Proposed Office Building

ID Task Name Duration Start Finish 09 07 Dec '09 14 Dec '09 21 Dec '09
W T F S S M T W T F S S M T W T F S S M T W T F S S
1 Design Lead in 20 days Mon 04/01/10 Fri 29/01/10
2 Receipt of Order 1 day? Mon 04/01/10 Mon 04/01/10
3 Place Order for Steel 1 day? Mon 04/01/10 Mon 04/01/10
4 Place Order for Long lead in items 1 day? Mon 04/01/10 Mon 04/01/10
5 Site clearance, removal of client materials
3 days Tue 05/01/10 Thu 07/01/10
6 Site investigation for old services/CAT 1Scan
day?of area
Thu 07/01/10 Thu 07/01/10
7 Set up site 4 days Fri 08/01/10 Wed 13/01/10
8 Breaking up of existing pavings to construct
14 daysnew Thu
car park
14/01/10 Tue 02/02/10
9 Ground improvement works 10 days Wed 03/02/10 Tue 16/02/10
10 Setting out of site 10 days Wed 17/02/10 Tue 02/03/10
11 Excavation works to reduce levels, for10foundations
days Wed / ground
03/03/10
beamsTue 16/03/10
12 Install new drainage 10 days Wed 17/03/10 Tue 30/03/10
13 Foundations for steel frame 10 days Wed 31/03/10 Tue 13/04/10
14 Erection of steel frame 5 days Wed 14/04/10 Tue 20/04/10
15 Intumescent Paint to Steel 5 days Wed 21/04/10 Tue 27/04/10
16 Install Bison Beams 5 days Wed 28/04/10 Tue 04/05/10
17 Erect Scaffold for Bricklayers 5 days Wed 05/05/10 Tue 11/05/10
18 Construction of external walls To Building
12 days Wed 12/05/10 Thu 27/05/10
19 Form Ground Floor slab/Power float 2 days Fri 28/05/10 Mon 31/05/10
20 Construct internal walls/Partitions 5 days Tue 01/06/10 Mon 07/06/10
21 Screed to Floors 2 days Tue 08/06/10 Wed 09/06/10
22 Fire protection to all voids/ penetrations
5 days Thu 10/06/10 Wed 16/06/10
23 Plaster to internal walls/partitons 3 days Thu 17/06/10 Mon 21/06/10
24 Adapt scaffold for roof works 3 days Tue 22/06/10 Thu 24/06/10
25 Construction of roof/rainwater Pipes 10 days Fri 25/06/10 Thu 08/07/10
26 Install man safe system to roof 2 days Fri 09/07/10 Mon 12/07/10
27 Mechanical and Electrical first fix 20 days Tue 13/07/10 Mon 09/08/10
28 Adapt scaffold for windows and curtain7walling
days Tue 10/08/10 Wed 18/08/10
29 Curtain walling / windows and doors 8 days Thu 19/08/10 Mon 30/08/10

Task Milestone External Tasks


Project: Proposed Office & Amenity Bl
Split Summary External Milestone
Date: Wed 02/12/09
Progress Project Summary Deadline

Page 1
Proposed Office Building
ID Task Name Duration Start Finish 09 07 Dec '09 14 Dec '09 21 Dec '09
W T F S S M T W T F S S M T W T F S S M T W T F S S
30 Drop scaffold 2 days Tue 31/08/10 Wed 01/09/10
31 Canopy to front entrance 5 days Thu 02/09/10 Wed 08/09/10
32 Spiral stair case to side elevation 3 days Thu 09/09/10 Mon 13/09/10
33 Install ceilings 3 days Tue 14/09/10 Thu 16/09/10
34 Demountable partitions 3 days Fri 17/09/10 Tue 21/09/10
35 Painting to all walls / skirtings / ceilings5 days Wed 22/09/10 Tue 28/09/10
36 Floor coverings 5 days Wed 29/09/10 Tue 05/10/10
37 Internal fixtures, fitting, finishes 11 days Wed 06/10/10 Wed 20/10/10
38 Install kitchen units 3 days Thu 21/10/10 Mon 25/10/10
39 Tiling to all areas 4 days Tue 26/10/10 Fri 29/10/10
40 Mechanical and Electrical 2nd fix 6 days Mon 01/11/10 Mon 08/11/10
41 New drainage to building 5 days Tue 09/11/10 Mon 15/11/10
42 New services to building 5 days Tue 16/11/10 Mon 22/11/10
43 Final fix Electrical & Mechanical 4 days Tue 23/11/10 Fri 26/11/10
44 Install Lift 3 days Mon 29/11/10 Wed 01/12/10
45 Form new car park 7 days Thu 02/12/10 Fri 10/12/10
46 New drainage to car park 3 days Mon 13/12/10 Wed 15/12/10
47 Finish to Car Park/White Lining 5 days Thu 16/12/10 Wed 22/12/10
48 Brickwork retaining walls, steps and paving
3 daysworks
Mon 03/01/11 Wed 05/01/11
49 Install new entry gates 3 days Thu 06/01/11 Mon 10/01/11
50 External works / Planting 3 days Tue 11/01/11 Thu 13/01/11
51 Blockwork to externals / Remedials 5 days Fri 14/01/11 Thu 20/01/11
52 Commisioning 2 days Thu 21/01/10 Fri 22/01/10
53
54 Client fit out / Training 37 days Wed 01/12/10 Thu 20/01/11

Task Milestone External Tasks


Project: Proposed Office & Amenity Bl
Split Summary External Milestone
Date: Wed 02/12/09
Progress Project Summary Deadline

