Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Purpose Use this procedure to change or display actual assessment cycle. An actual assessment cycle is used for controlling how assessment or indirect activity allocation are processed. All the relevant information about the senders, receivers, sender rules, receiver rules and tracing factors is contained in Segments. In Profitability Analysis (CO-PA), you use a cycle to allocate cost center costs or process costs using assessment or indirect activity allocation to CO-PA. Trigger Perform this transaction when need to change actual assessment cycle. Menu Path Use the following SAP Easy Acces menu path(s) to begin this transaction: Accounting > Controlling > Profitability Analysis > Actual Postings > Period-End Closing > Transfer Cost Center Costs/ Process Costs > KEU5 - Assessment > Extra > Cycle > Change

Transaction Code KEU2, KEU3

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

1/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Screen Flow

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

2/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

3/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

4/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Procedure 1. In SAP, start the transaction using the menu path or transaction code. SAP Easy Access

2. Double-click the Accounting node 3. Double-click the Controlling node 4. Double-click the Profitability Analysis node 5. Double-click the Actual Postings node 6. Double-click the Period-End Closing node
Thursday, July 16, 2009 CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

. . . . .
5/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

7. Click the Scroll down button

8. Double-click the Transfer Cost Center Costs/Process Costs node . 9. Double-click the KEU5 - Assessment node You can also enter "KEU2" in the command field " " and click Enter " transaction. Set Operating Concern " to go directly to this .

10 As required, complete/review the following fields: . A R/O/C represent ation of a part of an organizati on for which the sales market is Description

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

6/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

structure d in a uniform manner. Field Example: TH01 R Operating concern 11 Click the Enter button . .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

7/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Execute Actual Assessment: Initial Screen

12 Click the Extras main menu .

. .

13 Click the Extras Cycle menu item .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

8/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Execute Actual Assessment: Initial Screen

14 Click the Change Shift + F6 menu item .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

9/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Change Actual Assessment Cycle: Initial Screen

15 Click the Cycle edit field .

. .

16 Click the Cycle possible entries button .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

10/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Cycle

17 Double-click the TH330 list item .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

11/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Change Actual Assessment Cycle: Initial Screen

18 Click the Enter button .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

12/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Change Actual Assessment Cycle: Header Data

19 Click the Overview segments button .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

13/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Segment Overview

20 Click the TH330-2 Name line item button .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

14/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Segment Overview

21 Click the Choose button .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

15/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Change Actual Assessment Cycle: Segment

22 Click the Senders/Receivers tab . 23 As required, complete/review the following fields: . An R/O/C organizati onal unit within a
Thursday, July 16, 2009

Description

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

16/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

controllin g area that represent sa defined location of cost incurrenc e. Field Example: 3303301 R Cost Center 24 Click the Header data button . .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

17/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Change Actual Assessment Cycle: Header Data

25 Click the Save button .

. .

26 Click the Overview segments button .

A success message is displayed indicating that a cycle has been changed.

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

18/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Segment Overview

27 Click the TH330-1 Name line item button . 28 Click the Choose button . .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

19/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Change Actual Assessment Cycle: Segment

29 Click the Edit main menu .

30 Click the Delete segment Shift+F2 menu item . . Delete Segment

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

20/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

21/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

31 Click the Yes button . Information

32 Click the Enter button .

CO-PA Change Actual Assessment Cycle: Segment

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

22/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

23/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

33 Click the Save button .

CO-PA Change Actual Assessment Cycle: Segment

34 Click the Exit button .

A success message is displayed indicating that a cycle has been changed.

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

24/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Change Actual Assessment Cycle: Segment

35 Click the Exit button .

36 Start the transaction using the menu path or transaction code. .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

25/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

SAP Easy Access

37 Double-click the KEU5 - Assessment node . You can also enter "KEU3" in the command field " " and click Enter " transaction.

