Hart High School
Phase I - Modernization Plan
All Buildings

Modernization/New Construction: Science Bldg, C, F, J, K, M, Q & R


Existing Condition

Summer 2008
Segment 1: Demo Bldg A and T
Portables

Segment 1: Demo Building A and T Portables - Complete


Segment 1 : Demo Bldg A and T
Portables

Segment 1: Demo Building A and T Portables - Complete


Segment 1 : Add Interim
Housing

Segment 1: Add Interim Housing - Complete


Segment 1 : Bldgs C & F

Segment 1: Building C South and Building F North - Demo Complete


Segment 1: Bldg S

In Process: New Science Building - Bid August 2008


Science Bldg Flyaround

In Process: New Science Building – Spring to Winter 2009


Science Bldg Flyaround

In Process: New Science Building – Winter 2009


Science Bldg Flyaround

In Process: New Science Building – Winter 2009


Science Bldg Flyaround

In Process: New Science Building – Winter 2009


Science Bldg Flyaround

In Process: New Science Building – Winter 2009


Science Bldg Flyaround

In Process: New Science Building – Winter 2009


New Standardized
Lab Classrooms and

Science Bldg Floor Plan


Prep rooms Typ.

Lighting
Carpet / Tile
Cabinetry
Power / Data
Acoustical Treatment
Fire Alarm
HVAC
Storage rooms
Restrooms

In Process: New Science Building Floor Plan – Winter 2009


Science Bldg Rendering

In Process: New Science Building – Winter 2009


Science Bldg Rendering

In Process: New Science Building – Winter 2009


Segment 1: Bldg S

In Process: New Science Building – Winter 2009


Segment 1 : Q10 Toilet

In Process: Q-Village Toilet Building – Summer 2009


All Buildings

Modernization/New Construction: Scheduled Start Winter 2008


Segment 1 : Bldgs C & F

Segment 1: Building C South and Building F North – Winter 2008


Segment 1 : Bldg F South

Segment 2: Building F South – Spring 2009


Modernized Food
Service Classroom

Bldg C Floor Plan Modernized Restroom

Standard Size
Classrooms, Typ.

MODERNIZED

Lighting
Carpet / Tile
Cabinetry
Power / Data
Acoustical Treatment
Fire Alarm
New HVAC
Additional Storage Space
EXISTING
Building C Plans
Bldg F Floor Plan

MODERNIZED

Modernized Restroom
Standard Size Classrooms, Typ.
Lighting
Carpet / Tile
Cabinetry
Power / Data
Acoustical Treatment
Fire Alarm
New HVAC
Additional Storage Spaces
EXISTING
Building F Plans
Segment 1 : Bldg. M SITE

Segment 3: Building M – Summer to Winter 2009


Standard Size Classrooms, Typ.

Bldg. M Floor New Restrooms


Modernized Art Studios

Plan Lighting
Carpet / Tile
Cabinetry
Power / Data
Acoustical Treatment
Fire Alarm

MODERNIZED

EXISTING
Building M Plans
Segment 1 : Bldg. K Site

Segment 4: Buildings J & K – Winter 2009 to Summer 2010


Modernized Physics Lab and
Prep Room

Bldg J Floor Plan New Restrooms

Standard Size Classrooms,


Typ.

MODERNIZED

Lighting
Carpet / Tile
Cabinetry
Power / Data
Acoustical Treatment
Fire Alarm
New HVAC

EXISTING
Building J Plans
Standard Size Classrooms, Typ.

Bldg. K Floor Standard Lab / Classrooms, Typ.

Plan Lighting
Carpet / Tile
Cabinetry
Power / Data
Acoustical Treatment
Fire Alarm

MODERNIZED

EXISTING
Building K Plans
Segment 1 : Bldg. R Site

Segment 5: Building R – Summer 2009 to Spring 2010


New Band Room

Bldg. R Floor Modernized Choral and Practice


Rooms

Plan Lighting
Carpet / Tile
Cabinetry
Power / Data
Acoustical Treatment
Fire Alarm
New HVAC
Additional Storage Rooms

MODERNIZED

EXISTING
Building R Plans
All Buildings

Modernization/New Construction: Science Bldg, C, F, J, K, M, Q & R


Segment 9 : Sitewide mod +
NC

Segment 6: New Fire Alarm System


All Buildings

Modernization/New Construction: Scheduled Complete Summer 2010


All Buildings

Modernization/New Construction: Interim Housing Removed


Rendering

Rendering
08.10.08