0 Reference Document and Drawing


SCR No. T 378523
2650813-M13-021-A Rev. 0 ITR Battery Room Exhaust Fan

2.0 Scope of Work
Supply and install one lot of exhaust air duct work for Battery Room according to given
reference drawing with following works and specification :-
All duct work will be fabricated with 5 mm thickness carbon steel material and hot
dipped galvanized after fabrication,
All welds to be 6 mm double continuous fillet,
The flange shall be according to ISO 15138: 2007 standard,
Installation of one unit of client supplied exhaust air fan,
Material thickness other components shall be according to reference drawing
2650813-M13-021-A Rev. 0