75%(8)75% fanden dieses Dokument nützlich (8 Abstimmungen)
3K Ansichten55 Seiten
A basement excavation is a construction dig. There are several common method of excavation, in order to build basement. Essential that the excavation is adequately supported, and the groundwater properly controlled.
A basement excavation is a construction dig. There are several common method of excavation, in order to build basement. Essential that the excavation is adequately supported, and the groundwater properly controlled.
A basement excavation is a construction dig. There are several common method of excavation, in order to build basement. Essential that the excavation is adequately supported, and the groundwater properly controlled.
SAKINAH KHALIDAH BINTI KAHARUDDIN SITI NADIRAH BINTI JAMIL Definition Basement: A basement excavation is a construction dig.
There are several common method of excavation, in order to build basement.
Essential that the excavation is adequately supported, and the groundwater properly controlled. Subsoil conditions and ground water level
Working space requirements and site constraints Maintenance of the wall and support system in permanent condition
Cost and times of construction
Local experience and available construction plant
TYPES OF EXCAVATION FOR BASEMENT CONSTRUCTIO N DIAPHRAGM WALL SHEET PILE WALL CONTIGUOUS BORED PILES WALL SECANT PILES
a form of driven piling using thin interlocking sheets of steel. Used vibrating hammer, t-crane and crawler drilling to establish it suitable for sites where the space around the excavation is insufficient for sloping back the sides SHEET PILE WALL SHEET PILE WALL It consist of rolled steel sections with interlocking edge joints The interlocking edges allow each sheet pile to slide into the next with relative ease.
1) POSITION OF STEEL 2) INSTALLATION OF FIRST SHEET PILE 3) INSTALLALTION OF SECOND SHEET PILE 4) REPITATION OF PROCESS
5) EXTENSION OF SHEET PILE Examples of Sheet Pile ADVANTAGES DISADVANTAGES Rapid installation Direct driving effect on the subsoil Steel can be either permanent or recovered Noisy very economical compare with the alternative of a diaphragm wall High capital investment if re- usage is restricted Seal may not be perfect Constructed by excavation in a trench which temporarily supported by bentonite slurry. Suitable for : sites where obstructions in the ground prevent sheet piles from being driven where the occurrence of groundwater is unfavorable for other methods of support. Also suitable for sites where considerations of noise and vibration On reaching founding level steel reinforcement is lowered into the trench, followed by concrete to displace the bentonite DIAPHRAGM WALL
2 ) Excavation of Panel 2. EXCAVATE TRENCH Examples of Diaphragm Wall ADVANTAGES DISADVANTAGES Permanent basement wall A lot of labour is needed Scan be designed to form part of a permanent foundation Long period of construction Minimum vibration and noise High cost Can be used in restricted space line of bored pile installed close together or touching.
Smaller diameter micro-pile may be installed in between each adjacent pile.
Gaps between the micro-pile and main piles are grouted.
1). POSITION OF BORED PILE
2) INSTALLATION OF CASING VIBRO HAMMER
3) AUGERING OF BORE PILE 4) INSTALLATION OF STEEL CAGE 5) CONCRETING OF BORE HOLE 6) EXTRACTION 7) REPITATION OF PRECESS Examples of Contiguous Bored Pile Advantages
Disadvantages
Built-up areas where noise and vibration should be limited
Concrete in shaft susceptible to squeezing or necking in soft soil where conventional types are used
In industrial complexes where access, headroom and/or restriction on vibration may make other methods such as steel sheet piling or diaphragm walling less suitable
Special techniques needed for concreting in water bearing soils
Lower cost
Concrete can be readily inspected after installation
Speed in construction for temporary and permanent wall where drilling conditions are conducive
Drilling a number of pile in group may cause loss of ground and settlement of adjacent structures
Higher capacity to overcome obstruction like rock compare to other system
Additional work are needed to form an acceptable surface to the wall
Drilling tools can be break up boulders or other obstructions
Lack of water tightness similar to contiguous bored piles except that they are constructed in: - male - female
interlock each other. male piles are reinforced while the female piles are not. In cases where lateral pressure from the soil is excessively high, male-male secant piles may be used.
1. CONSTRUCT A GUIDE WALL 2. INSTALLATION OF STEEL CASING 3) AUGERING OF PRIMARY BOREHOLES 4) CONCRETING OF PRIMARY BOREHOLES 5) AUGERING OF SECONDARY BOREHOLES 6) INSTALLATION OF STEEL CAGE 7) CONCRETING OF SECONDARY BOREHOLE 8) REPITATION OF PROCESS Example Secant Pile..
