DRAWING / DOCUMENT CONTROL LIST

INPUT
S.NO.

TITLE

DOCUMENT/DRAWING NO.

OUT

REV

FORMAT

RECEIVED DATE

REV

PDF

2-Dec-14

GIS CONTROL ROOM BUILDING

400/220 KV SLD-DARBHANGA

PDF

2-Dec-14

400/132 KV SLD-MOTHIHARI

PDF

2-Dec-14

QAP-BUS POST INSULATOR

PDF

2-Dec-14

QAP-CAPACITIVE VOLTAGE TRANSFORMER

PDF

2-Dec-14

QAP-CIRCUIT BREAKER

PDF

2-Dec-14

QAP-CURRENT TRANSFORMER

PDF

2-Dec-14

QAP-ISOLATORS

PDF

2-Dec-14

QAP-FASTENERS

PDF

2-Dec-14

10

QAP-GALVANIZED LATTICE STRUCTURE

PDF

2-Dec-14

11

QAP-LIGHTNING ARRESTER

PDF

2-Dec-14

12

QAP-GALVANIZED PIPE STRUCTURE

PDF

2-Dec-14

13

QAP-XLPE CABLE

PDF

2-Dec-14

14

DESIGN BASIS REPORT-400KV-125, 80 & 50 MVAR SHUNT


REACTORS

PDF

12-Dec-14

15

DESIGN BASIS REPORT FOR STEEL STRUCTURES FOR DARBHANGA


MOTHIHARI TRANSMISSION SYSTEM

PDF

12-Dec-14

16

CONTROL BUILDING GENERAL ARRANGEMENT & EQUIPMENT


LAYOUT DRAWING

PDF

12-Dec-14

DRAWING / DOCUMENT CONTROL LIST


INPUT
S.NO.

TITLE

DOCUMENT/DRAWING NO.

OUT

REV

FORMAT

RECEIVED DATE

REV

17

DESIGN MEMORANDUM REPORT FOR 400/220KV DARBHANGA &


400/132KV MOTHIHARI GIS SUBSTATION FOR DARBHANGA
MOTHIHARI TRANSMISSION SYSTEM

PDF

17-Dec-14

18

DESIGN BASIS REPORT-OUTDOOR SWITCHYARD

PDF

17-Dec-14

19

DESIGN BASIS REPORT FOR GENERAL CIVIL WORKS FOR


DARBHANGA MOTHIHARI TRANSMISSION SYSTEM

PDF

17-Dec-14

20

DESIGN BASIS REPORT-OUTDOOR EQUIPMENTS (SA, IT & WT)

PDF

17-Dec-14

DRAWING / DOCUMENT CONTROL LIST


INPUT
S.NO.

TITLE

DOCUMENT/DRAWING NO.

OUT

REV

FORMAT

RECEIVED DATE

REV

21

DESIGN BASIS REPORT-500MVA-400/220/33KV AUTO


TRANSFORMER FOR DARBHANGA GIS SUBSTATION

PDF

17-Dec-14

22

DESIGN BASIS REPORT-200MVA-400/132/33KV AUTO


TRANSFORMER FOR MOTHIHARI GIS SUBSTATION

PDF

17-Dec-14

23

Design Memorandum Report for : 400/220KV Darbhanga and


400/132KV Motihari GIS Substation

PDF

17-Dec-14

24

DESIGN BASIS REPORT FOR NEUTRAL GROUNDING EARTHING

PDF

22-Dec-14

25

245KV GIS-GA DRAWING FOR DARBHANGA

PDF

22-Dec-14

26

145KV GIS-GA DRAWING FOR MOTHARI

PDF

22-Dec-14

27

125MVAR LINE SHUNT REACTOR DRAWING

PDF

26-Dec-14

28

80MVAR LINE SHUNT REACTOR DRAWING

PDF

26-Dec-14

29

50MVAR LINE SHUNT REACTOR DRAWING

PDF

26-Dec-14

30

Layout of 400/220KV-Darbhanga

PDF

2-Jan-15

31

Layout of 400/132KV-Motihari

PDF

2-Jan-15

32

400KV Grinder structural design-type 4G1

PDF

5-Jan-15

33

Design Basis Report for Substation Automation System

PDF

7-Jan-15

34

Design Basis Report for CONTROL, RELAY & PROTECTION PANELS

PDF

7-Jan-15

DRAWING / DOCUMENT CONTROL LIST


INPUT
S.NO.

