Sie sind auf Seite 1von 19

STATION: NTPC

SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

PLANT AREA : CONTROL & INSTRUMENTATION


TESTING SCHEDULE : DDCMIS (OLCS,CLCS &IS)

LIST OF CONTENTS

1. PLANT DETAILS
2. TESTING OBJECTIVES
3. TESTING PROPOSALS
4. SERVICES REQUIRED
5. SAFETY PRECAUTIONS
6. EMERGENCY PROCEDURES
7. STATE OF THE PLANT
8. COMMISSIONING PROCEDURE
9. COMPLETION CRITERIA
10. APPENDICES

SHEET 1 OF 19

STATION: NTPC
SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 2 OF 19

PLANT AREA : CONTROL & INSTRUMENTATION


TESTING SCHEDULE : DDCMIS (OLCS,CLCS &IS)

1. PLANT DETAILS:
THIS SYSTEM CONSISTS OF OLCS,CLCS AND OTHER INTERFACE SYSTEM PANELS.
Each panel consists of Power supply module, Processor, Local Bus modules, Input and output modules (Analog and
Digital),Intra plant modules ,diagnostic modules and Interface modules either all or except one or two.

Sl. No.

modules

Cross reference

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25

Binary Input
Analog Input
Binary output
Analog output
Drive control
Processor for text output
Intra plant bus Access
Intra plant Bus coupler
IPB Coupler with address input
IPB Cable Power Supply
IPB cable input
IPB Traffic Director
Bus access
Bus circuit board
Bus coupler serial Interface
Bus isolation
Bus end
Cable for local bus extension
IPB Bus coupling
Bus traffic Director for extended Add range
Power supply
DC/DC convertor
Processor
IS between IPB & PC-AT
Diagnostic/SOE

70EBXX
70EAXX
70ABXX
70AAXX
70AS04/06
70KS01
70FA01
70FK01
XV7713
XV7715
XV7717/8
70FV01
70BA02
70BL01
70BK03
70BT01
70BA02
70BL03
70BK02
70BV05
XT37Y
KH370
70 PR 05
PC421
70SK3Z

XX 01,02,03,04 or 06 depending on versions/applications, it changes


Y 3 for distribution,6 for buffer & 7 supervision for positive voltages
Z 1 for video controller, 2 for RS232 interface for key board,3 for test memory ,4 for computer simulation memory
coupler, 5 for output voltage signal for trend,6 for EEPROM programming , 7 for local bus to computer buscoupler
NAME PLATE DETAILS

MAKE:ELECTRONICS DIVISION,BHEL,BANGALORE

STATION: NTPC
SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 3 OF 19

PLANT AREA : CONTROL & INSTRUMENTATION


TESTING SCHEDULE : DDCMIS (OLCS,CLCS &IS)

SYSTEM DESCRIPTION:
a) OLCS(CRB)Panels
These panels are used for operating single Drive in
open loop control system mode. In this outputs are not
controlled but monitored. Feedbacks, commands and other
parameters for drive are monitored through MMI. There are
22 such modules for NTPC Simhadri; CRB 01 to 22.
b) CLCS(CRA) Panels
These panels are used for operating Single drive in
CLCS mode i.e. the output is controlled by taking a
fraction of output as a controlling input to the system.
There are 15 such closed loop control system panels in NTPC
simhadri site. They are labeled as CRA 01 to 15.
c) IS Panels
These panels are used for interfacing IPB with PC-AT.
There are such 6 modules in NTPC simhadri site; labeled as
CRC 01 to 06.

STATION: NTPC
SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 4 OF 19

PLANT AREA : CONTROL & INSTRUMENTATION


TESTING SCHEDULE : DDCMIS (OLCS,CLCS &IS)

2.TESTING OBJECTIVE:
TO TEST THE DDCMIS PANELS AND TO MAKE THEM READY FOR SERVICE.

