DATE OF OPENING:
LAND AREA:
28,626 sq. m.
CFA:
40,267 sq. m.
16,308.54 sq. m.
FOOD TENANTS:
12
NON-FOOD TENANTS:
41
OPEN PARKING:
311 slots
MOTORCYCEL PARKING:
80 slots
6 slots
CINEMA N/A
CINEMA N/A
CINEMA N/A
CINEMA N/A
ELECTRICITY DISTRIBUTOR:
SUBSTATION CAPACITY: GENSETS CAPACITY: DIESEL TANK CAPACITY: CHILLERS CAPACITY: COOLING TOWER CAPACITY: TOTAL NO OF AHU: TOTAL NO OF FCU: TOTAL NO OF KEF: TOTAL NO OF KSF: TOTAL NO OF FAF: TOTAL NO OF EF: TOTAL NO OF SF TOTAL NO OF SEF: TOTAL NO OF PB: TOTAL NO OF LEF: WALKALATOR: (HYUNDAI): FREIGHT ELEVATORS (HYUNDAI): PASSENGER ELEVATORS (HYUNDAI):
REPORT OUTLINE:
1. 2. 3. 4.
FACILITIES STATUS UPDATES. EQUIPMENTS BREAKDOWN REPORT. UTILITIES CONSUMPTION, PRODUCTION AND DELIVERIES UPDATES. ENGINEERING AND MAINTENANCE ACTIVITIES SUMMARY AND UPDATES. (BUILDING AND PERIMETER) 5. BUSTED LIGHTS MONITORING UPDATES. 6. ISSUES AND NEEDS LIST. 7. PUNCHLISTS UPDATES.
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
DESCRIPTION
STATUS/REMARKS
CARE OF HYPERMARKET, ENGINEERING ALREADY SENT MESSAGE TO ADMIN TO INFORM HYPER FOR THE IMMEDIATE RECTIFICATION OF THE SAID ELEVATOR THE PAT AND EQ TANK ALREADY DECLOGGED BY MMRC, THE PUMP WILL BE FIXED ON WENESDAY OCT. 24, 2012.
25SEP2012
28
CLOGGED
17SEP2012
35
182kWh
189kWh 43.81L
203kWh
223kWh
219kWh
238kWh
316kWh
5 0 2 0 0
0 0 0 0 0
0 0 1 0 0
0 1 0 0 0
1 2 1 0 1
DESCRIPTION
De-clogging the manhole at Cover car park (exit)
DESCRIPTION
Bio-Augmentation/de-clogging the stub-out of tenants
DESCRIPTION
General Cleaning of Cooling Tower
DESCRIPTION
General Cleaning of Cooling Tower
DESCRIPTION
De-Clogging the drainage at south parking
DESCRIPTION
De-Clogging the drainage at south parking
DESCRIPTION
De-Clogging Pre Aerobic Tank and Equalization Tank by MMRC SM CENTER LAS PIAS WEEKLY REPORT (15OCT TO 21OCT 2012)
DESCRIPTION
De-Clogging Pre Aerobic Tank and Equalization Tank by MMRC
Engineering Design & Development
DESCRIPTION
Replacement of Defective Emergency Light Battery
DESCRIPTION
Replacement of Defective Emergency Light Battery
DESCRIPTION
Rectification of Leak Sources By Esicor
DESCRIPTION
Rectification of Leak Sources By Esicor
DESCRIPTION
Upgrading of Hi-Land Coffee Feeder Line
DESCRIPTION
Upgrading of Hi-Land Coffee Feeder Line
DESCRIPTION
FDAS Preventive Maintenance by JTY
DESCRIPTION
FDAS Preventive Maintenance by JTY
DESCRIPTION
Testing the fixed breaker of Freight Elevator
DESCRIPTION
Fixing the loose breaker terminal lugs of Freight Elevator
Engineering Design & Development
DESCRIPTION
Replacement of the worn out Drive wheel of MW downstream SM CENTER LAS PIAS WEEKLY REPORT (15OCT TO 21OCT 2012)
DESCRIPTION
Replacement of the worn out Drive wheel of MW downstream
Engineering Design & Development
REMARKS
0
0 0
0
0 0
REMARKS
NO INITIATED REPAIR DRIVE WHEEL IS SUBJECT FOR REPLACEMENT ALREADY REQUESTED FOR QUOTATION
END OF PRESENTATION
-THANK YOU-