Snag Lists

Work Order No.3
AL KHABISI ID: 2785 (Service Road)
Remaining Works
1-Traffic signs & Site Cleaning.
Comments to be rectified
1-Kerbstones Work (Flush/Up-stand) in various locations (see attached photos)
I- Concrete between asphalt and kerbstones had been cracked.
II- Damage on Kerbs to be rectified or changed the damage pieces.
III- Kerbs to be cleaned from concrete.
V- Some gaps are empty from concrete to be rectified.

CH: 0+003 (Flush Kerbs)
CH: 0+003 R/S (Up-stand Kerbs)
CH: 0+040 L/S (Flush & Up-stand)
2- Tiles Work (6.00cm @ Footpath) (see attached photos)
I-Footpath tiles are higher & lower or than Kerbs top in various locations.
II-Gaps (Joints) to be filled with black/crushed sand.
CH: 0+003 R/S
CH: 0+012 R/S
CH: 0+020 L/S
CH: 0+025 R/S
CH: 0+032 L/S
3-Tiles Work (8.00cm @ Footpath) (see attached photos)
I-Color Variation in tiles.
II-Gaps (Joints) to be filled with black/crushed sand.

Page 2 of 2

Work Order No.6
AL MUWAIJI ID: 2030 (Service Road and parking)
Remaining Works
1- Traffic signs & site cleaning
2- Verge preparation (CH:0+035 0+0110 R/S & CH:0+050 0+100 L/S)

Comments to be rectified
1-Tiles Work (6cm @ Footpath) (see attached photos)
I- Footpath tiles are higher & lower or than Kerbs top in various locations.
II- Existing paviors there are settlement due to improper fixing
CH: 0+010 0+024 R/S
CH: 0+025 R/S

2-Tiles Work (8cm Carriageway) (see attached photos)
I-Color Variation in tiles to be rectified.
II-Gaps (Joints) to be filled with black/crushed sand.

CH: 0+010 0+110
CH: 0+010 0+019
CH: 0+070 0+080
3-Kerbstones Work (Up-stand) (see attached photos)
I- Concrete to be rectified between Kerbs (Joints)
II-Clean Kerbs from concrete