SULTANATE OF OMAN

MINISTRY OF TRANSPORT AND COMMUNICATIONS


DIRECTORATE GENERAL OF ROADS & LAND TRANSPORT
MUSCAT

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT


TENDER NO. 51/2012
MONTHLY PROGRESS REPORT NO. 12
DECEMBER 2014

CONSULTANT:

CONTRACTOR:

RENARDET S.A. & PARTNERS CONSULTING


ENGINEERS LLC.
P.O. Box 579, Muscat, P.C. 100,
Sultanate of Oman

P.O. Box 614,


Muscat, P.C. 100,
Sultanate of Oman

CONSOLIDATED CONTRACTORS CO. LLC

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

Table of Contents
1.

PROJECT PARTICULARS .............................................................................................................................................. 2

2.

SCOPE OF WORK ....................................................................................................................................................... 3

3.

TYPICAL CROSS SECTIONS .......................................................................................................................................... 4

4.

SITE VISITS/ MEETINGS .............................................................................................................................................. 6

5.

ENGINEERS SITE STAFF ............................................................................................................................................. 7

6.

PROGRESS S-CURVE ................................................................................................................................................... 8

7.

STATUS OF MAJOR ACTIVITIES ................................................................................................................................ 10

8.

BRIDGE PROGRESS SCHEDULE ................................................................................................................................. 11

9.

MSE WALLS PROGRESS SCHEDULE ........................................................................................................................... 12

10.

BOX CULVERTS PROGRESS SCHEDULE...................................................................................................................... 14

11.

PROGRESS STATUS OF UTILITY CROSSING DUCTS .................................................................................................... 18

12.

PROJECT PROGRESS STRIP CHART ........................................................................................................................... 21

13.

FINANCIAL STATUS OF PAYMENTS .......................................................................................................................... 27

14.

DETAILS OF EQUIPMENT AVAILABLE AT SITE ........................................................................................................... 28

15.

DETAILS OF MANPOWER AVAILABLE AT SITE .......................................................................................................... 30

16.

QA/QC REPORTS...................................................................................................................................................... 32

17.

STATUS OF MATERIAL APPROVALS .......................................................................................................................... 36

18.

ENGINEERS COMMENTS ......................................................................................................................................... 38

19.

CORRESPONDENCE DURING THE MONTH................................................................................................................ 39

20.

PROGRESS PHOTOGRAPHS ...................................................................................................................................... 42

RENARDET S.A. & PARTNERS

Page 1

Monthly Progress Report December 2014

Project: Upgrading of Falaj Al Qabail Roundabout

1. Project Particulars
Client:

Ministry of Transport & Communications


P.O. Box 684, Muscat, Postal Code 113
Directorate General of Roads
Sultanate of Oman.

Consultant:

Renardet S.A & Partners L.L.C.


P.O. Box 579, Muscat, Postal Code 100
Sultanate of Oman.

Contractor:

Consolidated Contractors Company L.L.C.


P.O. Box 614, Muscat, Postal Code 100
Sultanate of Oman.

Project Commencement Date:

30.10.2013

Mobilization Period:

60 Days

Construction Period:

548 Days

Completion date:

29.06.2015

Original Contract Value:


(Including Contingencies)

R.O. 17,884,403.000

Amount of Contingencies:

R.O. 1,402,155.613

Original Contract Value:


(Excluding Contingencies)

R.O. 16,482,247.387

Planned Physical Progress for December


2014

8.32%

Actual Physical Progress for December


2014

6.89%

Planned physical progress cumulative up to


end of December 2014
Achieved physical progress cumulative up
to end of December 2014

RENARDET S.A. & PARTNERS

63.86%

58.30%

Page 2

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

2. Scope of Work
This project is located in Batinah Region on existing Batinah Highway in the Wilayat Sohar and
consists of construction of an interchange in place of existing roundabout along with allied works.
Total length of the project along Batinah highway is about 4.0 km which shall be converted from four
lanes to six lanes with tapering back to 4lanes, all as shown on plans. Also included in the scope of
work is the construction of service roads, pedestrian underpasses.
The work also includes expropriation of properties, relocation/protection of services (sewerage,
telephone, electricity, water, irrigation) road lighting works and traffic signals.
Major items within the scope of work consist of but not limited to the following:

