ACCOMPLISHMENT REPORT FOR THE MONTH OF DECEMBER

(As of December 18, 2013)


December 4, 2013

Conducted ocular inspection and site validation Re: TISP Water


Project in the LGU of Paglat, Maguindanao.
Construction of Paglat WSS L-III
80% fund released to the LGU
90% Physical Accomplishment

December 5, 2013

Conducted ocular inspection and site validation Re: TISP Water


Project in the LGU of Sultan sa Barongis, Maguindanao.
Construction & Installation of twenty six (26) Hand Pumps with Laundry
Shed (L-I)
80% fund released to the LGU
95% Physical Accomplishment

December 6, 2013

Conducted ocular inspection and site validation Re: TISP Water


Project in the LGU of General Salipada K. Pendatun, Maguindanao.
80% fund released to the LGU
Const. of Badak WSS (L-II): 90% Physical Accomplishment
Const. of Bagundang WSS (L-II): 65% Physical Accomplishment
Rehab. of Ramcor WSS (L-II): 45% Physical Accomplishment

December 9, 2013

Conducted ocular inspection and site validation Re: TISP Water


Project in the LGU of Mamasapano, Maguindanao.
Installation of Hand Pumps with Laundry Shed Level I
50% fund released to the LGU
70% Physical Accomplishment

December 10, 2013

Conducted ocular inspection and site validation Re: TISP Water


Project in the LGU of Mangudadatu, Maguindanao.
Construction of PWS (L-II)
45.% fund released to the LGU
50% Physical Accomplishment

Prepared by:
ENGR. ROHAINA T. SAPAL
Engineer I