Advantages
Disadvantages
- Provide higher degree of water tightness
- High cost for installation
- Stronger resistance to lateral pressure
- Ensuring complete contact of all piles over their full length
- Can be used on small and confined sites
- May be difficult in practice
- Suitable to built near building, roads and other sensitive structures
- Minimum noise and vibration CASE STUDY CONTRACT TITTLE Purpose to build 33 storey office tower developed by KL Sentral & MRCB for Lembaga Tabung Haji
SCOPE OF WORKS 1 BLOCK OFFICE WHICH CONSISTS OF : - 3 levels of basement parking - 2 levels of Main lobbies - 5 levels of elevated car parks - 1 level of M&E Floor - 20 levels of Offices - 2 levels of Penthouse
PROJECT BRIEFING - Location of site : KL Sentral - Located at congested area ( Putra,KTM,Erl station,shop lots building, private parking area,hotel, office building, etc ) - The land is existed flat - According to soil engineer, type of soil consist : sandy clay, silty clay, silty sand, shale and shale rock. - It was busy area within working hours
NATURE OF SITE METHOD STATEMENT OF BASEMENT WORKS SURVEY STAGE - Land surveyor play their role the original ground level and set out control point
SITE CLEARING - demolition of existing building small shop building - grubbing out bushes, trees and removal soil to reduce level - After site clear - hoarding, wash trough, storage and temporary site office CONSTRUCTION OF DIAPHRAGM WALL AND CONTIGUOUS BORED PILE
- two type of retaining wall has decided by engineer diaphragm wall and contiguous bored pile. - use existing diaphragm wall save cost and limited space ( refer layout plan) - reason : if build new diaphragm wall, ground anchor fixed to diaphragm wall will disturbed the foundation of existing building - use contiguous bored piled - For perimeter area did not have existing building - Bored piled : - total used : 260 nos - size : 750 mm - depth : 16 m - gap : 75 mm - use helical reinforcement - I machine can build only 2 bored pile in one day have 4 machine at site - after completion, use concrete 200 mm thk as skin wall + waterproofing - advantages using contig.bored pile : It is free standing didnt use anchor EXCAVATION - after completion of diaphragm wall and contiguous bored pile, excavate basement. - excavate 10.00 m depth - use 1m3 bucket excavator. - ramp system purpose of transportation loading and unloading construction material.( refer figure 5.19 ) - the ramp will remove after excavation process. - temporary opening entering excavation area ( refer figure 5.20 ) CONSTRUCTION TECHNOLOGY IV - BASEMENT CONSTRUCTION BASEMENT FOUNDATION
- use raft foundation as a foundation - depth : 2.75 m - size of reinforcement : 25 mm , 32 mm - concreting process concrete + ice cube low the temperature - reason use raft foundation : - carry a great load - soil hard material at site View 1 raft foundation construction View 5 Concreting of raft in progress View 6 completion of concreting Raft foundation CONSTRUCTIONN OF BASEMENT FRAME AND STRUCTURE
- method of construction : bottom up method ( refer figure below ) - starting by construction of basement column - start from B1 - B2 B3 - construction including concrete, formwork , reinforcement Construction of Basement Frame BACKFILLING - after completion of basement frame backfilling process - backfilling process by stage - after completion of B3, contractor constructing B2 level backfilling process proceed at level B3 - repeat backfilling sequence until upper level Backfilling the remaining excavated area COMPLETE BASEMENT - after backfilling process structural work for basement completely finished - proceed upper level construction floor , wall, etc. Complete Basement This property is a detached Victorian house in Hampstead, which had no existing cellar, a timber suspended floor and an existing partial lower ground floor. London Basement were asked to carry out the construction of a basement below the house and rear and side patios, creating an area of 196M (2109 sq.ft.), with a head height of 3M below the house and 2.9M below the patios. As you will see from the artists rendition, the majority of the basement space was to be used as an Art Gallery. The property had a part timber suspended, part solid floor and our clients lived in the property throughout the works, which took approx. 30 weeks. Two conveyors belts were installed from the areas of excavation into the skip situated on the road. Initially we carried out the design and installation of the temporary works required to support the existing building structure. This involved the installation of a series of cantilever needle beams passing through the external walls, at critical load points, supported on temporary compression piles placed adjacent to the external walls. This enabled us to be able to break out the existing foundations and replace them with the new designed steel support system. Whichever method supporting basement chosen and any consideration will have to be given to additional measures to achieve good performance corresponding to modern consumer expectations.