STATION: NTPC
SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 5 OF 19

PLANT AREA : CONTROL & INSTRUMENTATION


TESTING SCHEDULE : DDCMIS (OLCS,CLCS &IS)

3.TESTING PROPOSAL:
i)

INTRA PLANT BUS COMMUNICATION TO BE ESTABLISHED

ii) POWER SUPPLY OF ALL PANELS ARE NOT BE MIXED UP


iii)POWER & CONTROL BUSES ARE TO BE ISOLATED FROM
EARTH.
iv) POTENTIAL ACROSS EARTH & NEUTRAL(ZERO) POINT OF
THE PANEL SHOULD BE WITHIN SOME MILLI VOLTS.
v) INPUT,OUTPUT,DRIVE CONTROL,PROCESSOR,COMMUNICATION &
DIAGNOSTIC STATION MODULES ARE TO BE TESTED AT FIRST.
vi) FIELD CONNECTIONS ARE TO BE TESTED THEREAFTER
vii) ALL LOGICS TO BE TESTED & FIND OUT EACH OUTPUTS ARE AS PER
THE GIVEN LOGICS
viii) CALIBRATION OF OUTPUT SYSTEMS SUCH AS CONTROL VALVES,SERVO
MOTORS ETC ARE TO BE CARRIED OUT.
ix) CHANGEOVER OPERATION OF INTRA PLANT BUS TRAFFIC DIRECTORS
(70FV01) & INDIVIDUAL BUSCOUPLERS OF EACH PANELS ARE TO BE CHECKED
AND FOUND OK.

STATION: NTPC
SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

PLANT AREA : CONTROL & INSTRUMENTATION


TESTING SCHEDULE : DDCMIS (OLCS,CLCS &IS)

4.SERVICES REQUIRED:
500 V DC MEGGER
230 V 1 PHASE 50 Hz AC SUPPLY
24V DC SUPPLY
DIGITAL MULTIMETER

SHEET 6 OF 19

STATION: NTPC
SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 7 OF 19

PLANT AREA : CONTROL & INSTRUMENTATION


TESTING SCHEDULE : DDCMIS (OLCS,CLCS &IS)

5.0 SAFETY PRECAUTIONS:


GENERAL:
5.1

FUSES OF DIFFERENT RATINGS

ARE PROVIDED IN EACH CARDS TO

PROTECT ITSELF FROM OVERCURRENT, SHORT AT OUTPUT SIDE OR


ANY
5.2

OTHER INTERNAL FAULT.

CIRCUIT BREAKERS ARE PROVIDED TO PROTECT MAIN EQUIPMENTS


FROM SHORT, EARTHING OF INPUT POWER SUPPLIES

PERSONNEL :
5.3.1

ALL MEMBERS OF THE TEST TEAM AND ALL OTHER PERSONS


INVOLVED IN THIS TESTING SCHEDULE MUST BE MADE
FAMILIAR

5.3.2

WITH THE CONTENTS OF THE TESTING SCHEDULE.

SAFE ACCESSES TO AND ADEQUATE ESCAPE ROUTES FROM


CONFINED

AREAS MUST BE MAINTAINED.

5.3.3

SAFETY CLEARANCE CERTIFICATE WILL BE IN FORCE.

5.2

PLANT :

5.2.1

WHILE

INSERTING

MODULES

IN

DDCMIS,

ENSURE

THAT

THEY ARE NOT INSERTED UPSIDE DOWN, WHICH CAN BE


DISASTROUS.
5.2.2

ENSURE

THAT

WHILE

MEASUREMENTS/OBSERVATIONS

CARRYING
OF

THE

ACCIDENTAL SHORTING OF WIRES OCCURS.

POWER

OUT
SUPPLIES,

THE
NO

STATION: NTPC
SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 8 OF 19

PLANT AREA : CONTROL & INSTRUMENTATION


TESTING SCHEDULE : DDCMIS (OLCS,CLCS &IS)

5.2.3

CABLE USED FOR RTDS & OTHER TRANSMITTER MEASUREMENTS SHOULD


NOT HAVE ANY JOINTS

5.2.4

DO NOT USE HIGH VOLTAGE SOLDERING IRON FOR REMOVING OR


FIXING ANY COMPONENT IN THE ELECTRONIC MODULE, THIS MAY
DAMAGE PRINTED CIRCUITS.

USE 6V, 30V, SOLDERING IRON FOR

THIS PURPOSE.
5.2.5

VARIOUS

ELECTRONIC

MODULES

NEED

CERTAIN

JUMPERS

TO

CLOSED BY LINKS AND SOME JUMPERS ARE TO REMAIN OPEN.


