Activity ID Activity Name Remaining

Duration
Start Finish Total
Float
DONGGI COMMISSIONING (2 Month Scheme) DONGGI COMMISSIONING (2 Month Scheme)
203d 12-Jun-15 31-Dec-15 0d
MILESTONE MILESTONE
126d 28-Aug-15 31-Dec-15 0d
A1450 FLOWLINE SYSTEM READY FOR GAS IN 0d 28-Aug-15 126d
A1440 GAS IN 0d 05-Nov-15 0d
A1340 OPERATIONAL ACCEPTANCE 0d 31-Dec-15 0d
FACILITIES FACILITIES
182d 12-Jun-15 10-Dec-15 21d
TEMPORARYPOWER GENERATION TEMPORARYPOWER GENERATION 84d 12-Jun-15 03-Sep-15 119d
A1000 Temporary Power Generation ~30kW 7d 12-Jun-15 18-Jun-15 0d
A1350 Temporary Power Generation ~500kW 7d 26-Jun-15 02-Jul-15 182d
A1380 Temporary Power Generation ~2000kW 7d 28-Aug-15 03-Sep-15 49d
PERMANENT POWER GENERATION PERMANENT POWER GENERATION 49d 23-Oct-15 10-Dec-15 14d
A1120 Energize GTG A(Fuel) 14d 23-Oct-15 05-Nov-15 14d
A1130 Energize GTG B 7d 27-Nov-15 03-Dec-15 0d
A1140 Energize GTG C 7d 27-Nov-15 03-Dec-15 0d
A1150 Energize GTG D 7d 04-Dec-15 10-Dec-15 7d
A1530 Energize GTG A(With HP Fuel Gas) 7d 04-Dec-15 10-Dec-15 14d
MCC/SWITCHGEAR MCC/SWITCHGEAR 21d 19-Jun-15 09-Jul-15 0d
A1010 Pre-Test Switch Gear/ MCC 14d 19-Jun-15 02-Jul-15 0d
A1360 Energize MCC/ Switchgear 7d 03-Jul-15 09-Jul-15 0d
SUPPORT FACILITIES SUPPORT FACILITIES 21d 03-Jul-15 23-Jul-15 161d
A1040 Energize HVAC 7d 03-Jul-15 09-Jul-15 49d
A1020 Energize UPS/ Battery 7d 10-Jul-15 16-Jul-15 49d
A1030 Energize Lighting, Telecommunication & Other Facilities 7d 17-Jul-15 23-Jul-15 161d
DCS/SIS & F&G DCS/SIS & F&G 28d 17-Jul-15 13-Aug-15 49d
A1050 Energize DCS/SIS & ESD/ F&G 28d 17-Jul-15 13-Aug-15 49d
PRECOMMISSIONING PRECOMMISSIONING
105d 24-Jul-15 05-Nov-15 56d
PUMP TEST PUMP TEST 91d 24-Jul-15 22-Oct-15 0d
A1420 Individual Pump Test Run 91d 24-Jul-15 22-Oct-15 0d
FIELD INSTRUMENT TEST & FUNCTION TEST FIELD INSTRUMENT TEST & FUNCTION TEST 84d 14-Aug-15 05-Nov-15 49d
A1370 Field Instrument Test 84d 14-Aug-15 05-Nov-15 49d
A1430 Functional Test/ Trip Test 56d 11-Sep-15 05-Nov-15 0d
CHEMICAL CLEANING CHEMICAL CLEANING 49d 04-Sep-15 22-Oct-15 49d
A1390 Chemical Cleaning AGRU 14d 04-Sep-15 17-Sep-15 49d
A1400 Chemical Cleaning BSRU 28d 25-Sep-15 22-Oct-15 49d
PIPING PRECOMMISSIONING PIPING PRECOMMISSIONING 84d 07-Aug-15 29-Oct-15 63d
A1490 Flushing/ Blowing 70d 07-Aug-15 16-Oct-15 63d
A1500 N2 Purging 35d 25-Sep-15 29-Oct-15 63d
SYSTEM SYSTEM
168d 10-Jul-15 24-Dec-15 7d
COMMISSIONING PREPARATION COMMISSIONING PREPARATION 49d 23-Oct-15 10-Dec-15 21d
A1460 Chemical Preparation AGRU 7d 23-Oct-15 29-Oct-15 49d
A1470 Chemical Preparation DPCU 7d 23-Oct-15 29-Oct-15 49d
A1560 Chemical Preparation DHU 7d 23-Oct-15 29-Oct-15 49d
A1480 Fill Up Raw Water BSRU 14d 30-Oct-15 12-Nov-15 49d
A1540 Chemical Preparation BSRU (Incld Bactery) 7d 04-Dec-15 10-Dec-15 0d
UTILITY UTILITY 140d 10-Jul-15 26-Nov-15 35d
A1070 Commissioning Fire Water System 14d 10-Jul-15 23-Jul-15 161d
A1060 Commisioning UtilityAir & Instrument Air 7d 21-Aug-15 27-Aug-15 49d
A1080 Commissioning Water Treatment System 7d 28-Aug-15 03-Sep-15 49d
A1090 Commissioning N2 Generation System 7d 04-Sep-15 10-Sep-15 77d