Removal of existing asphalt surface, extension of existing embankment and earthwork to


achieve the designed profile and gradient.
Removal of existing drainage structures and construction of new ones including protection
works as shown on construction drawings and as directed.
Expropriation of open/built up properties and removal of existing structures thereupon.
Construction of interchange ramps, Box Girder Bridge, roundabout, pedestrian underpasses and
service roads.
Provision of new street lighting system/traffic signals and removal/disposal of existing street
light poles including conductors/cables, transformers, feeder pillars, foundations etc., all for the
proper completion of the job.
Construction of earthen embankment/sub grade, sub-base, aggregate base course, bituminous
base course and bituminous wearing course as per details on the construction drawings.
Installation of road side furniture (traffic signs, road marking etc.) and protection works on
embankment slopes.
Relocation/Protection of existing LT, 11KV and 33KV transmission lines and allied items
(transformers etc.) as per the requirements of concerned authority.
Relocation/Protection of existing utilities (sewerage, telephone, electricity, water lines and
irrigation) as per the requirements of concerned authorities.
Provision of ducts for future utilities as per the requirements of utility operator.
Construction of concrete safety barriers, fixing of guard rails and paving tiles.
Provision of traffic diversion in coordination with concerned authorities

RENARDET S.A. & PARTNERS

Page 3

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

3. Typical Cross Sections

RENARDET S.A. & PARTNERS

Page 4

Project: Upgrading of Falaj Al Qabail Roundabout

RENARDET S.A. & PARTNERS

Monthly Progress Report December 2014

Page 5

Monthly Progress Report December 2014

Project: Upgrading of Falaj Al Qabail Roundabout

4. Site visits/ Meetings


S. No.

Details of Site Visit/ meeting

Date

Final Outcome/ Decisions

Visit to M/s Assarain Concrete


Products, Muscat for inspection of
Process control of Paving Blocks

11.12.2014

Found that the process and quality


control measures are effectively
implemented.

Monthly review meeting at DGR Office

25.12.2014

The project progress and various


project issues are discussed.

RENARDET S.A. & PARTNERS

Page 6

Monthly Progress Report December 2014

Project: Upgrading of Falaj Al Qabail Roundabout

5. Engineers Site Staff


S.
Name
No.
1. Roberto Benigni

Designation

Date of
Joining

Head Supervision Projects

2.

Muneer Abdul

Resident Engineer

19.03.2014

3.

Hussein Shah

Material Engineer

04.01.2014

4.

Ernesto B. Paredes

Bridge Engineer

16.04.2014

5.

Sande H Tangaras

Civil Engineer

08.06.2014

6.

Danilo

Quantity Surveyor

19.06.2014

6.

Mohamed Safie

Land Surveyor

04.01.2014

7.

Aseef Iqbal

Site Inspector

10.02.2014

8.

Alaa Aldin Abdelfatah

Site Inspector

30.03.2014

9.

Walid Samy Abdoh Mostafa

Material Inspector

01.04.2014

Secretary

13.04.2014

10. Haneefa Mohmmed Al Zadjali

RENARDET S.A. & PARTNERS

Page 7

Monthly Progress Report December 2014

Project: Upgrading of Falaj Al Qabail Roundabout

6. Progress S-Curve
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT PROJECT - OMAN
MONTHLY CL 14 PLANNED VS. ACTUAL MANHOURS