SOME

CASES,

TESTING.

FEW

THIS

RESISTORS

INFORMATION

ARE
IS

TO

BE

GIVEN

IN

MOUNTED

BE
IN

BEFORE

RELEVANT

TEST

PROCEDURES OF THE MODULES.

IT IS IMPORTANT TO CROSS CHECK

THAT

RESISTORS

ALL

SUCH

LINKS

AND

ARE

MOUNTED

BEFORE

CONDUCTING TESTS.
5.2.6

ZERO

POTENTIAL

AND

EARTH

POTENTIAL

CONNECTED AT ONE POINT IN THE WORKS.

SHOULD

HAVE

BEEN

ENSURE THAT THE SAME

HAS BEEN DONE.


5.2.7

WHILE MEGGERING, ENSURE THAT ALL ELECTRONICS MODULES AND


SUBASSEMBLIES ARE REMOVED / SHORT CIRCUITED.

5.2.8

BEFORE

CONDUCTING

TESTS

ON

ELECTRONIC

MODULE,

CHECK

AVAILABILITY OF RELEVANT POWER SUPPLY (IF ANY) AT THE TEST


SOCKET OF MODULE OR RACK.
5.2.9

THE EARTH CONNECTIONS AT THE SUPPLY TERMINALS OF THE CRO


SHOULD BE REMOVED AND ISOLATED.

ALTERNATIVELY IT WOULD BE

PREFERABLE TO FEED THROUGH AN ISOLATING TRANSFORMER.

STATION: NTPC
SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 9 OF 19

PLANT AREA : CONTROL & INSTRUMENTATION


TESTING SCHEDULE : DDCMIS (OLCS,CLCS &IS)

6. EMERGENCY PROCEDURE:
6.1

EMERGENCY PUT OFF PB IS AVAILABLE AS AN OPTION AND MAINLY


SERVES TO DISCONNECT THE POWER SUPPLY TO THE PROCESSORS AND
OTHER CIRCUITS.

6.2

EMERGENCY TELEPHONE NUMBERS FOR HOSPITAL & FIRE STATIONS SHALL


BE PREDOMINANTLY DISPLAYED.

6.3

A TELEPHONE MUST BE AVAILABLE NEARBY

6.4

FIRST AID CHARTS FOR

ELECTRICAL SHOCKS MUST BE AVAILABLE

STATION: NTPC
SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 10 OF 19

PLANT AREA : CONTROL & INSTRUMENTATION


TESTING SCHEDULE : DDCMIS (OLCS,CLCS &IS)

7. STATE OF THE PLANT:


7.1 PANELS ARE ERECTED.
7.2 IP BUS CABLES ARE INTERCONNECTED & TERMINATED WITH RC NETWORKS
AT THE ENDS.
7.3 APPLICATION EPROMS ARE LOADED WITH CORRECT PROGRAMS.
7.4 NO CABLE CONDUCTOR STRANDS ARE BENT INADVERTENTLY & TOUCH THE
GROUND POINTS DIRECTLY;BUT GROUNDED THROUGH CAPACITOR.
7.5 POWER SUPPLY CABLES ARE CONNECTED.

STATION: NTPC
SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 11 OF 19

PLANT AREA : CONTROL & INSTRUMENTATION


TESTING SCHEDULE : DDCMIS (OLCS,CLCS &IS)

8.COMMISSIONING PROCEDURE:
i)

ENSURE IPB CABLE IS TERMINATED AS PER SEC 2.0 OF IPB


CHECKLIST

ii)

IN BK02/FV01 MODULES,CHECK S104 & S105 OF AKA/SKA &AKB/SKB


JUMPERS ARE IN POSITION 2 RESPECTIVELY TO ENABLE SWITCHOVER
TO REDUNDANT LINE IN CASE OF A FAULT IN THE WORKING LINE.
IF IN THE SAME IPB, ONE 70FV01a &70FV01b ARE USED IN
REDUNDANT MODE, THE PLUG IN JUMPER AKB/EKB(S105) MUST BE IN
POSITION 1 IN 70FV01b.

