2 TeamFormation 18days Sep2'14 Sep19'14 3 ChoosingTypeofStudy 5days Sep4'14 Sep8'14 4 SelectionofRelated Researchesforthechosen study 16days Sep9'14 Sep24'14 5 SelectionofProjectsbased onthechosenstudy 16days Sep9'14 Sep24'14 6 ProjectDraftReport 4days Sep22'14 Sep25'14 7 Reviewanalyzeandrework 4days Sep24'14 Sep27'14 8 Milestone1 0days Sep28'14 Sep28'14 9 10 Summarizerelevantpaper toyourstudy 8days Sep29'14 Oct6'14 11 Analyzingthepapersfor advandlimitationofeach work 7days Oct7'14 Oct13'14 12 Contrastingstudieswrtour project 7days Oct10'14 Oct16'14 ProjectOutline TeamFormation ChoosingTypeofStudy SelectionofRelatedResearchesforthechosenstudy SelectionofProjectsbasedonthechosenstudy ProjectDraftReport Reviewanalyzeandrework 9/28 Summarizerelevantpapertoyourstudy Analyzingthepapersforadvandlimitationofeachwork Contrastingstudieswrtourproject W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F 0,' Aug3,' Aug17, Aug31, Sep14, Sep28, Oct12, Oct26, Nov9,' Nov23, Dec7,' Dec21, Task Split Milestone Summary ProjectSummary ExternalTasks ExternalMilestone InactiveTask InactiveMilestone InactiveSummary ManualTask Durationonly ManualSummaryRollup ManualSummary Startonly Finishonly Deadline Progress Page1 Project:Project1 Date:Sep25'14 ID TaskName Duration Start Finish 13 Identifyimprovements made 5days Oct14'14 Oct18'14 14 Milestone2 0days Oct19'14 Oct19'14 15 16 Identifytoolssuitedtoour project 3days Oct20'14 Oct22'14 17 Installationofthesame withintheIDE 6days Oct23'14 Oct28'14 18 Importchosenprojectsinto Eclipse 8days Oct25'14 Nov1'14 19 Milestone3 0days Nov2'14 Nov2'14 20 21 Findingsuitablestatistical analysiswrtourresearch questions 8days Nov3'14 Nov10'14 22 Identifystatisticaltoolsor toolsgeneratinggraph 6days Nov5'14 Nov10'14 23 CreatestatisticalAnalysis 12days Nov11'14 Nov22'14 24 Milestone4 0days Nov23'14 Nov23'14 25 Identifyimprovementsmade 10/19 Identifytoolssuitedtoourproject InstallationofthesamewithintheIDE ImportchosenprojectsintoEclipse 11/2 Findingsuitablestatisticalanalysiswrtourresearchquestions Identifystatisticaltoolsortoolsgeneratinggraph CreatestatisticalAnalysis 11/23 W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F 0,' Aug3,' Aug17, Aug31, Sep14, Sep28, Oct12, Oct26, Nov9,' Nov23, Dec7,' Dec21, Task Split Milestone Summary ProjectSummary ExternalTasks ExternalMilestone InactiveTask InactiveMilestone InactiveSummary ManualTask Durationonly ManualSummaryRollup ManualSummary Startonly Finishonly Deadline Progress Page2 Project:Project1 Date:Sep25'14 ID TaskName Duration Start Finish 26 Compiledandrefactored sourcecode 9days Nov24'14 Dec2'14 27 ProjectReport 15days Nov26'14 Dec10'14 28 Projectpresentation 5days Dec8'14 Dec12'14 29 ReportReview 2days Dec11'14 Dec12'14 30 Milestone5 0days Dec13'14 Dec13'14 31 32 POD1 1day Sep24'14 Sep24'14 33 POD2 1day Oct1'14 Oct1'14 34 POD3 1day Oct8'14 Oct8'14 35 POD4 1day Oct15'14 Oct15'14 36 POD5 1day Oct22'14 Oct22'14 37 POD6 1day Oct29'14 Oct29'14 38 POD7 1day Nov5'14 Nov5'14 Compiledandrefactoredsourcecode ProjectReport Projectpresentation ReportReview 12/13 POD1 POD2 POD3 POD4 POD5 POD6 POD7 W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F 0,' Aug3,' Aug17, Aug31, Sep14, Sep28, Oct12, Oct26, Nov9,' Nov23, Dec7,' Dec21, Task Split Milestone Summary ProjectSummary ExternalTasks ExternalMilestone InactiveTask InactiveMilestone InactiveSummary ManualTask Durationonly ManualSummaryRollup ManualSummary Startonly Finishonly Deadline Progress Page3 Project:Project1 Date:Sep25'14 ID TaskName Duration Start Finish 39 POD8 1day Nov12'14 Nov12'14 40 POD9 1day Nov19'14 Nov19'14 41 POD10 1day Nov26'14 Nov26'14 42 POD11 1day Dec3'14 Dec3'14 43 POD12 1day Dec10'14 Dec10'14 POD8 POD9 POD10 POD11 POD12 W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F 0,' Aug3,' Aug17, Aug31, Sep14, Sep28, Oct12, Oct26, Nov9,' Nov23, Dec7,' Dec21, Task Split Milestone Summary ProjectSummary ExternalTasks ExternalMilestone InactiveTask InactiveMilestone InactiveSummary ManualTask Durationonly ManualSummaryRollup ManualSummary Startonly Finishonly Deadline Progress Page4 Project:Project1 Date:Sep25'14