Beruflich Dokumente
Kultur Dokumente
GRH. - SGE.
Obra
0301017
Subpresupuesto
004
TANQUE ELEVADO
Fecha
07/11/2009
Lugar
090117
Cdigo
Recurso
Unidad
Cantidad
Precio S/.
Parcial S/.
MANO DE OBRA
0147010002
OPERARIO
hh
216.5182
7.76
1,680.20
0147010003
OFICIAL
hh
81.8701
5.93
485.49
0147010004
PEON
hh
238.4267
4.71
1,123.01
3,288.69
MATERIALES
0202000007
kg
44.9370
4.00
179.76
0202000008
kg
19.2200
4.00
76.88
0202010002
0.6400
4.00
2.56
0202010003
0.6400
4.00
2.56
0202010005
12.6426
4.00
50.56
0202940065
9.4500
11.20
105.84
0203020003
801.3765
4.00
3,205.52
0204000000
ARENA FINA
m3
1.8986
150.00
285.00
0205000003
m3
6.3920
150.00
958.50
0205010004
ARENA GRUESA
m3
3.1584
140.00
442.40
0221000001
93.2628
20.00
1,865.20
0226040002
CANDADO 45 mm
und
1.0000
45.00
45.00
0229050001
CINTA TEFLON
rll
1.0000
1.20
1.20
0229060002
YESO EN BOLSAS DE 25 kg
bls
0.3200
6.50
2.08
0229200010
THINNER CORRIENTE
gal
0.0360
15.00
0.60
0230160036
ADITIVO IMPERMEABILIZANTE
gal
1.2012
28.00
33.60
0230460050
gal
0.0800
45.00
3.60
0230990056
CINTA TEFLON
und
5.5000
1.20
6.60
0238000000
HORMIGON
m3
1.7830
130.00
231.40
0239020027
LIJA DE FIERRO # 80
pza
3.4685
2.40
8.33
0239050000
AGUA
m3
0.8149
5.00
4.05
0243040000
MADERA TORNILLO
p2
368.7756
4.20
1,548.88
0243040005
CORDEL
ml
1.6000
0.20
0.32
0243040006
REGLA DE MADERA
p2
2.3913
4.70
11.23
0243550002
MADERA ANDAMIAJE
p2
17.8270
3.50
62.41
0243550008
ANDAMIO DE MADERA
p2
11.8700
4.20
49.85
0244010001
ESTACA DE MADERA
p2
4.0000
2.50
10.00
0254010001
gal
0.0360
45.00
1.80
0254020081
PINTURA ESMALTE
gal
0.2000
45.00
9.00
0254030029
gal
2.5785
25.00
64.50
0254060000
PINTURA ANTICORROSIVA
gal
0.0288
45.00
1.35
0254160003
IMPRIMANTE
gal
1.2893
22.00
28.38
0256920002
1.0000
200.00
200.00
0265000108
1.0000
600.00
600.00
0265000109
TUBERIA DE F G DE 1/2"
ml
3.6750
5.00
18.35
0265000110
TUBERIA DE F G DE 3/4"
ml
13.1250
7.50
98.48
0265050011
2.0000
4.00
8.00
0265050012
2.0000
7.50
15.00
0265050047
2.0000
11.50
23.00
0265130064
2.0000
3.50
7.00
0265140067
2.0000
7.00
14.00
0265140100
8.0000
3.50
28.00
0272130009
8.5000
4.00
34.00
0272310001
und
2.0000
4.20
8.40
0272310005
und
8.0000
2.80
22.40
0277000002
1.0000
21.45
21.45
0277000003
1.0000
25.00
25.00
0277000007
1.0000
45.00
45.00
0277030003
2.0000
24.00
48.00
0277050022
1.0000
21.00
21.00
und
10,536.03
EQUIPOS
0337010001
HERRAMIENTAS MANUALES
%MO
0348010011
5.7892
26.00
150.54
0348110003
CAMION VOLQUETE DE 8 m3
0.3199
95.00
30.40
0349030001
0.4169
19.00
7.98
0349070004
5.3320
15.00
79.95
0349880003
TEODOLITO
0.5120
10.00
5.10
hm
hm
136.76
410.73
Total
S/.
La columna parcial es el producto del precio por la cantidad requerida; y en la ltima columna se muestra el Monto Real que se est utilizando
S/.
Pgina :
Presupuestado S/.
1,681.41
485.50
1,122.87
3,289.78
179.75
76.88
2.56
2.56
50.58
105.84
3,205.50
284.91
958.81
442.17
1,865.17
45.00
1.20
2.08
0.54
33.63
3.60
6.60
231.79
8.33
4.09
1,548.66
0.32
11.41
62.39
49.84
10.08
1.62
9.00
64.47
1.30
28.37
200.00
600.00
18.38
98.50
8.00
15.00
23.00
7.00
14.00
28.00
34.00
8.40
22.40
21.45
25.00
45.00
48.00
21.00
10,536.18
136.76
150.51
30.38
7.94
79.98
5.12
410.69
14,235.45
14,236.65
14,236.65