12

120.00

MONTHS

Actual per Month

2013

CL14 Org Plan Cumulative %

Revised Sch. Cummulative %

2014
Jan

Feb

Mar

Apr

May

Jun

Actual Cumulative

2015
Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

CL14 Org Plan per Month %

0.01

0.25

1.42

4.23

7.25

10.06

9.42

9.73

10.21

9.79

8.49

5.72

4.55

3.56

2.79

3.83

3.55

3.47

1.67

Revised Sch. per Month %

0.11

0.14

0.23

0.28

1.71

3.18

6.84

9.16

9.14

9.08

7.69

7.98

8.32

6.96

6.50

4.68

3.59

3.34

4.42

Actual per Month

0.28

Oct

Sep

Aug

Jul

Jun

May

Apr

Feb

2015

Revised Sch. per Month %

Dec

CUMULATIVE PROGRESS

Jan

2014

CL14 Org Plan per Month %

MONTHLY PROGRESS

Nov

Sep

Jun

2013

Mar

0.00

Dec

Oct

20.00

Aug

Jul

40.00

May

Apr

60.00

Mar

Feb

80.00

Jan

% Cumulative

100.00

Dec

% MONTHLY

10

0.18

1.01

3.39

5.15

5.18

7.36

7.30

9.33

6.20

6.02

6.89

Jul
3.29
-

Aug
1.64
-

Sep
1.11
-

Oct
0.62
-

CL14 Org Plan Cum ulative %

0.01

0.26

1.67

5.91

13.15

23.21

32.64

42.37

52.58

62.37

70.86

76.59

81.13

84.69

87.48

91.31

94.86

98.33

100.00

100.00

100.00

100.00

100.00

Revised Sch. Cum m ulative %

0.11

0.25

0.48

0.76

2.47

5.64

12.48

21.64

30.78

39.87

47.55

55.53

63.86

70.81

77.31

81.99

85.59

88.93

93.35

96.64

98.27

99.38

100.00

Actual Cum ulative

RENARDET S.A. & PARTNERS

0.28

0.45

1.46

4.86

10.01

15.19

22.55

29.86

39.18

Page 8

45.39

51.41

58.30

Monthly Progress Report December 2014

Project: Upgrading of Falaj Al Qabail Roundabout

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT - OMAN

REV.:
0
PERIOD ENDING:

