Beruflich Dokumente
Kultur Dokumente
December 2005
Page 1 of 2
December 2005
Worksheets
TRADE A B C D E F G H I J
Building Site Work Subtotal Contingency Alternates Subtotal (C+E) CAF Subtotal Total I/GSF
(Base Bid (Base Bid (A + B) (Cx10%) (Fx3%) (C+G) (D+ F +G)
Estimate) Estimate) Round up to
next $100
TRADE Alternate #1 Alternate #2 Alternate #3 Alternate #4 Alternate #5 Alternate #6 Alternate #7 Alternate #8 Totals
General $0.00
Plumbing $0.00
Heating $0.00
Ventilating $0.00
Electrical $0.00
Asbestos $0.00
Sprinkler $0.00
$0.00
$0.00
$0.00
Column
Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00