Sub Contractor:

Peaks Construction Maintenance Co. Ltd.


Power Water Utility Company for J ubail Yanbu SETE Energy Saudia
Man Hours histogram
Resource
11-May J UN J UL AUG SEP OCT NOV DEC J AN FEB 10-Mar
CARPENTER 1 10 16 25 33 35 50 50 50 35 25
STEEL FIXER 1 12 19 33 40 45 60 80 70 45 33
CARPENTER HELPER 2 10 16 25 33 35 50 50 50 35 25
STEEL FIXER HELPER 2 12 19 33 40 45 60 80 70 45 33
LABOR 5 10 10 10 15 25 30 38 38 25 10
CONCRETE LABOR 3 10 10 10 10 10 12 15 15 10 10
SECURITY LABOR 1 2 2 2 2 2 2 1 1 2 2
EPOXY PAINTER 3 0 0 0 2 5 5 5 5 5 0
WELDER 5 2 1 1 1 1 1 1 1 1 1
TOTAL 23 68 93 139 176 203 270 320 300 203 139
2010 2011
23
68
93
139
176
203
270
320
300
203
139
11May JUN JUL AUG SEP OCT NOV DEC JAN FEB 10Mar
2010 2011
ManHourshistogram
CARPENTER STEELFIXER CARPENTERHELPER STEELFIXERHELPER LABOR CONCRETELABOR SECURITYLABOR EPOXYPAINTER WELDER TOTAL
Project No.
7200012306
Man Hours histogram
5/29/2010 Installation 48000 m3/day Industrial Wast Water Treatment Plant (IWTP)