Dec-14

MANHOURS OVERALL PROJECT S-CURVE

Item

Description

Budgeted
Man-Hrs

56,423

Road Diversions

Wtd.
%

2.73

Plan/
Actual

2013
Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

CL14 Plan %

0.30

8.67

19.23

26.89

31.77

36.64

41.51

46.39

51.26

56.13

61.01

65.88

70.76

75.63

80.50

85.38

90.25

95.13

100.00

100.00

100.00

100.00

100.00

80.93

84.74

88.56

92.37

96.18

100.00

100.00

100.00

100.00

100.00

100.00

100.00

80.66

87.59

88.57

100.00

100.00

100.00

Revised Plan %
Actual

CL14 Plan %

Clearing &
Removal of
Obstructions

19,558

Embankment

74,043

0.95

3.59

14,821

Subbase &
Aggregate Base

50,004

Bituminous
Pavement

73,724

0.72

42.78

46.60

50.41

54.23

58.04

61.86

44.11

51.21

56.24

60.13

65.67

69.96

74.25

0.00

0.38

20.37

47.70

48.33

48.33

48.33

48.33

3.57

48.33

48.33

48.33

48.33

29.85

78.13

78.13

78.13

78.13

78.13

78.13

Actual

10.09

10.09

17.59

19.52

77.42

69.96

70.18

70.18

70.18

83.49

84.12

84.95

0.00

0.00

0.78

0.00

Revised Plan %

Actual

Revised Plan %

Revised Plan %

0.00
0.00
-

0.00
0.00
-

1.01
0.00
-

9.21
5.00
0.00
-

6.58
4.35
29.30
5.00
0.00
-

16.76
4.89
45.91

29.38

41.37

58.64

Revised Plan %

66.60

0.00
-

0.00
-

0.00
-

0.00
-

82.85

84.75

3.32

12.89

28.83

43.89

60.03

74.82

5.27

14.93

29.52

47.15

47.31

67.50

56.90

62.24

64.59

67.94

69.08

69.08

75.05

4.26

8.17

16.03

32.68

53.13

67.05

67.47

67.47

53.23
0.00

62.16
0.00

74.91
0.00

78.29
11.07

91.86
26.27

98.62
41.98

115.33
59.98

148.20
78.73

3.58

17.42

5.42

10.68

1.26
0.00

74.18

Actual
0.00
-

0.00
-

0.00
-

0.00
-

0.08
-

3.19
7.77
-

19.32
-

31.22
-

65.67
59.91
78.13
84.75
90.03
82.85
67.90
79.90
31.37
44.94
0.08

69.48
77.84
78.13
85.24
95.24
93.48
68.32
79.90
51.32
51.98
8.44

73.30
90.27
78.13
92.34
95.95
98.64
68.32
85.20
75.82
52.14
22.42

77.11
94.93
78.13
92.34

100.00

100.00

100.00

100.00

100.00

95.95

96.09

98.30

99.46

99.54

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

68.32

81.11

93.02

97.11

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

75.82

87.25

87.25

98.60

100.00

100.00

100.00

100.00

100.00

100.00

51.97

86.66

90.05

93.03

100.00

89.45
75.82
90.14
46.57

98.36

92.60
75.82
90.14
51.97

Actual
CL14 Plan %

Concrete for
Box Culvert
/Underpas

788,138

Concrete for
Bridge

456,522

38.19

22.12

1.50

Incidental
Construction

275,037

MSE walls

141,190

13.33

6.84

MEP Works &


Ducts

83,264

2,063,644

4.03

100.000

0.00

0.23

1.43

2.97

10.17

51.47

63.06

74.26

75.97

77.37

0.26

2.64

7.33

20.62

35.14

50.06

62.76

68.40

72.78

74.07

Actual

0.48

1.26

5.59

14.93

27.72

40.08

55.38

66.20

71.35

77.45

Revised Plan %

0.00
0.00

0.00
0.00

4.02
0.00

Revised Plan %

Actual

0.00

0.00

0.00

15.21
0.01
0.00
2.50
0.00

34.62

71.33

6.05
0.00

14.73
0.38

18.14
1.21

22.33
2.63

26.30
3.42

30.75
4.23

34.14
5.50

46.19
6.08

56.00
6.08

8.09

26.17

57.85

49.42

14.39

13.24

16.19

16.72

27.56

21.22

41.44

54.32

0.00

0.00

2.80

0.00

Actual

0.00

0.00

0.00

Revised Plan %

Actual

Revised Plan
Actual Cum

0.11
-

4.43
6.16
0.00
-

99.96

59.51

Actual

92.89

49.64

0.00

84.50

39.02

83.46

29.64

0.00

83.38

22.09

81.40

13.76

0.00

69.26

7.75

Revised Plan %

Revised Plan %

57.89

2.77

17.23
9.87
0.00
-

0.13

5.52

2.61
33.36

4.98

6.42
65.07

17.87
8.31
80.79

43.85

61.59

72.98

81.15

7.02

20.33

38.29

10.67

12.36

14.45

16.54

93.82

100.00

100.00

100.00

100.00

100.00

74.67

83.42

84.04

84.30

87.32

95.58

98.11

99.44

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

85.14

87.00

93.50

100.00

100.00

100.00

100.00

100.00

100.00

100.00

99.76

100.00

100.00

100.00

100.00

100.00

100.00

94.70

98.41

100.00

100.00

100.00

100.00

34.35
78.53
83.94

82.40

99.38
94.70
84.42

88.97

99.76
94.70
85.35

92.13

94.70
92.86

98.55

100.00

100.00

100.00

100.00

100.00

50.60

59.52

72.89

81.07

96.39
83.55

86.89

90.26

95.34

98.27

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

2.30

17.26

33.64

49.01

64.70

79.88

95.44

