and Responsibilities Mechanical Completion and Performance Acceptance of Facilities

Definitions ACD: Agreed Completion Date APM: Asset Performance Management APMID: Asset Performance Management Integration Division DWS: DELINQUENT WORKSHEET - Mechanism to escalate unresolved Worksheets CQP: Contractor Quality Personnel CQR: Contractor Quality Representative INCR: Internal Non Conformance Report (Issued by Contractor) LBE: Logbook Entries (First level of reporting quality deficiency using Manual Logbook or the Quality Management Information System, QMIS)
Page 3 of 17

Document Responsibility: Inspection Engineering Standards Committee SAEP-381 Issue Date: 17 March 2013 Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

MCC: Mechanical Completion Certificate MPCS: Mechanical Performance and Close-out System MSAER: Mandatory Saudi Aramco Engineering Requirements Non-Conformities Escalation: A structured mechanism to progressively escalate pending quality and technical deficiencies to the concerned management. NCR: Non Conformance Report (Issued by Saudi Aramco through SAP QM). Project Quality Manager (PQM): The Senior Inspection Representative responsible for coordinating all inspection requirements on behalf of Inspection Department with SAPMT throughout all project phases, from Project Proposal up to Mechanical completion. QMIS: Quality Management Information System (also known as electronic Inspection Logbook). Repeat Violation: A non-compliance of the same MSAER, project specifications or standard drawings in the same activity area, that occurred more than once within six (6) months. SAPMT: Saudi Aramco Project Management Team SAP QM: Systems, Applications and Products in Data Processing-Quality Module Technical Deficiencies: Non-compliance to any MSAER or project specifications Worksheet: Mechanism for reporting major violations or escalating pending valid NCRs as stipulated in this Procedure. 6 Violations Definitions MAJOR (If any one of the following applies) 1) 2) Violations of company standards including GIs that put the quality and integrity of the facility including its workers and equipment at risk. Actions that violate the Corporate values by submitting forged items & counterfeit materials.

MODERATE (If any one of the following applies) 1) Any violation to MSAER, project specifications and approved IFC drawings that if the next phase of work (critical path) is continued without correcting the violation,

Page 4 of 17

Document Responsibility: Inspection Engineering Standards Committee SAEP-381 Issue Date: 17 March 2013 Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

the structural integrity of the next phase will be jeopardized. Such violation if not corrected in a timely manner will lead to more severe damage or complexity. 2) Any violation to Schedule Q.
Commentary Note: Minor violations related to Schedule Q listed in Appendix D are excluded from this definition.

3)

If the violation will be categorized YES item as defined in GI-0002.710 during the partial MCC stage.

MINOR (If any one of the following applies) 1) 2) Any violation to SAES, SAMSS, project specifications and approved IFC drawings but the next phase of work is not dependent on the correction of the violation. If the violation will be categorized as NO item as defined in GI-0002.710 during the partial MCC stage.

Instructions 7.1 Quality Issues Notification 7.1.1 Quality or technical deficiencies shall be reported in a timely manner through QMIS for LBE, or SAP QM (NCR or WS) depending on the identified violation as defined in Section 6. Potential non-conforming materials, products or work shall be proactively highlighted through the QMIS to avoid re-work. A letter of concern signed by the PID Superintendent shall be addressed to the Department Head of the MCC/PMCC Chairman whenever MCC/PMCCs are approved in the MPCS without ID signature due to converted and unresolved YES items for other Organizations. This letter shall be copied to ID and PMT Department Managers. A letter of concern signed by the ID Manager shall also be addressed to the Manager of the MCC/PMCC Chairman whenever MCC/PMCCs are approved in the MPCS system and IDs YES items are converted to NO without obtaining IDs agreement. This letter shall be copied to Proponent VP, ES VP and PM VP. A letter of concern signed by the ES Chief Engineer shall be addressed to the Admin Area head of the MCC/PMCC Chairman whenever a Facility is commissioned without Inspection Departments
Page 5 of 17

