R E P O R T I N G

L I V E F R O M T H E
F I E L D


S T A T U S O F W O R K P R O G R E S S
A S O N
1 2 / 0 7 / 2 0 1 4










BLOCK BLOCK BLOCK BLOCK A AA A



BLOCK BLOCK BLOCK BLOCK B BB B





BLOCK BLOCK BLOCK BLOCK C CC C






BLOCK BLOCK BLOCK BLOCK D DD D



BLOCK BLOCK BLOCK BLOCK E EE E



BLOCK BLOCK BLOCK BLOCK F FF F




BLOCK BLOCK BLOCK BLOCK G GG G




AMENITIES BLOCK AMENITIES BLOCK AMENITIES BLOCK AMENITIES BLOCK GROUND & FIRST FLOOR BLOCK WORKS & GROUND & FIRST FLOOR BLOCK WORKS & GROUND & FIRST FLOOR BLOCK WORKS & GROUND & FIRST FLOOR BLOCK WORKS &
PLASTERING FINISHES PLASTERING FINISHES PLASTERING FINISHES PLASTERING FINISHES IN PROGRESS IN PROGRESS IN PROGRESS IN PROGRESS


AMENITIES BLOCK AMENITIES BLOCK AMENITIES BLOCK AMENITIES BLOCK BLOCK WORKS & PLASTERING FINISHES BLOCK WORKS & PLASTERING FINISHES BLOCK WORKS & PLASTERING FINISHES BLOCK WORKS & PLASTERING FINISHES IN IN IN IN
PROGRESS PROGRESS PROGRESS PROGRESS




RAMP SIDE R.C WALL WORKS & COMPOUND WALL PAINTING WORKS RAMP SIDE R.C WALL WORKS & COMPOUND WALL PAINTING WORKS RAMP SIDE R.C WALL WORKS & COMPOUND WALL PAINTING WORKS RAMP SIDE R.C WALL WORKS & COMPOUND WALL PAINTING WORKS
IN PROGRESS IN PROGRESS IN PROGRESS IN PROGRESS



COMPOUND WALL PAINTING WORKS & PERIPHERAL LANDSCAPE COMPOUND WALL PAINTING WORKS & PERIPHERAL LANDSCAPE COMPOUND WALL PAINTING WORKS & PERIPHERAL LANDSCAPE COMPOUND WALL PAINTING WORKS & PERIPHERAL LANDSCAPE
WORKS WORKS WORKS WORKS IN PROGRESS IN PROGRESS IN PROGRESS IN PROGRESS




CENTRE COURT YARD CENTRE COURT YARD CENTRE COURT YARD CENTRE COURT YARD WATER FEATURE BODY WORKS WATER FEATURE BODY WORKS WATER FEATURE BODY WORKS WATER FEATURE BODY WORKS IN PROGRESS IN PROGRESS IN PROGRESS IN PROGRESS



STATUS OF FINISHING WORKS


AMIGO BLOCK

INTERNAL 1
ST
COAT PAINTING COMPLETED
DOOR FRAMES FIXING COMPLETED
DOOR SHUTTERS FIXING IN PROGRESS
MARBLE 3
RD
AND 4
TH
COAT POLISH IN PROGRESS
TILING WORKS IN ALL BATH ROOMS COMPLETED
TILING WORKS IN KITCHEN & UTILITY COMPLETED
CORNICE WORKS COMPLETED
WINDOWS FIXING COMPLETED
TOILET FALSE CEILING WORKS GRID CEILING WORKS COMPLETED
KITCHEN GRANITE COUNTER FIXING IN PROGRESS
LIFT LOBBY FINISHING WORKS - IN PROGRESS
LIFT INSTALLATION IN PROGRESS
EXTERNAL TEXTURE PAINTING - IST COAT COMPLETED

BELLAMY BLOCK

TERRACE OVER HEAD TANK FINISHING WORKS - COMPLETED
EXTERNAL PLASTERING WORK - UNDER PROGRESS. 90% COMPLETED
MARBLE LAYING WORKS COMPLETED UPTO 14
TH
FLOOR, PENTHOUSE IS IN PROGRESS
BATHROOM/KITCHEN TILING WORKS ARE IN PROGRESS
CEILING PAINTING WORKS ARE IN PROGRESS
STAIRS GRANITE FLOOR WORKS COMPLETED
STAIRS M.S RAILING WORKS - COMPLETED
TOILETS MARBLE COUNTER FIXING IN PROGRESS
UNITS ELECTRICAL WIRING STARTED
FIRE SAFETY WORKS COMPLETED UPTO 11
TH
FLOOR
WINDOWS FIXING IN PROGRESS
BALCONY S.S RAILING FIXING & GRANITE COPING WORKS - IN PROGRESS



RAYA BLOCK

INTERNAL 1
ST
COAT PAINTING COMPLETED
DOOR FRAMES FIXING COMPLETED
DOOR SHUTTERS FIXING IN PROGRESS
TILING WORKS AT ALL THE BATH ROOMS COMPLETED
TILING WORKS AT KITCHEN & UTILITY COMPLETED
CORNICE WORKS COMPLETED
WINDOWS FIXING COMPLETED
TOILET FALSE CEILING WORKS GRID CEILING WORKS COMPLETED
LIFT LOBBY FINISHING WORKS ARE IN PROGRESS
LIFT INSTALLATION IN PROGRESS