iii) DATA COMMUNICATION CHECKS


CHECK ALL DATAS ARE RECEIVED IN END MODULE THROUGH
BK02 OVER IPB; OTHERWISE FOLLOW THE PROCEDURE MENTIONED IN
THE PAGE 04,05& 06 OF 11 OF IPB CHECK LISTS
ENSURE THE FOLLOWING
a) THE MAXITERMI,70BL02/70BL03, MODULE CONNECTIONS ARE
FIRM AND OK.
b) COOLING FAN DIRECTION IS SUCH THAT IT DRAWS AIR FROM
BOTTOM AND EXHAUSTS OUT AT THE TOP
c) PROTECTIVE DIODES IN THE BACK PLANE PCB(DN,DI,CK,ADR&
Z) ARE HEALTHY.

STATION: NTPC
SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 12 OF 19

PLANT AREA : CONTROL & INSTRUMENTATION


TESTING SCHEDULE : DDCMIS (OLCS,CLCS &IS)

d) PROPER DISTRIBUTION OF POWER SUPPLIES TO INDIVIDUAL


RACKS IN TF,TQ,TL,SOE INTER PANEL CONNECTIONS &
SYNCHRONISATION SIGNAL WIRING TO FV01s FROM
DIAGNOSTIC STATION AS PER RELEVANT DOCUMENTS

iv)

INPUT MODULES

a) ALARM SIGNAL SHOULD NOT APPEAR IN HEALTHY STATE


b) ENSURE DIAGNOSTIC IS WORKING UNDER THE CONDITIONS OF WIRE
BREAK, SHORT CIRCUIT, SUPPLY FAILURE ETC
c) APPROPRIATE COMPENSATING RESISTORS ARE TO BE SUED BETWEEN
PIN 17 & 19 IN EA04 MODULES
d) INPUT SIGNALS MUST BE POTENTIAL AS WELL AS ELECTRO MAGNETIC
INTERFERENCE FREE AND FIXED CONTACTS

v)OUTPUT MODULES
a) ALARM SIGNAL SHOULD NOT APPEAR IN HEALTHY STATE

b)

DIAGNOSTIC RESPONSES LIKE MODULE FAILURE, MISSING


PCB ARE TO BE CHECKED.
v)

DRIVE CONTROL MODULES

a)

ENSURE THAT CORRECT APPLICATION EPROM IS PUT PROPERLY WITH


CORRECT POLARITY.

STATION: NTPC
SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 13 OF 19

PLANT AREA : CONTROL & INSTRUMENTATION


TESTING SCHEDULE : DDCMIS (OLCS,CLCS &IS)

b)

ENSURE POWER SUPPLY AT A/M STATIONS, PUSH BUTTONS/LAMPS IN


CONTROL ROOM ETC

c)

INTERFACE SIGNALS (TORQUE/LIMIT SWITCH/POSITION


FEEDBACKS, COMMAND OUTPUTS THROUGH RELAYS,E/P
CONVERTOR, ACTUATOR) ARE TO BE CHECKED

d)

ENSURE THE MODULE IS IN NOT SIMULATOR MODE.

e)

PROTECTION LOGIC IS IN ORDER FOR ALL THE O/PS

f)

THE OUTPUT TELEGRAMS ARE ALL OK

g)

DIAGNOSTIC INFORMATION IS PROPER FOR VARIOUS FAULT


CONDITIONS

h)

ENSURE CORRECT DRIVE CONTROL STANDARD FUNCTIONS ARE


PROGRAMMED

i)

ENSURE FEEDBACK TRANSMITTER IS PROPERLY TERMINATED,


GROUNDING OF THE VALVE POSITION, FEEDBACK CABLE ARE NOT
PRESENT IN CASE OF 70AS06 & ITS CALIBRATION WITH LOAD IS
PROPER

j)

CHECK HARD WIRED PROTECTION

IS PROPERLY TERMINATED

vii) PROCESSOR MODULE


ENSURE THE FOLLOWING
a)

CORRECT VERSION OF FIRMWARE IS USED

STATION: NTPC
SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 14 OF 19

PLANT AREA : CONTROL & INSTRUMENTATION


TESTING SCHEDULE : DDCMIS (OLCS,CLCS &IS)

b)

APPLICATION EPROMS WITH CORRECT APPLICATION PROGRAM


NUMBERS ARE USED

c)