7.1.2 7.1.3

7.1.4

7.1.5

Document Responsibility: Inspection Engineering Standards Committee SAEP-381 Issue Date: 17 March 2013 Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

review/signature on the MCC/PMCC. This letter shall be copied to Internal Auditing, ES VP and PM VP. 7.1.6 Starting a project which excludes ANY Mandatory Saudi Aramco Engineering Requirement (MSAER), without securing the required waiver approved by applicable management level authority shall be issued a Worksheet. Initiators, approvers and other interested parties of quality issue notifications shall be in accordance with Appendix E, Table of Responsibilities for Quality Issue Notification. Third Delinquent Worksheet (DWS3) shall be copied to Internal Auditing for their follow-up action.

7.1.7

7.1.8 7.2

Agreed Completion Date (ACD) for LBEs, NCRs and Worksheets 7.2.1 PID PQM, SAPMT Senior Project Engineer or Lead Project Engineer and the Contractor Quality Representative are responsible for determining the initial Agreed Completion Date (ACD) for LBEs, NCRs and Worksheets. When no agreement on the ACD of any type/category of Quality Notification could be reached, the ACD shall be decided mutually by the next level of authority from ID and PMT, depending on the Quality Notification category. If an extension of ACD is justified and mutually agreed by ID & PMT representatives, one-time basis approval of ACD extension is allowed. If no agreement of the new ACD is reached by the ID and PMT initiators and approvers, the ACD shall be established by the next higher signature level(s) per the below matrix.
Quality Notification Type Contractors Internal NCR Logbook Entry (LBE) NCR Worksheet ID Rep ID Field Supvr ID Field Supvr ID Unit Supervisor ID PQM PMT Rep PMT Project Engineer PMT Project Engineer PMT Sr. Project Engineer PMT Project Manager

7.2.2

7.2.3

In case a conflict on establishing the ACD continues, the PMT Department Manager shall make the final decision.

Page 6 of 17

Document Responsibility: Inspection Engineering Standards Committee SAEP-381 Issue Date: 17 March 2013 Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

7.3

Handling of Contractors Internal NCR 7.3.1 Saudi Aramco strongly encourages all Contractors to take advantage of all opportunities to enhance their quality management system implementation and to fully utilize their internal QA/QC system towards a high project quality delivery. ID shall initiate escalation if a Contractor does not act to correct quality/technical non compliances within the mutually agreed ACD. To encourage Contractors QC Team to implement their internal quality management system effectively, the Contractors recommended completion date shall be accepted, unless found unreasonable by PMT project engineer and the ID Field Supervisor. When the Contractors QC personnel report and document a quality non-compliance, ID shall follow the work process per Appendix B, Contractors Internal NCR. When an Internal NCR has been issued by the Contractors QC, Saudi Aramco quality notification shall be recorded by PID in the General Comments category of the QMIS, for the purpose of Lessons Learned collection. The QMIS entry shall be closed when the internal NCR is completed or when escalated to SA NCR due to non-compliance within the ACD.

7.3.2 7.3.3

7.3.4

7.3.5

7.4

Clarifications to Appendix D Examples of Violations and Escalation Steps 7.4.1 Clearance of Unavailability of approved Contractor QA Manager or Contractor QC Manager" in Appendix D shall be based on actual mobilization at the project site of the approved Contractor QA Manager or QC Manager and not just submission or approval of resumes. Absence of an already approved and mobilized Contractor QA/QC Manager, due to verified emergency leave could be exempted by the PQM provided that the leave of absence shall not be more than seven (7) calendar days without an approved replacement. Clearance of Insufficient QC Manpower (Deficiency > 10% of Plan) in Appendix D shall also be based on actual mobilization of the approved Contractor QC personnel at the project site, and not just submission or approval of resumes.

7.4.2

7.5

Non-Conformities Escalation Process 7.5.1 Escalation processes shall be in accordance with Appendix C, Quality Issues Escalation Matrix.
Page 7 of 17

Document Responsibility: Inspection Engineering Standards Committee SAEP-381 Issue Date: 17 March 2013 Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

7.5.2

Logbook Entries (LBEs) shall be made for deficiencies defined as Minor. LBEs shall be made through the QMIS or Manual logbook. (Manual logbook entry shall be done only in exceptional cases and shall have prior approval by the relevant Division Head.

