2G Swop preparation

Pre-requisites
25 sites ready
Transmission
MSS site creation
ISP
BSC Acceptance
Acceptance KPI document

Swop preparartion - few days before Swop


XML download
XML verify
network freeze 3 days before.
MSS check
Access letter for Airport runway
Drive test

Swop Schedule
Schedule stategy - CBD last
Schedule

Swop Process
To be discussed

2G Swop Process
Estimated downtime per sector is 1 hour.
Time
08H00

Task
Sector 1
Huawei to switch off 1st sector
NI team to pull down existing Huawei antenna
New Nokia antenna to be installed at same height and azimuth as Huawei antenna, tilts to be as per design
Sector to be unlocked and brought on air
1st CS and PS call by NI team

Responsible party

Name

Huawei
Nokia
Nokia
Nokia
Nokia

Taworn
Taworn
Amit
Taworn

Sector 2
Huawei to switch off 1st sector
NI team to pull down existing Huawei antenna
New Nokia antenna to be installed at same height and azimuth as Huawei antenna, tilts to be as per design
Sector to be unlocked and brought on air
1st CS and PS call by NI team

Huawei
Nokia
Nokia
Nokia
Nokia

Taworn
Taworn
Amit
Taworn

Sector 3
Huawei to switch off 1st sector
NI team to pull down existing Huawei antenna
New Nokia antenna to be installed at same height and azimuth as Huawei antenna, tilts to be as per design
Sector to be unlocked and brought on air
1st CS and PS call by NI team

Huawei
Nokia
Nokia
Nokia
Nokia

Taworn
Taworn
Amit
Taworn

Site Verification
DT team to conduct site verification tests once site is up and alarm free
DT logs to be provided to Nokia for analysis and SSV template completion
Results/Report of SSV to be shared with NetOne {DM}

Nokia
Nokia
Nokia
Nokia

Sharif
Sharif
Sharif

Site monitoring
Daily report

Nokia
Nokia

Derrick

OSS stats reporting


Daily report

Nokia
Nokia

Derrick

Da
TASKS
Site Installtion
XML Creation
OSS KPI for GSM creation in NetAct
SWAP sites by NI
SSV Complete
Weekly OSS KPI submission
Cluster Drive Test Complete
Site Acceptance
Cluster Acceptance

Start Date
11/1/2014
12/1/2014
1/15/2015
2/2/2015
2/3/2015
2/7/2015
3/2/2015
3/3/2015
3/15/2015

Duration
70
45
15
28
35
60
15
30
30

Site Installtio

XML Creat

OSS KPI for GSM creation in NetA

SWAP sites by

SSV Comple

Weekly OSS KPI submissio

Cluster Drive Test Comple

Site Acceptan

Cluster Acceptan

Days
Complete

Incomplete
70
45
12
0
0
0
0
0
0

Site Installtion
XML Creation

I for GSM creation in NetAct


SWAP sites by NI
SSV Complete

Weekly OSS KPI submission

Cluster Drive Test Complete


Site Acceptance
Cluster Acceptance

0
0
3
28
35
60
15
30
30

Incomplete
Complete
Start Date