PROJECT : SMALL IRRIGATION SYSTEM (DIVERSION DAM)

LOCATION : BARANGAY SAMBULAWAN, LEYTE, LEYTE


POTENTIAL AREA : 38 Hectares
BENEFICIARIES SERVE : 40 Farmers

PROJECT PROGRAM OF WORK

ITEM NO. PARTICULARS UNIT QUANTITY WEIGHT UNIT COST AMOUNT

1.00 Const'n. of Camp/Bank House sq.m. 42.00 19.24 L.S. 42,500.00


2.00 Diversion of Water & Care of creek Hrs. 80.00 8.48 234.00 18,720.00
3.00 Dam Flooring & Cut-Off Wall
3.10 Structural Excavation cu.m. 4.77 0.21 99.31 473.71
3.20 Concrete Class "A" cu.m. 3.68 10.89 6,537.86 24,059.32
3.30 Reinforcing Steel Bars kls. 222.34 3.90 38.75 8,615.68
3.40 Structural Backfill cu.m. 1.85 0.10 119.17 220.46
4.00 Retaining Wall & Pier
4.10 Structural Excavation cu.m. 13.45 0.60 99.31 1,335.72
4.20 Concrete Class "A" cu.m. 5.62 16.64 6,537.86 36,742.77
4.30 Reinforcing Steel Bars kls. 339.72 5.96 38.75 13,164.15
4.40 Structural Backfill cu.m. 11.75 0.63 119.17 1,400.25
5.00 Outlet Works
5.10 Excavation cu.m. 3.38 0.15 99.31 335.67
5.20 Concrete Class "A" cu.m. 1.15 3.40 6,537.86 7,518.54
5.30 Reinforcing Steel Bars kls. 69.30 1.22 38.75 2,685.38
5.40 Backfill cu.m. 1.65 0.09 119.17 196.63
6.00 Grouted Riprap 250 mm dia. cu.m. 11.61 14.83 2,821.65 32,759.36
6.10 Excavation cu.m. 5.73 0.26 99.31 569.05
7.00 Flashboard (Lumber) bd.ft. 70.00 2.43 76.79 5,375.30
8.00 Canalization (1250 LM)
8.10 Excavation cu.m. 135.45 6.09 99.31 13,451.54
8.20 Backfill cu.m. 89.95 4.85 119.17 10,719.34

TOTAL 100.00 220,842.86

Prepared by: Recom. Approval:

BUENAVENTURA L. PITAO ERLINDO P. LAPLANA


Engr. II, Prov'l. Ag. Eng'g. Group Prov'l. Agriculturist

Reviewed by: APPROVED BY:

WELL V. CAPANGPANGAN CIRILO BALAGAPO, JR.


Chief, Reg'l. Ag. Eng'g. Group Reg'l. Director

CONCURRED BY:

_____________________________
Municipal Mayor