7.5.3

Repeat of Moderate or Major violation within six (6) months will result to a Quality Notification starting at the next higher level of Violation Category and Notification. Repeat of a Minor violation due to negligence shall be considered as Moderate violation. Repeated Internal Non-Conformance Report (INCR) within six (6) months shall be, as in Appendix B, Contractors Internal NCR: 7.5.4.1 7.5.4.2 Escalated to SA NCR if the Contractor failed to Report the Repeated INCR Escalated to Violation-after-the-fact Entry in the QMIS if the contractor has detected and reported the Repeated INCR

7.5.4

7.5.5

Valid NCR shall be escalated to a Worksheet (WS) when any of the following applies: 7.5.5.1 7.5.5.2 Valid NCR is not corrected or completed on the ACD (including the extension period, if extension is approved) Valid NCR issued by Inspection Department is not approved by SAPMT within five (5) working days

7.5.6

A Worksheet that was not resolved on or before the ACD, including the approved extension period (if extension is approved), shall be escalated to Delinquent Worksheet, after discussing and notifying the relevant PMT representative. Once the project reaches its MCC stage, all open LBEs, NCRs, Worksheets and DWS shall be transferred to MPCS. Items required for start-up or impacting safety are to be marked as YES Items. All other items shall be designated as No Items.

7.5.7

Responsibilities 8.1 Project Inspection Division Head 8.1.1 Reviews and approves or rejects PMT request to extend ACD for Worksheets
Page 8 of 17

Document Responsibility: Inspection Engineering Standards Committee SAEP-381 Issue Date: 17 March 2013 Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

8.1.2 8.1.3 8.1.4 8.2

Approves Worksheets issued by the PQM/Sr. Supervisor Initiates issuance of Delinquent Worksheet (DWS1) Reviews and approves or rejects the deletion of SAP notifications

Project Quality Manager (PQM) or Senior Supervisor 8.2.1 8.2.2 8.2.3 8.2.4 8.2.5 PQM may initiate issuance of Non-Conformance Reports (NCRs) in lieu of Field Supervisor Initiates issuance of Worksheet (WS) Reviews and may grant one-time approval of ACD extension prior to escalation of valid NCR Decides cases of violations not clearly defined in Section 6 and not listed in Appendix D Examples of Violations and Escalation Steps Performs quality roles and responsibilities defined in this SAEP, GI-0400.001 Quality Management Roles and Responsibilities and GI-0002.710 Mechanical Completion and Performance Acceptance of Facilities

8.3

Project Inspector or Field Supervisor 8.3.1 8.3.2 Highlights to SAPMT any potential non-conforming material, product or work through the QMIS to avoid re-work. Reports in a timely manner any quality or technical deficiency through the QMIS or SAP QM (LBE or NCR) depending on the committed violations as defined in Section 6 and categorized in Appendix C, Quality Issues Escalation Matrix Field Supervisor may initiate issuance of Non-Conformance Reports (NCRs) in lieu of Project Quality Manager (PQM)

8.3.3 8.4

SAPMT 8.4.1 Ensures project full compliance with SAEP-302, Instructions for Obtaining a Waiver of a Mandatory Saudi Aramco Engineering Requirement Approves valid NCRs initiated by Inspection Department within five (5) working days

8.4.2

Page 9 of 17

Document Responsibility: Inspection Engineering Standards Committee SAEP-381 Issue Date: 17 March 2013 Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

8.4.3

Performs quality roles and responsibilities defined in this SAEP, GI-0400.001 Quality Management Roles and Responsibilities and GI-0002.710 Mechanical Completion and Performance Acceptance of Facilities

Cancelled Quality Notifications Submitted quality notifications in SAP QM shall not be marked for deletion without proper justification approved by PID Division Head. The approved justification shall be attached in the quality notification being marked for deletion.

28 January 2012 17 March 2013

Revision Summary New Saudi Aramco Engineering Procedure. Minor revision to provide clarification on selected sections.