TITLE

DOCUMENT/DRAWING NO.

OUT

REV

FORMAT

RECEIVED DATE

REV

35

Design Basis Report for FIRE FIGHTING PROTECTION SYSTEM

PDF

7-Jan-15

36

Design Basis Report for PRE ENGINEERED BUILDING FOR


DARBNANGA MOTHIHARI TRANSMISSION SYSTEM

PDF

7-Jan-15

37

Final Layout of 400/220KV-Darbhanga

PDF

7-Jan-15

38

400-220 KV Section Layout- Darbhanga

PDF

10-Jan-15

39

General Technical Requirements for 400/220kV Darbhanga and


400/132kV Motihari GIS Substation For Darbhanga Motihari
Transmission system

PDF

12-Jan-15

DRAWING / DOCUMENT CONTROL LIST


INPUT
S.NO.

TITLE

DOCUMENT/DRAWING NO.

OUT

REV

FORMAT

RECEIVED DATE

REV

40

ROAD, STONE PITCHING & BOUNDARY WALL LAYOUT FOR


DARBHANGA

PDF

12-Jan-15

41

DETAILS OF BOUNDARY WALL FOR DARBHANGA

PDF

12-Jan-15

42

GEOTECHNICAL INVESTIGATION REPORT For 400 KV D/C


MUZAFFARPUR TO DARBHANGA TRANSMISSION LINE

PDF

21-Jan-15

43

Geotechnical Investigation Report for LILO of 400KV D/C BarhGorakhpur to Motihari Transmission line

PDF

24-Jan-15

44

DETAILS OF BOUNDARY WALL FOR MOTIHARI

PDF

27-Jan-15

45

ROAD, STONE PITCHING & BOUNDARY WALL LAYOUT FOR


MOTIHARI

PDF

27-Jan-15

46

Section of 400/132kV-MOTIHARI

PDF

27-Jan-15

47

Design Basis Report for Diesel Generator Set

PDF

28-Jan-15

48

Design Basis Report for EOT Cranes

PDF

28-Jan-15

DRAWING / DOCUMENT CONTROL LIST


INPUT
S.NO.

TITLE

DOCUMENT/DRAWING NO.

OUT

REV

FORMAT

RECEIVED DATE

49

500MVA- 400/220/33KV Foundation Drawing

PDF

28-Jan-15

50

500MVA- 400/220/33KV General Arrangement-1

PDF

28-Jan-15

51

500MVA- 400/220/33KV General Arrangement-2

PDF

28-Jan-15

52

500MVA- 400/220/33KV ICT Transport Drawing

PDF

28-Jan-15

53

500MVA- 400/220/33KV HV Bushing- 420kV, 1250A

PDF

28-Jan-15

54

500MVA- 400/220/33KV MV Bushing- 245kV, 2000A

PDF

28-Jan-15

55

500MVA- 400/220/33KV LV Bushing- 52kV, 3150A

PDF

28-Jan-15

56

500MVA- 400/220/33KV HVN Bushing- 36kV, 2000A

PDF

28-Jan-15

57

500MVA- 400/220/33KV ICT Rating Plate

PDF

28-Jan-15

58

500MVA- 400/220/33KV ICT Valve Schedule Plate

PDF

28-Jan-15

59

DESIGN BASIS REPORT for LT Switchgear

PDF

31-Jan-15

60

SLD-AC/DC AUXILIARY SYSTEM- MOTIHARI

PDF

31-Jan-15

61

SLD-AC/DC AUXILIARY SYSTEM- DARBHANGA

PDF

31-Jan-15

62

Design Basis Report for Gas Insulated Switchgear

PDF

3-Feb-15

63

200MVA- 400/132/33KV Foundation Drawing

PDF

4-Feb-15

64

200MVA- 400/132/33KV General Arrangement-1

PDF

4-Feb-15

65

200MVA- 400/132/33KV General Arrangement-2

PDF

4-Feb-15

66

200MVA- 400/132/33KV ICT Transport Drawing

PDF

4-Feb-15

67

200MVA- 400/132/33KV HV Bushing- 420kV, 1250A

PDF

4-Feb-15

REV

DRAWING / DOCUMENT CONTROL LIST


INPUT
S.NO.

TITLE

DOCUMENT/DRAWING NO.