PARAMETERS ARE SET ACCORDING TO THE SCHEME USING 70SK06 OR


DIAGNOSTIC STATION

d)

FAULT ANNUNCIATIONS ARE ALL RIGHT UNDER ALL FAULT


CONDITIONS

e)

DIAGNOSTIC EPROM READING FACILITY IS ENABLED

f)

PROCESSOR NUMBERS ARE CORRECTLY SET WHEN MORE THAN ONE


PROCESSOR MODULE IN A LOCAL BUS IS PRESENT

g)

PROGRAM END STATEMENT IS PROGRAMMED AFTER THE USER PROGRAM


IN ALL PROCESSOR MODULES

h)

THE INTERPROCESSOR DATA TRANSFER ADDRESS RANGE IS BEYOND


THE LAST SERVICE ADDRESS USED IN 70BK02 MODULE IN CASE OF
70PR05 MODULES CONFIGURED IN HOT STANDBY MODE.

vi)

COMMUNICATION MODULE

a)

ENSURE WIRING IS OK BETWEEN 70BK02,70FV01 & XV7713/ 70FA01

b)

ALL MODULES INSIDE XV7713/70FA01 ARE PROPERLY PLACED

c)

RC CIRCUIT IS SOLDERED & PLACED PROPERLY AT THE BEGINNING


& AT THE END OF IP BUS CABLE (XV/FA BOXES)

STATION: NTPC
SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 15 OF 19

PLANT AREA : CONTROL & INSTRUMENTATION


TESTING SCHEDULE : DDCMIS (OLCS,CLCS &IS)

d)

IP BUS IS TERMINATED IN ALL PANELS WITH PROPER LUGS.


ENSURE COAXIAL CABLE CONNECTIONS

e)

TO REDUCE DISTURBANCES ENSURE THAT THE IPB CABLE IS


EARTHED AT MORE POINTS(MULTIPLE EARTHING)

f)

IN CASE 70BK02b IS USED WITH 70FV01a,ENSURE C80 CAPACITOR


OF 70FV01a IS CHANGED FROM 47nf TO 147nf

g)

ALARM SIGNAL SHOULD NOT APPEAR IN ANY OF THE 70BK02 &


70FV01

h)

IN 70BK02 MODULES, ENSURE THAT


1. LINE NUMBERS 016 & 017 ARE PROGRAMMED WITH DF02 & 03FF
RESPECTIVELY TO ENABLE EPROM READING FACILITY FROM
DIAGNOSTIC STATION
2. IN WORD MARSHALL PROGRAMMING,STARTING FROM LINE NUMBER
0400,THE BK NUMBERS ARE CALLED IN THE ASCENDING ORDER,AS
OTHERWISE THE MODULE WONT FUNCTION

i)

ENSURE EARTH LINK IS SOLDERED IN ALL XV MODULES

j)

AFTER IPB IS COMMISSIONED, CHECK THE CHANGEOVER OPERATION


OF REDUNDANT IPB TRAFFIC DIRECTORS(70FV01)

STATION: NTPC
SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 16 OF 19

PLANT AREA : CONTROL & INSTRUMENTATION


TESTING SCHEDULE : DDCMIS (OLCS,CLCS &IS)

ix) DIAGNOSTIC STATION


a)

ENSURE THAT THE CORRECT VERSION OF FIRMWARE IS LOADED IN


70SK33 MODULE IN PROPER LOCATION

b)

APPLICATION PROGRAM IS LOADED & NO RAMS PRESENT IN 70SK33

c)

NO OTHER EPROM, RAMS ARE IN 70SK33

d)

OPERATION OF DC/DC CONVERTOR MODULES ARE OK & THE OUTPUTS


ARE WITHIN PERMISSIBLE LIMITS

e)

CHECK THE INTERCONNECTION CABLES/FKB FOR SOE OPERATION

f)

ENSURE THAT NO DIAGNOSTIC/SOE STATION MODULES ARE


INSERTED/PULLED OUT IN POWER-ON CONDITION

g)

ENSURE THAT THE WORD 02 IS MARSHALLED TO 01 IN DIAGNOSTIC


STATION AS THIS SYCHRONISATION WORD IS USED IN ALL THE P13
LOCAL BUSES

h)