" to go directly to this

38 Start the transaction using the menu path or transaction code. .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

26/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Set Operating Concern

39 As required, complete/review the following fields: . A R/O/C represent ation of a part of an organizati on for which the sales market is structure d in a uniform manner. Field Example: TH01 R Operating concern Description

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

27/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

40 Click the Enter button .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

28/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Execute Actual Assessment: Initial Screen

41 Click the Extras main menu . 42 Click the Cycle menu item .

. .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

29/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Execute Actual Assessment: Initial Screen

43 Click the Display Shift+F7 menu item .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

30/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Display Actual Assessment Cycle: Initial Screen

44 Click the Cycle edit field .

. .

45 Click the Cycle possible entries button .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

31/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Cycle (1) 14 Entries found

46 Double-click the TH330 list item

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

32/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

33/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Display Actual Assessment Cycle: Initial Screen

47 Click the Enter button .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

34/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Display Actual Assessment Cycle: Header Data

48 Click the First segment button .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

35/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Display Actual Assessment Cycle: Segment

49 Click the Senders/Receivers tab .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

36/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Display Actual Assessment Cycle: Segment

50 Double-click the TH_SOUTT Sales Org. edit field .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

37/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Display Set

51 Click the Enter button .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

38/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Display Actual Assessment Cycle: Segment

52 Click the Next page button .

53 Double-click the ALL_EXCL_INDO_AVLocal Level 01 edit field . .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

39/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Display Set

54 Click the Enter button .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

40/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Display Actual Assessment Cycle: Segment

55 Click the Scroll up button .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

41/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Display Actual Assessment Cycle: Segment

56 Click the Receiver Tracing Factor tab .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

42/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Display Actual Assessment Cycle: Segment

57 Click the Receiver Weighting Factors tab .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

43/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Distribution Criteria List

58 Click the Sales Organization check box . 59 Click the Level 1 check box . 60 Click the Local Level 01 check box . Distribution Criteria List . .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

44/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

61 Click the Enter button .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

45/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Display Actual Assessment Cycle: Segment

62 Click the Overview segments button .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

46/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Segment Overview

63 Click the TH330-4 Name line item button . 64 Click the Choose button . .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

47/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Display Actual Assessment Cycle: Segment

65 Click the Senders/Receivers tab .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

48/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Display Actual Assessment Cycle: Segment

66 Click the Next page button .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

49/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Display Actual Assessment Cycle: Segment

67 Double-click the INDOCHINALocal Level 01 edit field .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

50/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Display Set

68 Click the Enter button .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

51/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Display Actual Assessment Cycle: Segment

69 Click the Scroll up button .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

52/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Display Actual Assessment Cycle: Segment

70 Click the Receiver Tracing Factor tab .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

53/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Display Actual Assessment Cycle: Segment

71 Click the Receiver Weighting Factors tab .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

54/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Distribution Criteria List

72 Click the Profitability Unit check box . 73 Click the Banner check box . 74 Click the Enter button . . .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

55/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Display Actual Assessment Cycle: Segment

75 Click the Header data button .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

56/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

CO-PA Display Actual Assessment Cycle: Header Data

76 Click the Exit button .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

57/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Execute Actual Assessment: Initial Screen

77 Click the Exit button .

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

58/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Result You have changed and displayed actual assessment cycle.

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

59/60

Work Instruction

KEU2-KEU3 - JPN - Change-Display Actual Assessment Cycle

Scenario Instructions In this simulation you are required to: Change/Display Actual Assessment Cycle in SAP ECC 6.0.

Required Data This section provides the field data required to complete this exercise. Refer to this data sheet as necessary while performing the exercise. 3303301 01.01.2008 TH330 Field Cost Center Start Date Cycle TH01 Operating concern Value

Thursday, July 16, 2009

CO_KEU2-KEU3_JPN_Change-Display Actual Assessment Cycle.udc

60/60

Das könnte Ihnen auch gefallen