Sie sind auf Seite 1von 4

Project:Kashmir Railway Project Date:05-05-2009

SECURITY DEPOSIT RELEASE FORM

1. Name of Work: Execution of water booth at Island platform at


Anantnag Station on Qazigund Baramulla new BG Rail Line Project.

2. Name of Agency: M/S Itoo Construction, Mandole, Anantnag.

3. LOA No: IRCON/J&K-SGR/1008/ Water Booth


Ananatnag/ A-1/19517 ; dt:13.05.2008
4. Date of completion as per LOA: 28-06-2008

5. Actual date of completion: 31-12-2008

6. Date of Final Measurement: 31-12-2009

7. Date Defect Liability Period: 14-02-2009

8. Value of Work as Per LOA: Rs. 3,71,216.72

9. Contractor’s request Letter No:

10. Value of Work after Variation: Rs. 2,80,915.43

11. Security Deposit Deducted: MB No: 1327

Page No CC: Amount:

11 1 Rs. 16,693.00

20 2 Rs. 10,865.00 .
Rs. 27,558.00

Cont………………. Page 2
12. Certificate: Certified that the work has been completed
satisfactorily and certified by ShriSurajit Ghosh, DM/ Civil of Ircon.
100% S.D amount i.e. Rs. 27,558.00 may be released.

13. Certified that the defect liability period is completed and there is no
defect observed during the defect liability period.

(Surajit Ghosh)
DM/ Civil

DGM/Civil

AGM/Civil

JGM/Finance

GM/Srinagar
Project:Kashmir Railway Project Date:05-05-2009

SECURITY DEPOSIT RELEASE FORM

1. Name of Work: Construction of Temporary ramp for Feeding


Ballast at Chainage 21/100 in phase-II on Qazigund Baramulla new BG
Rail Line Project.

2. Name of Agency: M/s Hamid Bin Rashid, R/o Sursona, Batingoo,


Anantnag, Kashmir.

3. LOA No: IRCON/J&K-SGR/1008/ Temporary Ramp/20954


Dt:22.08.2008
4. Date of completion as per LOA: 21-09-2008

5. Actual date of completion: 21-09-2008

6. Date of Final Measurement: 29-09-2008

7. Date Defect Liability Period: 06-11-2008

8. Value of Work as Per LOA: Rs. 4,64,058.13

9. Contractor’s request Letter No:

10. Value of Work after Variation: Rs. 4,97,467.00

11. Security Deposit Deducted: MB No: 1391

Page No CC: Amount:


11 1 Rs. 49,747.00
.
Rs. 49,747.00

Cont………………. Page 2
12. Certificate: Certified that the work has been completed
satisfactorily and certified by ShriSurajit Ghosh, DM/ Civil of Ircon.
100% S.D amount i.e. Rs. 49,747.00 may be released.

13. Certified that the defect liability period is completed and there is no
defect observed during the defect liability period.

(Surajit Ghosh)
DM/ Civil

DGM/Civil

AGM/Civil

JGM/Finance