ENSURE THAT A 70AB01 MODULE IS PROVIDED IN DIAGNOSTIC


STATION WITH ADDRESS 01 & THE PIN 13 OF THIS MODULE IS
HARDWIRED TO ALL 70FV01 MODULES(PIN 95) TO ENABLE ALL
70FV01 MODULES TO FLOAT A ADDRESS & AT THE SAME TO HAVE
SYNCHRONISM IN FLASHING OF LAMPS ON THE DESK. PIN 95 OF
70BK02 MODULES IS HARDWIRED TO ALL 70EB10 MODULES (IF OUB
61 EXIST) TO ENABLE THEM TO START THE MILLISECOND COUNTER
AT THE SAME TIME.

STATION: NTPC
SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 17 OF 19

PLANT AREA : CONTROL & INSTRUMENTATION


TESTING SCHEDULE : DDCMIS (OLCS,CLCS &IS)

i)

ENSURE THAT THE 70BV05 MODULE CYCLE TIME IS SELECTED AS 20


ms IN BOTH DIAGNOSTIC STATION & THE SOE STATION AND SOE AS
MASTER, DIAGNOSTIC STATION AS SLAVE

j)

MARSHALL THE WORDS 02,03,FE FROM SOE STATION INTO


DIAGNOSTIC STATION

k)

ENSURE THAT SOE COMMAND WORD IS TRANSMITTED TO ALL


STATIONS WHEREVER 70EB10 MODULES ARE LOCATED

l)

CHECK JUMPER SETTINGS AND CORRECT INSTALLATION OF


RAM,EPROM, APPLICATION EPROMS,FIRMWARE EPROMS AS PER
ANNEXURE I

x)FIELD CONNECTIONS
a)

ENSURE SIGNAL/SHIELD ARE PROPERLY TERMINATED

b)

FERRULES TO B E PROVIDED FOR ALL USED CABLE CORES IN


JUNCTION BOXES AND UNSIGNED CABLE ENTRIES USED TO BE
PLUGGED

xi)FLAME SCANNER
a) ENSURE THAT PROPER JUMPER SELECTIONS ARE MADE IN THE
POWER SUPPLY MODULE BEFORE PUTTING INTO SERVICE.
b) DO NOT REMOVE OR INSERT ANY MODULE UNDER POWER-ON
CONDITION

STATION: NTPC
SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 18 OF 19

PLANT AREA : CONTROL & INSTRUMENTATION


TESTING SCHEDULE : DDCMIS (OLCS,CLCS &IS)

9.COMPLETION CRITERIA:
DDCMIS IS COMMISSIONED. ALL PARAMETERS AS PER SCHEME ARE
MONITORED & CONTROLLED FROM OPERATING STATIONS. SEQUENCE OF EVENTS IN
CASE OF TRIP ON FAULT, CHANGEOVER, PROCESS CHANGES AND
STARTING/STOPPING OF MAIN EQUIPMENTS ARE FOUND AVAILABLE IN THE
WORKSTATION MONITORS. CHANGEOVER OF PROCESSORS, IP BUS LINES ARE
FOUND OK WHEN FAULT OCCURS

& NO DISTURBANCE IN THE DATA TRANSFER

STATION: NTPC
SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 19 OF 19

PLANT AREA : CONTROL & INSTRUMENTATION


TESTING SCHEDULE : DDCMIS (OLCS,CLCS &IS)

10. APPENDICES:
DRAWINGS:

EARTHING PRACTICE

- ED 046 28 02/REV 01
( 19 SHEETS)

PRECOMMISSIONING OF P13/42 - EC 00001 /REV 01


( 17 SHEETS)
IPB CHECKLIST

- SK 676 410 0105 REV01


( 11 SHEETS)

FV & BK LISTS FOR IPBs - 1-50-1638-01REV01(15.8.2001)


1-50-1639-01REV01(15.8.2001)
LOG SHEETS :

I) INDIVIDUAL TERMINAL RESISTANCE OF IP BUS


AT VARIOUS PANEL
II)LIST OF JUMPER SETTINGS,VERSIONS OF
APPILICATION PROGRAMS USED
III) LIST OF SOEs CONFIGURED