Beruflich Dokumente
Kultur Dokumente
STATION
Construction – &
Commissioning.
Mr. A. S. DAITHANKAR,
Retd. S.E. MSETCL, Pune
In the last lecture we have seen the lay outs the
positioning of various equipments in the sub stations
also we have seen the equipments in the sub
substations.
Commissioning: -
(1) Check operations of Air pressure switches for
alarm trip, lockouts, compressor operations at
their recommended values.
(2) Check the above operations of gas density
monitor for lockout, trip, operations of breakers.
a) T & P Requirement
i) Oil lank of adequate capacity.
ii) Filter machine of preferably 6 KL/hr circulating
capacity and capable of achieving full vaccume of
5 torrs with main and roots vaccume pumps.
iii) The separate arrangement for evacuation of N2
Gas inside the transformer tank with
simultaneous filtration of oil should be available
on the filter machine.
iv) The filter papers should be cleaned and replaced
if necessary
v) The heaters provided on the filter machine should
be checked
vi) The LT Cable of adequate size to take the load of
filter machine should be laid from ACDB with a
main switch near filter machine.
vii) The rubber hoses, flanges of adequate sizes
should be available to fit on the machine, storage
oil tank and transformer as required.
The oil storage tank, the filter machine should be
properly arranged and AC supply should be
connected to filter machine
viii) The oil BDV tester upto 100 Kv range should be
available.
Oil filling
1. Oil from the sealed barrels should be taken in the
storage tank through filter machine.
2. The oil storage tank should be cleaned from
inside before oil is taken in to it.
3. Once the oil is taken in the storage tank it should
be filtered till the desired values of BDV and water
content as recommended by the manufacturer
are achieved.
4 Once the oil is ready it should be filled in the
transfer tank from the bottom valve and the full
transformer upto desired level in the conservator
including headers, radiators should be filled.
5. The radiators should be flushed with the oil to
remove the dust, foreign material from them if any
before filling the oil.
6. The BDV of the existing oil in the main tank of the
transformer should be checked before oil filling.
7. Now the oil leakage from all the joints should be
check and attended by tightening the nut bolts
Oil filtration
The oil filtration should now be carried out by circulation
of oil through filter machine. The inlet and out let pipes
from machine to transformer should be changed as per
requirement after certain hours.
Oil filling
1) The oil should now be filled in to the transformer
tank under vaccume. The vaccume pulling in the
tank will avoid chances of air getting trapped or
forming pockets. The oil is first filled upto core
level in the main tank through filter machine.
Earth Switch
5) Earth switch usually comparies of a vertical
break switch arm with the contact at the extrem
end and engages with fixed contact fixed on the
post insulator on the line side. They have
saperate operating box and operating system.
Mechanical interlock is provided between main
and earth swithches so that earth switch can be
operated only when main isolator is off and vice
versa.
b) These isolatos are operated form local as well
from remote ends (i.e. pannels) The control wiring
is to be connected accordingly between pannels
and the operating mechanisms of isolators
6. Arcing Horns :-
These are provided for insulation co-ordination.
The use of arcing horns is avoided where the
insulation strength between poles (i.e. phases)
and between two poles of same phases when the
isolator is open, is higher than that between live
points of poles to earth.
7. Construction and commissioning
a) The structure is assemble according to the
drawing provided and levelled properly.
7. C & R Pannels
The C & R Pannels are mounted in control room
the main functions are
a. To control the operations of breakers under
normal and abnormal conditions of system
b. Provide indications of status of equipment's in the
switch yards.
c. To indicate the current in the system, bus voltage,
line voltage, temperature of transformer windings,
oil etc.
d. Measurement of energy through energy meters
e. The annunciation of the fault in the sub station or
any abnormal conditions is seen on the
annunciator facia, alarm for trip and non trip
signal are given
f) Float charger -
i. For providing load current
ii) The trickle charging for battries
j) The float charger is also taken into service and can feed
the load.