Sie sind auf Seite 1von 1

17

th
April 2014,
To,
Eng. Khaled

Dammam.
SUB: Removal of Workstations
Dear Mr. Khaled,
As It has been approved the carpet tiles color, I request you to remove all the Workstations
which are there in 6
th
Floor. We are unable to start the flooring work due to workstations placed
over there. So I hope you will take action at earliest to avoid delay in work.

Thanks and regards
Shaik Feroz
Project Engineer