OEAEL PRESENTATION

BY:-

 ROHIT SINGH
 KUMAR DEEPAK
 SAHIL SAHNI

SAURABH MISHRA
 SA-2
 Wedding Date: April 22

 22 the cherry blossoms on campus are always in full bloom.

 Result in beautiful wedding pictures.

 Reservation of church and reception hall.

 Jane Summers to be my maid of honour from Guatemala.

 Cake and table decorations by Jack Catering service.

 Mrs. Watson for dress work.

 Invitations from Bob’s Printing Shop.


Problems Faced
 Church Booking 3 Days
 Church Notice 17 Days
 Church Decoration 3 Days
 Jane Summer – Maid of Honor 10 Days
 Jack’s Catering – Notice 10 Days
 Cake & Table Decoration 2 Days
 Wedding Dress Pattern 3 Days
 Dress Material from NY 8 Days
 Mrs. Watson – Dress Designer 6 Days
 Final fitting of Dress 2 Days
 Clean & Press the Dress 2 Days
 Invitation Card Style 3 Days
Problems Faced (contd.)
 Printing of Cards - Bob’s Press 12 Days

 Compiling the Guest List 4 Days

 Addressing the Cards 4 Days

 Taking the Cards to Post Office 1 Day

 Dispatch of Invitation Cards 10 Days


 Gifts to bridesmaid at Rehearsal Dinner 1 Day
The Campus Wedding Case Project Network

PATH 1: Reserve Church (1) – Church Notice (17) – Decorate Church (3) – Wedding (1) -- length 22
days.

PATH 2: Choose Cake (2) – Jack’s Catering (10) – Rehearsal Dinner (1) – Wedding (1) – length 14
days.

PATH 3: Get Gifts (1) – Rehearsal Dinner (1) – Wedding (1) – length 3 days.

PATH 4: Travel from Guatemala (10) – Fit Dress (2) – Clean & Press (2) – Wedding (1) -- length 15
days.

PATH 5: Choose Pattern (3) – Receive Lace (8) – Sew Dress (11) – Fit Dress (2) – Clean & Press (2)

Wedding (1) –length 27 days.

PATH 6: Choose Invitations (3) – Receive Invitations (12) – Address Invitations (4) – Inv. To Post
Office (1) – Invitation Lead Time (10) – Wedding (1) – length 31 days.

PATH 7: Prepare Guest List (4) – Address Invitations (4) – Inv. To Past Office (1) – Invitation Lead
Time (10) – Wedding (1) – length 20 days.

Some assumptions are in order: (1) we assume that we can start tomorrow (April 1), (2) everyone
works 7 days a week.

Path 1, 5 and 6 are all critical. Path 5 and 6 will have to be crashed to meet the wedding date of April
22.
3. What is the minimum cost plan that meets the April 22 date?

For path 6, we would reduce the time to Receive the Invitations to 5 days (cost $35) and hire help to
address Invitations to reduce this time to 2 days (cost $50). This would reduce the path length to
exactly 22 days at a cost of $85.

For path 5, we would reduce the time to Receive Lace to 5 days (cost $25), reduce Clean & Press to
1 day (cost $30), and hire Mrs. Watson 1 day to reduce Sew Dress to 10 (cost $120) days. This
would reduce the path length to exactly 22 days at a cost of $175.

The minimum cost to have the wedding on April 22 is $260.