S.

No Description Completion date


Switchyard
1 Supply and installation of capacitors 31/12/12
2 S&I of HT cables and termination 5/1/13
3 S&I of windows in control room 25/01/13
4 TNEB portion of switchyard works 25/01/2013
5 TNEB metering room construction 25/01/2013
6 TNEB tower erection works 25/01/2013
7 HT cable works from Transformer to Panel board 8/1/13
8 Testing and pre commissioning of EHT and HT system 30/01/2013
9 Gate works + fencing works 8/1/13
Downstream works
10
HT cable works from HT Panel board to Soft starters and LBS panels
10/1/13
11 630 KVA transformer earthing 10/1/13
12
630 KVA transformer cabling and termination - Primary and secondary
10/1/13
13 S&I of of Main panel, SSB, MCC,MLSB and APFC panel 30/01/2013
14 Cabling between main panel and sub panels 10/1/13
15 Equipment cabling and termination 20/01/2013
16 Earthing for plant 20/01/2013
Timing plan for balance works as on 25.12.12