PROJ ECTSCHEDULE
Total 122 01AUG12 30NOV12
SYSTEM DESIGN DRAWINGS
SDD 10 Design and Drafting of Works 7 01AUG12 07AUG12
SDD 20 Design 1st Review and Approval 5 08AUG12 12AUG12
SDD 30 Minor Revision 5 13AUG12 17AUG12
SDD 40 2nd Review and Approval 3 18AUG12 20AUG12
MATERIAL PROCUREMENT
MP 10 MS Plates 5 13AUG12 17AUG12
MP 20 Pipes 3 16AUG12 18AUG12
MP 30 PPN Strainers 3 19AUG12 21AUG12
MP 40 Resins 5 22AUG12 26AUG12
MP 50 Pumps 5 27AUG12 31AUG12
MP 60 Accessories 5 01SEP12 05SEP12
PRODUCTION and INSTALLATION
INS 10 Rolling of Plates/ Fab. of Conical Bot. @ Manila 21 18AUG12 07SEP12
INS 20 Delivery of Materials on Site 7 03SEP12 09SEP12
INS 30 Fabrication of Tanks 21 10SEP12 30SEP12
INS 40 Foundation Works 5 28SEP12 02OCT12
INS 50 Installation of Tanks 7 03OCT12 09OCT12
INS 60 Piping Works 7 10OCT12 16OCT12
INS 70 Rubber Lining 7 17OCT12 23OCT12
INS 80 Loading of Resins 3 24OCT12 26OCT12
INS 90 Application of Accessories 5 27OCT12 31OCT12
INS 100 Punchlisting and Other Works 7 01NOV12 07NOV12
TESTING
TST 10 Finishing Works 5 08NOV12 12NOV12
TST 20 Testing of Tank System 3 13NOV12 15NOV12
TST 30 Commissioning & Training of Personnel 5 16NOV12 20NOV12
TST 40 Punchlisting 10 21NOV12 30NOV12
TURN-OVER
TO 10 Project Turn-over 0 30NOV12
2012
J AUG SEP OCT NOV DEC
30 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24
Design and Drafting of Works
Design 1st Review and Approval
Minor Revision
2nd Review and Approval
MSPlates
Pipes
PPN Strainers
Resins
Pumps
Accessories
Rolling of Plates/ Fab. of Conical Bot. @ Manila
Delivery of Materials on Site
Fabrication of Tanks
Foundation Works
Installation of Tanks
Piping Works
Rubber Lining
Loading of Resins
Application of Accessories
Punchlisting and Other Works
Finishing Works
Testing of Tank System
Commissioning & Training of Personnel
Punchlisting
Project Turn-over
Primavera Systems, Inc.
Start Date 01AUG12
Finish Date 30NOV12
Early Bar
Progress Bar
Critical Activity
PROJECTSCHEDULE
DM TANK
Sheet 1of 1
Date Revision Checked Approved