Page 10 of 17

Document Responsibility: Inspection Engineering Standards Committee SAEP-381 Issue Date: 17 March 2013 Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

Appendix A - Quality Issues Reporting Process

Page 11 of 17

Document Responsibility: Inspection Engineering Standards Committee SAEP-381 Issue Date: 17 March 2013 Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

Appendix B Contractors Internal NCR


Contractors INCR

PID to Initially record INCR in the General Comments of QMIS, marked as For Info

Moderate Or Major Violation? Yes

No

Repeat Minor INCR? w/in 6 months

No

Yes

No

Repeat INCR? w/in 6 Months

No

One-time extension granted? Yes

No

Completed on ACD? Yes

Yes

No

Reported by Contractor? Yes

No

Completed on Extension Date?

Yes

Change QMIS entry to Violation-after-the fact

Completed on ACD? No One-time extension granted? No

Yes

Yes

Completed on Extension date?

Yes

No Escalate INCR into SA-NCR, then Close INCR & QMIS

Follow the Quality Issue Reporting Process

Close INCR & QMIS

Page 12 of 17

Document Responsibility: Inspection Engineering Standards Committee SAEP-381 Issue Date: 17 March 2013 Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

Appendix C - Quality Issues Escalation Matrix Violation Type Minor Moderate Major 1st Notification LBE NCR WS ESCALATION STAGES 2 3 4 WS DWS1 DWS2 DWS1 DWS2 DWS3 DWS2 DWS3 -

1 NCR WS DWS1

5 DWS3 -

Page 13 of 17

Document Responsibility: Inspection Engineering Standards Committee SAEP-381 Issue Date: 17 March 2013 Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

Appendix D - Examples of Violations and Escalation Steps


ESCALATION MATRIX S/N 1. Sample Violation Forged Quality Documents Procurement and/or Installation of counterfeit materials classified as inspectable per SAEP-1151 Note: For non-inspectable materials, PQM decides on the initial Violation Category Starting a project which excludes ANY Mandatory Saudi Aramco Engineering Requirement (MSAER), without securing the required waiver approved by applicable management level authority. Unavailability of approved Contractor QA Manager or Contractor QC Manager Commencing of Special Process activity as specified in Schedule Q without approved procedures/personnel Concrete or Asphalt placement without pre-approval of the batching plant or mix design Use of non-approved third party service providers Starting work without IFC Drawings or not submitting required Quality Documents as per Schedule Q Note: Categorization is PQM discretion Placing RVL/Inspectable materials and equipment with unapproved source Carrying out modification work on accepted systems (PROCESS-RELATED) without SA approval Preservation and Storage of equipment and materials classified as Inspectable per SAEP-1151 that are not in accordance with the approved quality plan and schedule Q Note: Categorization is PQM Discretion Contractors Internal NCR not resolved at the approved completion date Failure of the Contractor to control and implement the quality requirements of its batch plants, subcontractors and other service providers as required per Schedule Q. (e.g., Not assigning his own QC inspectors at the manufacturer and service provider locations per Schedule Q, and relying only on the In-House QC) Contractor failure to conduct complete quality system audits per Schedule Q requirements Recommended Phase for Proactive Notification Job X/Kick-off/Weekly QC Meetings Job X/Kick-off/Weekly QC Meetings Violation Category

Major

2.

Major

3.

Job X/Kick-off Meetings

Major

4. 5. 6. 7.

Job X/Kick-off Meetings/ Weekly QC Meetings Job X/Kick-off/Weekly QC Meetings Kick off Meetings/Weekly QC meetings Kick off Meetings/Weekly QC meetings Kick off Meetings/Weekly QC meetings Kick off Meetings/Weekly QC meetings Kick off Meetings/Weekly QC meetings

Moderate Moderate Moderate Moderate Moderate Minor Moderate Moderate

8.

9. 10.

11.

Kick off Meetings/Weekly QC meetings

Moderate Minor

12.

Kick off Meetings / Weekly QC meetings

Moderate

13.