Page 2
Proposed Office Building
28 Dec '09 04 Jan '10 11 Jan '10 18 Jan '10 25 Jan '10 01 Feb '10 08 Feb '10
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

04/01
04/01
04/01

Task Milestone External Tasks


Project: Proposed Office & Amenity Bl
Split Summary External Milestone
Date: Wed 02/12/09
Progress Project Summary Deadline

Page 3
Proposed Office Building
28 Dec '09 04 Jan '10 11 Jan '10 18 Jan '10 25 Jan '10 01 Feb '10 08 Feb '10
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Milestone External Tasks


Project: Proposed Office & Amenity Bl
Split Summary External Milestone
Date: Wed 02/12/09
Progress Project Summary Deadline

Page 4
Proposed Office Building
15 Feb '10 22 Feb '10 01 Mar '10 08 Mar '10 15 Mar '10 22 Mar '10 29 Mar '10
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Milestone External Tasks


Project: Proposed Office & Amenity Bl
Split Summary External Milestone
Date: Wed 02/12/09
Progress Project Summary Deadline

Page 5
Proposed Office Building
15 Feb '10 22 Feb '10 01 Mar '10 08 Mar '10 15 Mar '10 22 Mar '10 29 Mar '10
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Milestone External Tasks


Project: Proposed Office & Amenity Bl
Split Summary External Milestone
Date: Wed 02/12/09
Progress Project Summary Deadline

Page 6
Proposed Office Building
05 Apr '10 12 Apr '10 19 Apr '10 26 Apr '10 03 May '10 10 May '10 17 May '10
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Milestone External Tasks


Project: Proposed Office & Amenity Bl
Split Summary External Milestone
Date: Wed 02/12/09
Progress Project Summary Deadline

Page 7
Proposed Office Building
05 Apr '10 12 Apr '10 19 Apr '10 26 Apr '10 03 May '10 10 May '10 17 May '10
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Milestone External Tasks


Project: Proposed Office & Amenity Bl
Split Summary External Milestone
Date: Wed 02/12/09
Progress Project Summary Deadline

Page 8
Proposed Office Building
24 May '10 31 May '10 07 Jun '10 14 Jun '10 21 Jun '10 28 Jun '10 05 Jul '10
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Milestone External Tasks


Project: Proposed Office & Amenity Bl
Split Summary External Milestone
Date: Wed 02/12/09
Progress Project Summary Deadline

Page 9
Proposed Office Building
24 May '10 31 May '10 07 Jun '10 14 Jun '10 21 Jun '10 28 Jun '10 05 Jul '10
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Milestone External Tasks


Project: Proposed Office & Amenity Bl
Split Summary External Milestone
Date: Wed 02/12/09
Progress Project Summary Deadline

Page 10
Proposed Office Building
12 Jul '10 19 Jul '10 26 Jul '10 02 Aug '10 09 Aug '10 16 Aug '10 23 Aug '10
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Milestone External Tasks


Project: Proposed Office & Amenity Bl
Split Summary External Milestone
Date: Wed 02/12/09
Progress Project Summary Deadline

Page 11
Proposed Office Building
12 Jul '10 19 Jul '10 26 Jul '10 02 Aug '10 09 Aug '10 16 Aug '10 23 Aug '10
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Milestone External Tasks


Project: Proposed Office & Amenity Bl
Split Summary External Milestone
Date: Wed 02/12/09
Progress Project Summary Deadline

Page 12
Proposed Office Building
30 Aug '10 06 Sep '10 13 Sep '10 20 Sep '10 27 Sep '10 04 Oct '10 11 Oct '10
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Milestone External Tasks


Project: Proposed Office & Amenity Bl
Split Summary External Milestone
Date: Wed 02/12/09
Progress Project Summary Deadline

Page 13
Proposed Office Building
30 Aug '10 06 Sep '10 13 Sep '10 20 Sep '10 27 Sep '10 04 Oct '10 11 Oct '10
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Milestone External Tasks


Project: Proposed Office & Amenity Bl
Split Summary External Milestone
Date: Wed 02/12/09
Progress Project Summary Deadline

Page 14
Proposed Office Building
18 Oct '10 25 Oct '10 01 Nov '10 08 Nov '10 15 Nov '10 22 Nov '10 29 Nov '10
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Milestone External Tasks


Project: Proposed Office & Amenity Bl
Split Summary External Milestone
Date: Wed 02/12/09
Progress Project Summary Deadline

Page 15
Proposed Office Building
18 Oct '10 25 Oct '10 01 Nov '10 08 Nov '10 15 Nov '10 22 Nov '10 29 Nov '10
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Milestone External Tasks


Project: Proposed Office & Amenity Bl
Split Summary External Milestone
Date: Wed 02/12/09
Progress Project Summary Deadline

Page 16
Proposed Office Building
06 Dec '10 13 Dec '10 20 Dec '10 27 Dec '10 03 Jan '11 10 Jan '11 17 Jan '11
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Milestone External Tasks


Project: Proposed Office & Amenity Bl
Split Summary External Milestone
Date: Wed 02/12/09
Progress Project Summary Deadline

Page 17
Proposed Office Building
06 Dec '10 13 Dec '10 20 Dec '10 27 Dec '10 03 Jan '11 10 Jan '11 17 Jan '11
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Milestone External Tasks


Project: Proposed Office & Amenity Bl
Split Summary External Milestone
Date: Wed 02/12/09
Progress Project Summary Deadline