PRICE SCHEDULE FOR SUPPLY OF 66 KV SINGLE CIRCUIT

TANSMISSION LINE MATERIALS USING PANTHER


CONDUCTOR ON PER KM BASIS

FINAL - ABSTRACT

Sl.No. Description Amount

1 66 KV SC Line - SUPPLY 2033835.00

2 66 KV SC Line - ERECTION 152470.00

3 CIVIL WORKS 365000.00

GRAND TOTAL 2551305.00

Note : The above estimate is on Per KM basis


Right of way is not included
Any clearence required from forest department is not included in our offer
Supply rates are inclusive of duties & taxes, delevery Ex- Project site
For Erection & Civil works : Service tax prevailing at the time of billing shall be extra to
your account

Cost of 66 KV SC line with Panther Conductor for


approx 2 KMs of Length in Bhayath, Mandvi
Taluk,Bhuj District 5102610.00
PRICE SCHEDULE FOR CIVIL WORKS 0n Per KM Basis
SL.NO. Description Unit Qty Total Unit Total
erection Cost in Rs.
Cost in Rs.
1 2 3 7 8

Foudation of 66 KV DC Towers
including excavation, stub setting ,
concrete, back filling, coping etc
complete. Note:
The quoted foundations are valid for
DFR, WBC & hard rock soil conditions
only. Any other type of soil like fully
submerged etc or any special design of
foundation required is not included in
our offer.
1.1 'A' type Towers Nos. 1 75000 75000
1.1.1 'B' type Towers Nos. 1 85000 85000
1.2 'C' type Towers Nos. 1 95000 95000
1.2.1 'D' type Towers Nos. 1 110000 110000
TOTAL 365000.00

Note : The above estimate is on Per KM basis


Right of way is not included in our offer
Any clearence required from forest department is not included in our offer
PRICE SCHEDULE FOR ERECTION / LABOUR OF 66 KV SINGLE CIRCUIT
TANSMISSION LINE MATERIALS ON PER KM BASIS
Sl.No. Description Unit Qty Unit Total
Rate Amount
in Rs. in Rs.
Fabrication, Proto testing and supply of
66KV galvanised towers as per
1 Kalpatharu designs and drawings
'A' type Towers including stubs MT 1.9
'B' type Towers including stubs MT 3.2
'C' type Towers including stubs MT 4.2
'D' type Towers including stubs MT 5
'D' type 3 mtre extension MT 0.65
Total Weight of Tower Per KM MT 14.95 5800.0 86710.00
Step bolts, bolts and nuts, washers etc.
fully galvanized required for the above
2 towers. MT 0.5 4500.0 2250.00
3 Tower Accessories
a] Phase Plates Nos. 1 60.0 60.00
b] Caution Plates Nos. 1 60.0 60.00
c] Circuit Plates Nos. 1 60.0 60.00
d] Number Plates Nos. 1 60.0 60.00
e] Grounding Sets
I Pipe type Nos. 1 1000.0 1000.00
f] Anti climbing devices Nos. 1 750.0 750.00
g] Earth Bonds
I. 300mm long Nos. 1 110.0 110.00
ii 450mm long Nos. 3 135.0 405.00
4 Conductor and ground wire
PANTHER ACSR Conductor with 1.5%
a] sag. Km 3.15 9000.0 28350.00
Over head ground wire 7/3.15 mm
galvanizes iron, steel, reinforced [with
b] 1.5% sag] Km 1.05 3900.0 4095.00
Insulator with Hardware for PANTHER
5 ACSR conductor
Single Suspension fittings with 4 Nos.
a] 90KN insulators and Hardware. Set 3 200.0 600.00
Single tension fittings with 5 Nos. 90KN
b] insulator and hardware Set 15 200.0 3000.00
Double Suspension fittings with 8 nos. 90
c] KN insulators and hardware.
Double tension fittings with 10 nos. 90 KN
d] insulators and hardware. Set 3 200.0 600.00
Accessories for PANTHER ACSR
6 conductor
a] Mid span compression joint Nos. 1 450.0 450.00
b] Repair Sleeves Nos. 1 115.0 115.00
c] Vibration dampers Nos. 24 140.0 3360.00
d] PG clamp Nos. 18 60.0 1080.00
e] Preformed armour rods Nos. 3 115.0 345.00
Sl.No. Description Unit Qty Unit Total
Rate Amount
in Rs. in Rs.
Hardware and Accessories for
7 Groundwire.
a] Mid span compression joint Nos. 1 340.0 340.00
b] Compression type tension clamp Nos. 6 1690.0 10140.00
c] Suspension clamps Nos. 1 115.0 115.00
d] Repair Sleeves Nos. 1 115.0 115.00
e] PG Clamp Nos. 6 50.0 300.00
8 Check Survey KM 1 8000 8000.00

