HW2 (Chapter 5, 6, 8)

Chapter 5 Exercise
3. Below is a project WBS with cost apportioned by percent. If the total project cost is estimated to
be $600,000, what are the estimated costs for the following deliverables?

a. Design?
A) $240,000
b. Programming?
A) $120,000
c. In-house testing?
A) $120,000
What weaknesses are inherent in this estimating approach?
A) It needs realistic historical data, if the estimate is off everything else will be also, and project
has to be similar to past projects for sub-deliverables to be useful.

4. Firewall Project XT. Using the complexity weighting scheme and the function point complexity
weighted table shown below, estimate the total function point count. Assume historical data
suggest five function points equal on person month and six people can work on the project.

Complexity Weight Table


Number of inputs

10

Rated complexity low

Number of outputs

20

Rated complexity average

Number of inquiries

10

Rated complexity average

Number of files

30

Rated complexity high

Number of interfaces

50

Rated complexity high

a. What is the estimated project duration?


Complexity Weighting
Element
Count
Low
Average
High
Inputs
10
10 x 2
Outputs
20
20 x 6
Inquiries
10
10 x 4
Files
30
30 x 12
Interfaces
50
50 x 15
Total

=
=
=
=
=
=

Total
20
120
40
360
750
1,290

A) 1290 / 5 function points = 258 person months. Assuming six people available, the project
duration will be approximately 43 months (258 / 6 = 43)
b. If 20 people are available for the project, what is the estimated project duration?
A) The project duration will be approximately 12.9 months if 20 people are available (258 / 20 =
12.9)

c. If the project must be complete in six months, how many people will be needed for the
project?
A) 43 people will be needed to complete the project in approximately 6 months (258 / 43 = 6)

Chapter 6 Exercises
Creating a Project Network
1. Here is a work breakdown structure for a wedding. Use the method described in the
Snapshot from Practice: The Yellow Sticky Approach to create a network for this project.
Note: Do not include summary tasks in the network (i.e., 1.3, Ceremony, is a summary task; 1.2,
Marriage license, is not a summary task). Do not consider who would be doing the task in building
the network. For example, do not arrange hiring a band to occur after florist because the same
person is responsible for doing both tasks. Focus only on technical dependencies between tasks.
Hint: Start with the last activity (wedding reception), and work your way back to the start of the
project. Build the logical sequence of tasks by asking the following question: In order to have or do
this, what must be accomplished immediately before this? Once completed, check forward in time by
asking this question: Is this task(s) the only thing that is needed immediately before the start of the
next task?
Work Breakdown Structure
1. Wedding project
1.1 Decide on date
1.2 Marriage license
1.3 Ceremony
1.3.1 Rent church
1.3.2 Florist
1.3.3 Create/print programs
1.3.4 Hire photographer
1.3.5 Wedding ceremony
1.4 Guests
1.4.1 Develop guest list
1.4.2 Order invitations
1.4.3 Address and mail invitations
1.4.4 Track RSVPs
1.5 Reception
1.5.1 Reserve reception hall
1.5.2 Food and beverage
1.5.2.1 Choose caterer
1.5.2.2 Decide on menu

1.5.2.3 Make final order


1.5.3 Hire band
1.5.4 Decorate reception hall
1.5.5 Wedding reception

Drawing AON Networks


2. Draw a project network from the following information. What activity(s) is a burst activity? What
activity(s) is a merge activity?

A) Activity A is burst activity, and Activity D is a merge activity.

AON Network Times


7. The project information for the custom order project of the Air Control Company is presented here.
Draw a project network for this project. Compute the early and late activity times and the slack times.
Identify the critical path.

9. You are creating a customer database for the Modesto Nuts minor league baseball team. Draw a
project network given the information below. Complete the forward and backward pass, compute
activity slack, and identify the critical path.
How long will this project take? How sensitive is the network schedule? Calculate the free slack and
total slack for all noncritical activities.

10. J. Wold, project manager of Print Software, Inc., wants you to prepare a project network;
compute the early, late, and slack activity times; determine the planned project duration; and identify
the critical path. His assistant has collected the following information for the Color Printer Drivers
Software Project:

13.* You are completing a group term paper. Given the project network that follows,
complete the forward and backward pass, compute activity slack, and identify the critical path. Use
this information to create a Gantt chart for the
project. Be sure to show slack for noncritical activities.

Lag Exercises
19. Given the following information, draw the project network. Compute the early, late, and slack
times for the project network. Which activities on the critical path have only the start or finish of the
activity on the critical path?

10

20.* Given the information in the following lag exercises, compute the early, late, and slack times for
the project network. Which activities on the critical path have only the start or finish of the activity on
the critical path?

11

Chapter 8 Exercises
2. Given the network plan that follows, compute the early, late, and slack times. What is the project
duration? Using any approach you wish (e.g., trial and error) develop a loading chart for resource
resources Carpenters (C) and Electricians (E). Assume only one Carpenter is available and two
Electricians are available. Given your resource schedule, compute the early, late, and slack times
for your project. Which activities are now critical? What is the project duration now?

12

3. Compute the early, late, and slack times for the activities in the network that follows, assuming a
time-constrained network. Which activities are critical? What is the time-constrained project
duration?
Note: Recall in the schedule resource load chart the time constrained schedule interval (ES
through LF) has been shaded. Any resource schedule beyond the shaded area will delay the
project.
Without consideration of resources the project is estimated to take 13 time units and the critical
path is 2 4 6 (see Network Diagram).
Assume you have only three resources and you are using a computer using a computer that
uses software that schedules projects by the parallel method and following heuristics. Schedule
only one period at a time!
Minimum slack
Smallest duration
Lowest identification number
Keep a log of each activity change and update you make each periode.g., period 0-1, 1-2, 2-3,
etc. (Use a format similar to the one on page 241.) The log should include any changes or updates
in ES and slack times each period, activities scheduled, and activities delayed. (Hint: Remember
to maintain the technical dependencies of the network.) Use the resource load chart to assist you
in scheduling (see pages 260-261).
List the order in which you scheduled the activities of the project. Which activities of your
schedule are now critical?
Recompute your slack for each activity given your new schedule. What is the slack for activity
1? 4? 5?

13

14

15

9.
Given the time-phased work packages and network, complete the baseline budget form for
the project.

16

10. Given the time phased work packages and network, complete the baseline budget form for the
project.

17

Mini-case report - Individual

You will select one of the cases from the list and write a report.
Three individual case write-ups are to be completed during the semester. The written reviews are to be 1
2 pages type-written, double spaced, one-inch margins using a question/answer format citing of any
outside references (if needed). Cases will be graded based on depth of analysis, content and format.
Students can submit up to four cases. Best three cases in terms of highest scores will be included in the
final grade evaluation.

A list of approved selections from the text will be provided. The selected written review must be
submitted as a part of the homework. Late submission penalty will be applied after the deadlines.
Select one from the following list.
Chapter 5 Sharp Printing
Chapter 6 Greendale Stadium Case
Chapter 8 PowerTrain LTD.

18