from OPERATION side to E/M EQ4PD-0014 Rev : 01 Finishing Time NO
Person in Charge
ITEM Date
Time
Group Leader
Supervisor
1 Liquid Draw Off
2 PW flushing 3 Ethylene / NG isolation 4 Liquid Hold isolation 5 PA Purge 6 O2 check (target O2 conc. = 21%) 7 Flammable gas ( less than : 1000 ppm) 8 MCC off
Note : After finish above confirmation, operation side can hand over the plant to E/M