ID Task

Mode
Task Name Duration Start Finish Predecessors Resource Names
1 COIMBATTORE PIPELINE 20 days Sat 01/02/14 Thu 27/02/14 AJAY TAPADIA,ANAND GUNDECHA,CML TEAM,EXCAVATION TEAM,LAYING TEAM,RAJAN KHADLOYA,TAPE COAT TEAM,TRANSPORT,TYAGARAJAN,VIJAY CHANDER REDDY
2 AGREEMENT 1 day Sun 02/02/14 Sun 02/02/14 RAJAN KHADLOYA,VIJAY CHANDER REDDY
3 MATERIAL PROCUREMENT 9 days Mon 03/02/14Thu 13/02/14 2 ANAND GUNDECHA
4 PRE ARRANGEMENTS SITE 5 days Mon 03/02/14Fri 07/02/14 2 TYAGARAJAN
5 MAN POWER MOBILISATION 3 days Mon 10/02/14Wed 12/02/144 VIJAY CHANDER REDDY
6 CML 8 days Sun 02/02/14 Tue 11/02/14 CML TEAM
7 TAPE COATING 7 days Thu 13/02/14 Fri 21/02/14 5,6 TAPE COAT TEAM
8 QUALITY CHECK 1 day Mon 24/02/14Mon 24/02/147 TPI
9 BILLING 1 day Tue 25/02/14 Tue 25/02/14 8 JS ASSOCIATES
10 JINDAL SAW NEGOTIATIONS 1 day Fri 14/02/14 Fri 14/02/14 2 AJAY TAPADIA,RAJAN KHADLOYA,VIJAY CHANDER REDDY
AJAY TAPADIA,ANAND GUNDECHA,CML TEAM,EXCAVATION TEAM,LAYING TEAM,RAJAN KHADLOYA,TAPE COAT TEAM,TRANSPORT,TYAGARAJAN,VIJAY CHANDER REDDY
RAJAN KHADLOYA,VIJAY CHANDER REDDY
ANAND GUNDECHA
TYAGARAJAN
VIJAY CHANDER REDDY
CML TEAM
TAPE COAT TEAM
TPI
JS ASSOCIATES
AJAY TAPADIA,RAJAN KHADLOYA,VIJAY CHANDER REDDY
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
27 Jan '14 03 Feb '14 10 Feb '14 17 Feb '14 24 Feb '14 03 Mar '14
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 1
Project: coimbattore project
Date: Wed 12/02/14