OUT

REV

FORMAT

RECEIVED DATE

68

200MVA- 400/132/33KV MV Bushing- 245kV, 2000A

PDF

4-Feb-15

69

200MVA- 400/132/33KV LV Bushing- 52kV, 3150A

PDF

4-Feb-15

70

200MVA- 400/132/33KV HVN Bushing- 36kV, 2000A

PDF

4-Feb-15

71

200MVA- 400/132/33KV ICT Rating Plate

PDF

4-Feb-15

REV

DRAWING / DOCUMENT CONTROL LIST


INPUT
S.NO.

TITLE

DOCUMENT/DRAWING NO.

OUT

REV

FORMAT

RECEIVED DATE

72

200MVA- 400/132/33KV ICT Valve Schedule Plate

PDF

4-Feb-15

73

Short circuit calculation for flexible conductor (as per IEC 60865 and
IEEE 605)- MOTIHARI

PDF

4-Feb-15

74

Sag - Tension calculation (as per IS 5613 and IS 802)- MOTIHARI

PDF

4-Feb-15

75

Temperature rise calculation for rigid conductor (as per IEEE 605)DARBHANGA

PDF

4-Feb-15

76

Temperature rise calculation for flexible conductor (as per IEC TR


61597)- DARBHANGA

PDF

4-Feb-15

77

Temperature rise calculation for rigid conductor (as per IEEE 605)MOTIHARI

PDF

4-Feb-15

78

Temperature rise calculation for flexible conductor (as per IEC TR


61597)- MOTIHARI

PDF

4-Feb-15

REV

DRAWING / DOCUMENT CONTROL LIST


INPUT
S.NO.

TITLE

DOCUMENT/DRAWING NO.

REV

FORMAT

OUT
RECEIVED DATE

REV

DRAWING / DOCUMENT CONTROL LIST


INPUT
S.NO.

TITLE

DOCUMENT/DRAWING NO.

REV

FORMAT

OUT
RECEIVED DATE

REV

DRAWING / DOCUMENT CONTROL LIST


INPUT
S.NO.

TITLE

DOCUMENT/DRAWING NO.

REV

FORMAT

OUT
RECEIVED DATE

REV

OUTPUT
FORMAT

SUBMISSION DATE

PDF

2-Dec-14

PDF

3-Dec-14

PDF

3-Dec-14

PDF

4-Dec-14

PDF

4-Dec-14

PDF

4-Dec-14

PDF

4-Dec-14

PDF

4-Dec-14

PDF

4-Dec-14

PDF

4-Dec-14

PDF

4-Dec-14

PDF

4-Dec-14

PDF

4-Dec-14

PDF

17-Dec-14

PDF

22-Dec-14

PDF

17-Dec-14

REMARKS

OUTPUT
FORMAT

SUBMISSION DATE

PDF

20-Dec-14

PDF

19-Dec-14

PDF

22-Dec-14

PDF

22-Dec-14

REMARKS

OUTPUT
FORMAT

SUBMISSION DATE

DOC.

19-Dec-14

DOC.

19-Dec-14

DOC.

20-Dec-14

DOC.

27-Dec-14

DOC.

27-Dec-14

DOC.

27-Dec-14

DOC.

7-Jan-15

DOC.

7-Jan-15

DOC.

7-Jan-15

DOC.

7-Jan-15

DOC.

7-Jan-15

DOC.

9-Jan-15

PDF

10-Jan-15

PDF

19-Jan-15

REMARKS

OUTPUT
FORMAT

SUBMISSION DATE

PDF

20-Jan-15

PDF

20-Jan-15

DOC.

9-Jan-15

PDF

19-Jan-15

PDF

21-Jan-15

REMARKS

OUTPUT
FORMAT

SUBMISSION DATE

PDF

20-Jan-15

PDF

20-Jan-15

PDF

23-Jan-15

PDF

29-Jan-15

PDF

2-Feb-15

PDF

2-Feb-15

PDF

2-Feb-15

PDF

29-Jan-15

PDF

29-Jan-15

REMARKS

OUTPUT
FORMAT

SUBMISSION DATE

REMARKS

OUTPUT
FORMAT

SUBMISSION DATE

REMARKS

OUTPUT
FORMAT

SUBMISSION DATE

REMARKS

OUTPUT
FORMAT

SUBMISSION DATE

REMARKS

OUTPUT
FORMAT

SUBMISSION DATE

REMARKS

OUTPUT
FORMAT

SUBMISSION DATE

REMARKS