Total 152470.00

Note : The above estimate is on Per KM basis


Right of way is not included
Any clearence required from forest department is not included in our offer
PRICE SCHEDULE FOR SUPPLY OF 66 KV SINGLE CIRCUIT TANSMISSION LINE
MATERIALS ON PER KM BASIS
Sl.No. Description Unit Qty Unit Total
Rate Amount
in Rs. in Rs.

Fabrication, Proto testing and supply


of 66KV galvanised towers as per
1 Kalpatharu designs and drawings
'A' type Towers including stubs MT 1.9
'B' type Towers including stubs MT 3.2
'C' type Towers including stubs MT 4.2
'D' type Towers including stubs MT 5
'D' type 3 mtre extension MT 0.65
Total Weight of Tower Per KM MT 14.95 82200.0 1228890.00
Step bolts, bolts and nuts, washers
etc. fully galvanized required for the
2 above towers. MT 0.5 125600.0 62800.00
3 Tower Accessories
a] Phase Plates Nos. 1 325.0 325.00
b] Caution Plates Nos. 1 325.0 325.00
c] Circuit Plates Nos. 1 325.0 325.00
d] Number Plates Nos. 1 325.0 325.00
e] Grounding Sets
I Pipe type Nos. 1 4200.0 4200.00
f] Anti climbing devices Nos. 1 5100.0 5100.00
g] Earth Bonds
I. 300mm long Nos. 1 480.0 480.00
ii 450mm long Nos. 3 900.0 2700.00
4 Conductor and ground wire
PANTHER ACSR Conductor with
a] 1.5% sag. Km 3.15 155900.0 491085.00
Over head ground wire 7/3.15 mm
galvanizes iron, steel, reinforced [with
b] 1.5% sag] Km 1.05 45000.0 47250.00
Insulator with Hardware for PANTHER
5 ACSR conductor

Single Suspension fittings with 4 Nos.


a] 90KN insulators and Hardware. Set 3 5050.0 15150.00
Single tension fittings with 5 Nos.
b] 90KN insulator and hardware Set 15 5950.0 89250.00

Double Suspension fittings with 8 nos.


c] 90 KN insulators and hardware. UR 9450.0
Double tension fittings with 10 nos. 90
d] KN insulators and hardware. Set 3 11400.0 34200.00

Sl.No. Description Unit Qty Unit Total


Rate Amount
in Rs. in Rs.
Accessories for PANTHER ACSR
6 conductor
a] Mid span compression joint 1 630.0 630.00
b] Repair Sleeves 1 550.0 550.00
c] Vibration dampers 24 1100.0 26400.00
d] PG clamp 18 650.0 11700.00
e] Preformed armour rods 3 900.0 2700.00
Hardware and Accessories for
7 Groundwire.
a] Mid span compression joint 1 320.0 320.00
b] Compression type tension clamp 6 950.0 5700.00
c] Suspension clamps 1 950.0 950.00
d] Repair Sleeves 1 320.0 320.00
e] PG Clamp 6 360.0 2160.00

Total 2033835.00

Note : The above estimate is on Per KM basis


Right of way is not included in our offer
Any clearence required from forest department is not included in our offer