ELEMENT

COST OF RATE
ELEMENT

/m2

ELEMENTAL DATA QUANTITY


Quantity Rate
FACTOR

8705

54.41

130

66.96

0.81

2A Frame
2B Upper Floors
2C Roof
2D Stairs
2E External Walls
2F Windows & Externl.Doors
2G Internal Walls & Partns.
2H Internal Doors

3440
6841
13434

21.5
42.76
83.96

160
86
130

21.5
79.55
103.34

1
0.54
0.81

10934
9174
1828
1538

68.34
57.34
11.43
9.61

109
16
70
3

100.31
573.36
26.11
512.55

0.68
0.1
0.44
0.02

SUPERSTRUCTURE

47189

294.94

3A Wall Finishes
3B Floor Finishes
3C Ceiling Finishes

766
4089
408

4.79
25.56
2.55

141
158
158

5.43
25.88
2.58

0.88
0.99
0.99

INTERNAL FINISHES

5263

32.9

FITTINGS & FURNISHINGS

721.7778

4.51

3276.603
0
353
177

20.48
0
2.21
1.11

0
0

0
0

3807

23.8

0
0

0
0

SUBSTRUCTURE

Gross Floor Area :

5A Sanitary Appliances
5C Disposal Installations
5N B.W.I.C.
5O Profit & Attendances
BUILDING SERVICES

5B Services Equipment
5D Water Installations

5E Heat Source (Inc. in 5F)


5F Space Heating/Air Treatment
5G Ventilation System
5H Electrical Installations
5I Gas (N/R)
5J Lifts and Conveyors
5K Protective Installations
5L Communications
5M Special Installations

0
3280.346
0
2828.615
0
0
0
960.3462
0

0
20.5
0
17.68
0
0
0
6
0

M. & E. SERVICES

7069.308

44.18

72755

454.74

9094
1455

56.84
9.09

83304

520.65

75210
8094.357

470.06
50.59

BUILDING & ENGINEERING


6A Preliminaries
6B Contingencies

TOTAL COST

Building
Engineering

30-Sep-02
160 m2

ELEMENTAL
PERCENTAGE
%
11.96

4.73
9.4
18.46
15.03
12.61
2.51
2.11
64.85

1.05
5.62
0.56
7.23
0.99

4.5
0
0.49
0.24
5.23

0
0

0
4.51
0
3.89
0
0
0
1.32
0
9.72

100
12.5
2

90.28
9.72

Das könnte Ihnen auch gefallen