Sie sind auf Seite 1von 3

State of Illinois

CAPITAL DEVELOPMENT BOARD


FOR CDB USE ONLY
PROPOSED PROJECT Name:
COST BUDGET Project No:
Contract No:
C.F. Locale Design Phase

CDB PROJECT NUMBER: DATE PREPARED:


BLDG. INVENTORY NO: PROJECT STATUS:
PROJECT: GSF: NSF: NASF/GSF:
LOCATION: SITE ACREAGE:
A/E: PREPARED BY:
CDB PROJECT MANAGER:

1. LAND ACQUISITION COST RECAP OF CONSTRUCTION COSTS (Base Bid)

2. MOVABLE EQUIPMENT (From Page 2 Worksheet)


3. ART-IN ARCHITECTURE TRADE ESTIMATES (Column H)
4. OTHER General $220.00
5. A/E Basic Service Fee Plumbing $0.00
6. Additional Services Heating $0.00
7. Construction Admin. Fee Ventilating $0.00
8. On-Site Representative Electrical $0.00
9. Subtotal (1 thru 8) $0.00 Asbestos $0.00
10. A/E REIMBURSABLES Sprinkler $0.00
a. Subsoil Investigation $0.00
b. Design Ph. Material Testing $0.00
c. Construction Ph Material Test $0.00
d. Printing Contingency (Column D Total) $12.00
e. 13. TOTAL BASE BID BUDGET
f. (Trade estimates plus contengency) $232.00
g.
h. 14. TOTAL BUDGET ( 12 plus 13) $232.00
i. 15. Total Project Funds
(From Project Scope)

Available Funds for


16. Construction $0.00
(15 minus 12)
11. Subtotal (10a thru 10i) $0.00
17. Alternates (Total from Page 2) $0.00

18. Base Bid plus Alternates


12. TOTAL (9 plus 11) $0.00 (13 plus 17) $232.00

December 2005
Page 1 of 2

December 2005
Worksheets
TRADE A B C D E F G H I J
Building Site Work Subtotal Contingency Alternates Subtotal (C+E) CAF Subtotal Total I/GSF
(Base Bid (Base Bid (A + B) (Cx10%) (Fx3%) (C+G) (D+ F +G)
Estimate) Estimate) Round up to
next $100

General $120.00 $120.00 12.00 $0.00 $120.00 $100.00 $220.00 $232.00


Plumbing $0.00 0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Heating $0.00 0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Ventilating $0.00 0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Electrical $0.00 0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Asbestos $0.00 0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Sprinkler $0.00 0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Column
Totals $120.00 $0.00 $120.00 $12.00 $0.00 $120.00 $100.00 $220.00 $232.00

TRADE Alternate #1 Alternate #2 Alternate #3 Alternate #4 Alternate #5 Alternate #6 Alternate #7 Alternate #8 Totals
General $0.00
Plumbing $0.00
Heating $0.00
Ventilating $0.00
Electrical $0.00
Asbestos $0.00
Sprinkler $0.00
$0.00
$0.00
$0.00
Column
Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00