In Dev.

# 1 and
4, zone# 4,
cluster# 2,
unit# 8 EFECO
workers are
using Damaged
electrical power
cables to
perform their
activities.

In Dev.# 4
zone# 2,
cluster# 8,
unit# 11
electrical
work in in
process
inside the
building and
broken
wooden
planks are
used as
access/
egress to
enter the
building.

In Dev.# 3
and 4
Excavations
are open
without
adequate
barrication
and warning
sings while
MEP work is
in progress
in these
developmen
ts.

In Dev.# 1,
zone# 2,
cluster# 3,
electrical
department
driver has not
secured loose
material
while
shifting.

In Dev.# 3 one# 3,
cluster# 3 electrical
workers are
performing their
job while place
ladder at edge
point without
appropriate
barricade and full
body harness.