Kick off Meetings / Weekly QC meetings

Moderate

14.

Kick off Meetings / Weekly QC meetings

Moderate

Page 14 of 17

Document Responsibility: Inspection Engineering Standards Committee SAEP-381 Issue Date: 17 March 2013 Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process
ESCALATION MATRIX S/N Sample Violation Contractor failure to conduct the 6-months Management Review Meetings and submit the results/recommendations to Saudi Aramco at the prescribed time Insufficient QC Manpower (Deficiency > 10% of Plan) Contractor failure to perform/implement inspection per approved ITP without adequate notification or justification (HOLD POINT activities) Contractor failure to perform/implement inspection per approved ITP without adequate notification or justification (Witness Point activities) QC Personnel on part time basis, either routinely performing non-QC functions or covering QC jobs in a different geographical location without prior approval of the ID Area Field Supervisor Insufficient QC Manpower (Deficiency < 10% of Plan) Failure to submit, incomplete, poor quality or late submittal of the required weekly or monthly deliverables as required by Schedule Q Poor or incomplete quality submittals or documentations Note: PQM has the option to increase this category as MAJOR if the submittals are for critical activities such as hydro test package of oil & gas facilities Poor, late or incomplete submission of the required weekly or monthly deliverables/documentations as required by Schedule Q Note: PQM has the option to increase this category as MAJOR if the submittals are for critical activities such as hydro test package of oil & gas facilities Failure to submit the required weekly or monthly deliverables/documentations as required by Schedule Q Note: PQM has the option to increase this category as MAJOR if the submittals are for critical activities such as hydro test package of oil & gas facilities Recommended Phase for Proactive Notification Violation Category

15.

Kick off Meetings / Weekly QC meetings Job X / Kick-off Meetings/ Weekly QC Meetings Kick off Meetings / Weekly QC meetings Kick off Meetings / Weekly QC meetings

Moderate

16.

Moderate

17.

Moderate

18.

Minor

19.

Job X / Kick-off / Weekly QC Meetings Job X / Kick-off Meetings Kick off Meetings / Weekly QC meetings

Minor

20.

Minor

21.

Minor

22.

Kick off Meetings / Weekly QC meetings

Minor

23.

Kick off Meetings / Weekly QC meetings

Minor

24.

Kick off Meetings / Weekly QC meetings

Minor

Legend: L = e-Log Book entry N = Non-Conformance Report (Q8 Notification) W = Worksheet (Q9 Notification)

Page 15 of 17

Document Responsibility: Inspection Engineering Standards Committee SAEP-381 Issue Date: 17 March 2013 Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

Appendix E - Table of Responsibilities for Quality Issue Notification


Responsible NCR Initiator / Issuer Field Supervisor/ PQM Approver Project Engineer / Sr. Project Engineer Recipient / Addressed To PM Representative Interested/Copied Parties Division Head, PID Division Head, PM Project Manager Proponent Site Rep. Worksheet PQM/ID Sr. Supervisor Division Head, PID Department Manager, PM General Manager, PM Sr. Project Engineer Department Manager, ID Division Head, PM Proponent Site Rep. DWS1 PID Division Head Department Manager, ID General Manager, PM Vice President, PM Vice President, ES Chief Engineer Project Manager Dept. Managers, PMT & Proponent DWS2 ID Manager Chief Engineer Vice President, PM Vice President, ES General Manager, PM General Auditor Dept. Managers, PMT & Proponent PID Division Head DWS3 Chief Engineer Vice President, ES Sr. Vice President, E&PM Vice President, PM General Manager, PMT General Auditor Project Manager ID Manager Dept. Managers, PMT & Proponent

Page 16 of 17

Document Responsibility: Inspection Engineering Standards Committee SAEP-381 Issue Date: 17 March 2013 Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

Appendix F - Index 1 2 3 4 5 6 7 8 9 Scope.. 2 Purpose.. 2 Conflicts and Deviations.. 2 Applicable Documents.. 3 Definitions... 3 Violations Definitions 4 Instructions. 5 Responsibilities. 8 Cancelled Quality Notifications. 10