BONARO BLOCK

TERRACE OVER HEAD TANK FINISHING WORKS - COMPLETED
EXTERNAL PLASTERING WORK - UNDER PROGRESS. 93% COMPLETED
MARBLE LAYING WORKS COMPLETED UPTO 14
TH
FLOOR, PENTHOUSE IS IN PROGRESS
BATHROOM/KITCHEN TILING WORKS ARE IN PROGRESS
CEILING PAINTING WORKS ARE IN PROGRESS
STAIRS GRANITE FLOOR WORKS COMPLETED
STAIRS M.S RAILING WORKS - COMPLETED
TOILETS MARBLE COUNTER FIXING IN PROGRESS
UNITS ELECTRICAL WIRING STARTED
FIRE SAFETY WORKS COMPLETED UPTO 14
TH
FLOOR
WINDOWS FIXING IN PROGRESS
BALCONY S.S RAILING FIXING & GRANITE COPING WORKS - IN PROGRESS
TERRACE WATERPROOFING WORKS ARE IN PROGRESS






KADIN BLOCK

INTERNAL 1
ST
COAT PAINTING COMPLETED
DOOR FRAMES FIXING COMPLETED
DOOR SHUTTERS FIXING IN PROGRESS
MARBLE 3
RD
AND 4
TH
COAT POLISH IN PROGRESS
TILING WORKS AT ALL THE BATH ROOMS COMPLETED
TILING WORKS AT KITCHEN & UTILITY COMPLETED
CORNICE WORKS COMPLETED
WINDOWS FIXING COMPLETED
TOILET FALSE CEILING WORKS GRID CEILING WORKS COMPLETED
KITCHEN GRANITE COUNTER FIXING IN PROGRESS
LIFT LOBBY FINISHING WORKS ARE IN PROGRESS
LIFT INSTALLATION IN PROGRESS
EXTERNAL TEXTURE PAINTING 1
ST
COAT IN PROGRESS


CARA BLOCK

TERRACE OVER HEAD TANK FINISHING WORKS - COMPLETED
EXTERNAL PLASTERING WORK COMPLETED
MARBLE LAYING WORKS COMPLETED UPTO 14
TH
FLOOR, PENTHOUSE IS IN PROGRESS
BATHROOM/KITCHEN TILING WORKS ARE IN PROGRESS 90% COMPLETED
CEILING PAINTING WORKS ARE IN PROGRESS
STAIRS GRANITE FLOOR WORKS COMPLETED
STAIRS M.S RAILING WORKS - COMPLETED
TOILETS MARBLE COUNTER FIXING IN PROGRESS
UNITS ELECTRICAL WIRING IN PROGRESS
FIRE SAFETY WORKS COMPLETED UPTO 14
TH
FLOOR
WINDOWS FIXING IN PROGRESS
EXTERNAL PAINTING WORKS IN PROGRESS
BALCONY S.S RAILING BASE PLATES FIXING & GRANITE COPING - IN PROGRESS

SUHUBA BLOCK

INTERNAL 1
ST
COAT PAINTING COMPLETED
DOOR FRAMES FIXING COMPLETED
DOOR SHUTTERS FIXING IN PROGRESS
MARBLE 3
RD
AND 4
TH
COAT POLISH IN PROGRESS
TILING WORKS AT ALL THE BATH ROOMS COMPLETED
TILING WORKS AT KITCHEN & UTILITY COMPLETED
CORNICE WORKS COMPLETED
WINDOWS FIXING COMPLETED
TOILET FALSE CEILING WORKS AND GRID CEILING WORKS COPMLETED
KITCHEN GRANITE COUNTER FIXING IN PROGRESS
LIFT LOBBY FINISHING WORKS ARE IN PROGRESS
LIFT INSTALLATION IN PROGRESS
EXTERNAL TEXTURE PAINTING IST COAT COMPLETED.

PODIUM


PODIUM CENTRE COURTYARD FOCAL TREE YARD RETAINING WALL COMPLETED

OTHER EXTERNAL DEVELOPMENT WORKS:


SEWERAGE TREATMENT PLANT STRUCTURE WORKS - COMPLETED
COMPOUND WALL WORK - ON SOUTH & EAST SIDE - COMPLETED
BASEMENT RAINWATER COLLECTION PITS 4 NOS. - COMPLETED

BASEMENT FLOOR ANTI TERMITE TREATMENT WORKS, SOLING WORKS & PCC WORKS
ARE COMPLETED

BASEMENT FLOOR DRAIN WORKS ARE IN PROGRESS

BASEMENT ELECTRICAL CABLE TRAY WORKS IN PROGRESS

BASEMENT FIRE SAFETY RING MAIN WORKS ARE IN PROGRESS

AMENITY BLOCK STRUCTURAL WORKS COMPLETED UPTO TERRACE,
BLOCK WORKS AND PLASTER FINISHES ARE IN PROGRESS

CLUB HOUSE FIRST FLOOR SLAB SHUTTERING WORKS ARE IN PROGRESS

SWIMMING POOL- R.C BASE SLAB AND SIDE WALL CONSTRUCTION IN PROGRESS

PODIUM WATERPROOING WORKS AND LANDSCAPE WORKS IN PROGRESS



Vaswani Group