A1410 Commissioning Cooling Water 7d 25-Sep-15 01-Oct-15 91d
A1011 Commissioning LP & HP Flare (Pilot by LPG) 14d 30-Oct-15 12-Nov-15 49d
A1250 Commissioning Condensate System 7d 06-Nov-15 12-Nov-15 35d
A1260 Commissioning Produce Water System 7d 06-Nov-15 12-Nov-15 35d
A1160 Produce LP Fuel Gas System 7d 13-Nov-15 19-Nov-15 0d
A1510 Commissioning Hot Oil 7d 13-Nov-15 19-Nov-15 35d
A1520 Produce HP Fuel Gas System 7d 20-Nov-15 26-Nov-15 0d
PROCESS PROCESS 49d 06-Nov-15 24-Dec-15 0d
A1110 Commissioning Separator System 7d 06-Nov-15 12-Nov-15 0d
A1320 Commissioning Incinerator 7d 13-Nov-15 19-Nov-15 35d
A1170 Commissioning AGRU (LP) 7d 20-Nov-15 26-Nov-15 0d
A1180 Commissioning DHU 7d 20-Nov-15 26-Nov-15 0d
A1190 Commissioning DPCU 7d 20-Nov-15 26-Nov-15 0d
A1210 Commissioning Booster Compressor 14d 04-Dec-15 17-Dec-15 7d
A1220 Commissioning BSRU 7d 11-Dec-15 17-Dec-15 0d
A1230 Commissioning Bleed Water Treatment 7d 18-Dec-15 24-Dec-15 0d
A1240 Commissioning Sulfur Packaging System 7d 18-Dec-15 24-Dec-15 0d
A1550 Commissioning AGRU (HP) 7d 18-Dec-15 24-Dec-15 0d
OFFSITE FACILITIES OFFSITE FACILITIES
42d 13-Nov-15 24-Dec-15 7d
A1270 Condensate Tank 7d 13-Nov-15 19-Nov-15 35d
A1280 Produce Water Tank 7d 13-Nov-15 19-Nov-15 35d
A1290 Truck Condensate 7d 13-Nov-15 19-Nov-15 35d
A1300 Trunkline 7d 18-Dec-15 24-Dec-15 7d
A1310 Senoro Facilities 7d 18-Dec-15 24-Dec-15 7d
TEST TEST
7d 25-Dec-15 31-Dec-15 0d
A1330 Performance Test 7d 25-Dec-15 31-Dec-15 0d
Jun Jul Aug Sep Oct Nov Dec Jan
2015 2016
FLOWLINE SYSTEM READY FOR GAS IN
GAS IN
OPERATIONAL ACCEPTANCE
Temporary Power Generation ~30kW
Temporary Power Generation ~500kW
Temporary Power Generation ~2000kW
Energize GTGA(Fuel)
Energize GTG B
Energize GTG C
Energize GTGD
Energize GTGA(With HP Fuel Gas)
Pre-Test Switch Gear/ MCC
Energize MCC/ Switchgear
Energize HVAC
Energize UPS/ Battery
Energize Lighting, Telecommunication & Other Facilities
Energize DCS/SIS & ESD/ F&G
Individual Pump Test Run
Field Instrument Test
Functional Test/ Trip Test
Chemical Cleaning AGRU
Chemical Cleaning BSRU
Flushing/ Blowing
N2 Purging
Chemical Preparation AGRU
Chemical Preparation DPCU
Chemical Preparation DHU
Fill Up Raw Water BSRU
Chemical Preparation BSRU (Incld Bactery)
Commissioning Fire Water System
Commisioning UtilityAir & Instrument Air
Commissioning Water Treatment System
Commissioning N2 Generation System
Commissioning Cooling Water
Commissioning LP & HP Flare (Pilot by LPG)
Commissioning Condensate System
Commissioning Produce Water System
Produce LP Fuel Gas System
Commissioning Hot Oil
Produce HP Fuel Gas System
Commissioning Separator System
Commissioning Incinerator
Commissioning AGRU (LP)
Commissioning DHU
Commissioning DPCU
Commissioning Booster Compressor
Commissioning BSRU
Commissioning Bleed Water Treatment
Commissioning Sulfur Packaging System
Commissioning AGRU (HP)
Condensate Tank
Produce Water Tank
Truck Condensate
Trunkline
Senoro Facilities
Performance Test
PPGM DONGGI

COMMISSIONING SCHEDULE DONGGI (INTERNAL)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
Page 1 of 1 12-Jun-15