Beruflich Dokumente
Kultur Dokumente
Bottlenecks
Data.
• No. of shovels = 3
• All three shovels can operate at the same time
• Time taken by the each shovel to load the truck = 10 minutes
• No. of crushers = 3
• Crushers operational at a given time = 2
• Maximum output from each crusher = 520 tones / hr
• The ‘octopus’ can process 1200 tones/hr
• Total loading time for loading a truck = 10 minutes
• Time for a trip from pit to crusher = 15 minutes
• Time for unloading at the crusher = 10 minutes
• Time for a trip from crusher to the pit = 10 minutes
• Each truck can carry 80 tones of ore
• Operation time for company = 24 hours a day, 7 days a week
• Production of the company = 24,000 tones per day
Total Cycle time for one truck to pick up ore from shovels
One cycle time
Therefore
1440 = 32 Trips
45
i
Number of tones a truck can carry / day
= 80 x 32 = 2560 tones
Trucking Operation:
The company operates 24 hrs / day, 7 day a week to meet the signed contract to
supply the customer, i.e. 24,000 tones/ day, in addition the assumption we made that
there is no depletion or wastage of time and final product supplying to the customer,
therefore, amount extracted is equal to the amount of granite produced. Thus
To find the minimum number of trucks, in a day, required to meet the daily output
requirements we divide the total output in a day by amount of tones carried by a truck
in a day i.e.
b) Percent Utilization
Each shovel can load a truck in 10 minutes, and each truck can carry 80 tones of load.
As there are three shovels working, therefore load of 80 tones by one shovel can make it
in every 10 minute.
Thus, in one hour, 6 loads of 80 tones = 80 x 6 = 480 tones (Amount loaded by one
shovel)
ii
By three Shovels.
Every 45 minutes a truck completes one whole cycle from the quarry to the pit.
iii
Percentage utilization of crushers.
Percentage Utilization
(Actual utilization ÷ Maximum utilization) * 100, where Actual utilization = 24,000
Shovels = 69.44%
Trucks = 93.75%
Crushers = 96.15%
Octopus = 83.33%
c) Bottleneck Operation.
The apparent bottleneck is the crushers it has highest maximum percent utilization
recorded as 96.15%.
d) Recommendation.
iv
lets say that third crushing line will be operational with in the time limit contract than the
following will be answer working will all crushing lines.
As we can see the percent utilization will be reduced by staggering 32%, than again the
new bottleneck will be recoded in trucks percentage utilization i.e 93.75%, In that case
necessary investment is much needed to avoid creating any bottlenecks
v
Problem (2)
Line Balancing
a) Precedence Diagram
A11
D11
G7
B7
C12 E5 F13
H9 I 15
Factory operates for 450 minutes per day (Counting all breaks)
vi
d. Line Balancing.
Therefore,
Work station 1:
Workstation 2:
vii
= [(22-27) / 27] x 100 = 18.51%
Workstation 4:
Problem (3)
Statistical Process Control
viii
Measurement of abandon call rates nation-wide taken every hour
a)
µ = 16.1
σ = 1
E( x ) = µ
E( x ) = 16.1
σx = σ/√ n
= 1/√12
σ x = 0.288
b) 3 σ Control limits
UCL x = µ + 3(σ/√ n)
= 16.1 + 3(0.288)
UCL x = 16.9
LCL x = µ - 3(σ/√ n)
ix
= 16.1 - 3(0.288)
LCL x = 15.2
c)
X = 16.1+16.8+15.5+16.5+16.5+16.4+15.2+16.4+16.3+14.8+14.2+17.3
12
X = 16
Sample no X
10 14.8
11 14.2
12 17.3
@ 100% of standard, the total cycle time is calculated as 2.45 min and worker will work
(8 hours) 480 min / per day.
If the bonus of 15% is to be paid, items must be shaped 100 / 115 of the standard time
xi
= 2.13 min
= 2.45-2.13 = 0.32
= 0.23 min
= 0.48 min
8 Total cycle time = 2.45 Total cycle time = 2.45 Total cycle time = 2.45
If the bonus of 30% is to be paid, items must be processed 100 / 130 of the standard time
(2.45 min).
= 1.88- 1.90
xii
Critical Path
a. Network Diagram
A2 C4 F4 H4 J3
D4 G7 L6
xiii
B4 E1 I6 K5
b. Critical Path
Because critical path is the longest part in the project and total calendar time for required
project, therefore normal completion time for the project is however 26 weeks to
complete this project
Manager signed the contract to complete the project in 45 weeks and the normal
completion time is 26 weeks which actually is two weeks over the normal completion
time, thus total penalty for two weeks worth $650, breaking down further to activity A
manager it saves $5 against $ 325 and one week of completion, furthermore if the
manager pays $275 for activity D, which manager can actually saves $50 for another
week, therefore the project will be finished with in 24 weeks and manager spends $595,
instead of $650, which saves extra $55
If the activities outside the critical path speed up or slow down (within limits), total
project time does not change, similarly activity F (slack time), does not descend under
critical path, thus there wouldn’t be any delay in project, there fore manager will not take
any actions against activity F
Problem 6
Data
xiv
H= holding or carrying cost per year =$20 x 23%= $4.60
(a) E.O.Q =
2x D x S
H
= 2 x 2080 x $10
$4.60
= ~ 96 units
= ~ 22 order / year
=
D Q
S + H
Q 2
= 0 269
100 + 1
269 2
= $269.5
xv
= 316.23
= ~ 317 units
= 1.58
D Q
= S + H
Q 2
500 317
100 1
= 317 2
= $316.23
(e) The sensitivity level is low with these demands variable. There would be no doubt
that the costs are being cheaper with the increase of quantity (demand).
xvi