1. Provide the services of a factory-trained manufacturers representative to assist the Contractor in the installation and start-up service of the equipment and to train Owner's personnel as specified. 2. Start-up checklists: Perform the following final checks before Start-up: a. Inspect primary and secondary power connections. b. Inspect control interconnections. c. Inspect grounding. 3. Starting Procedures: Follow the manufacturer's written procedures and the following as a minimum: a. Visually and mechanically inspect to include the following: vibration isolation, anchoring, grounding, installation verification using manufacturers checklist, flexible bus connections, torque of bus and cable connections, and tap changer operation. b. Verify operation of temperature controls/alarms. c. Perform winding insulation tests. d. Conduct turns ratio test. e. Perform power factor/dissipation test on windings and bushings. f. Perform high voltage and low voltage winding and core resistance measurements. g. Check and confirm percentage of impedance is identical for all three transformers comparing nameplates.