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

17.63

25.69

35.90

49.03

65.95

72.27

72.29

83.86

0.17

0.79

1.43

5.65

70.94

75.04

94.02

96.43

49.13

80.05

0.99

13.41

21.84

30.56

32.94

0.33

2.34

9.42

17.07

23.51

31.40

9.26

13.38

16.87

17.75

20.45

14.38

26.70

24.67

100.00

100.00

100.00

100.00

100.00

100.00

41.66

47.49

47.55

47.55

83.28

93.95

97.61

100.00

100.00

100.00

0.25

0.48

0.76

2.47

5.64

12.48

21.64

30.78

39.87

47.55

55.53

63.86

70.81

77.31

81.99

85.59

88.93

93.35

96.64

98.27

99.38

100.00

0.28

0.45

1.46

4.86

10.01

15.19

22.55

29.86

39.18

45.39

51.41

58.30

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Jun

Jul

Aug

2014

2013
Jan

Feb

Mar

Apr

2015
Jan

Feb

Mar

Apr

May

Sep

Oct

CL14 Org Plan per Month %

0.01

0.25

1.42

4.23

7.25

10.06

9.42

9.73

10.21

9.79

8.49

5.72

4.55

3.56

2.79

3.83

3.55

3.47

1.67

Revised Sch. per Month %

0.11

0.14

0.23

0.28

1.71

3.18

6.84

9.16

9.14

9.08

7.69

7.98

8.32

6.96

6.50

4.68

3.59

3.34

4.42

3.29

1.64

1.11

0.62

Actual per Month

CUMULATIVE PROGRESS

36.51

Dec

MONTHLY PROGRESS

23.65

Actual
CL14 Plan %
30,920

0.00

Revised Plan %
CL14 Plan %

Drainage Works

TOTAL

38.97

43.00
7.40

CL14 Plan %

35.16

37.31
-

CL14 Plan %

30.90

22.36
-

CL14 Plan %

24.18

13.03
-

CL14 Plan %

17.58

6.62
-

Actual
CL14 Plan %
2.42

0.00

9.30

CL14 Plan %

Structural
Excavation

2015

Revised Plan %
CL14 Plan %

4.11

2014

0.28

0.18

1.01

3.39

5.15

5.18

7.36

7.30

9.33

6.20

6.02

6.89

CL14 Org Plan Cum ulative %

0.01

0.26

1.67

5.91

13.15

23.21

32.64

42.37

52.58

62.37

70.86

76.59

81.13

84.69

87.48

91.31

94.86

98.33

100.00

100.00

100.00

100.00

100.00

Revised Sch. Cum m ulative %

0.11

0.25

0.48

0.76

2.47

5.64

12.48

21.64

30.78

39.87

47.55

55.53

63.86

70.81

77.31

81.99

85.59

88.93

93.35

96.64

98.27

99.38

100.00

0.28

0.45

1.46

4.86

10.01

15.19

22.55

29.86

39.18

45.39

51.41

58.30

Actual Cum ulative

RENARDET S.A. & PARTNERS

Page 9

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

7. Status of Major Activities


Sl.
No.

Description

Unit

BOQ Qty.
(Revised)

Actual
Qty.

%
Completion

Clearing & Grubbing

M2

162,000

138,801

85.67%

Borrow Excavation (to


embankment)
Granular Sub-base

M3

340,000

221,412

65.12%

M3

28,700

10,499

36.58%

M3

15,000

13,207

88.04%

Concrete for Culverts (1st


stage)
Concrete for Bridge

M3

9,500

4,696

49.43%

Steel reinforcement Fixing

ton

4,900

2,974

60.69%

Working Piles

M3

2,826

2,826

100.00%

Mortared Stone Riprap

M3

5,210

0.00

0.00%

MSE Walls Fixing

M2

13,030

8,461

64.93%

10

RCC Drainage Pipes

LM

4,530

1,856

40.97%

11

Aggregate Base Course

M3

70,300

2,220

3.16%

3
4

RENARDET S.A. & PARTNERS

Page 10

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

8. Bridge Progress Schedule


SUB-STRUCTURE WORK PROGRESS (LHS)
P3L
P1L
P2L
P4L

ACTIVITY

P5L

AB1 L

9-Nov-14 9-Nov-14 9-Nov-14 15-Nov-14

PEDESTAL/POT BEARING

N/A

PIER
2nd Lift

Height (m)

1st Lift

Height (m)

24-Jul-14

13-Aug-14 19-Aug-14
6.920

N/A

6.920

1.248

15-Sep-14 10-Aug-14

1.440

1.210

6.920

29-Jun-14

23-Jul-14 7-Aug-14

29-Sep-14 4-Sep-14

6.920

6.920

1.153

AB2 L

1.225

17-May-14

4-Sep-14 23-Jun-14

PILE CAP (Pier & Abut.) 4-Nov-14 17-May-14 18-Jun-14

8-May-14

25-Aug-14 11-Jun-14

21-Oct-14 11-May-14 11-Jun-14

1-May-14

17-Aug-14 3-Jun-14 24-Dec-14

BIT. PAINTING

F/P & BLINDING

28-May-14 26-Jun-14

SUB-STRUCTURE WORK PROGRESS (RHS)


AB1 R
P3R
P1R
P2R
P4R

ACTIVITY

16-Oct-14 14-Oct-14 14-Oct-14 16-Oct-14

PEDESTAL/POT BEARING

N/A

PIER
2nd Lift

Height (m)

1st Lift

Height (m)

22-Jun-14

9-Jun-14 28-Jun-14
6.920

6.920

6.920

0.649

0.423

P5R

AB2 R

N/A

20-Sep-14 10-Jul-14
6.920

26-May-14

20-May-14 11-Jun-14
0.366

6.920

10-Sep-14 22-Jun-14
0.461

0.438

12-May-14 25-May-14

8-May-14

PILE CAP (Pier & Abut.)

9-Oct-14

4-May-14 13-May-14

30-Apr-14

27-Aug-14 20-May-14 22-Dec-14

F/P & BLINDING

2-Oct-14 27-Apr-14 7-May-14

22-Apr-14

20-Aug-14 14-May-14 14-Dec-14

BIT. PAINTING

4-Sep-14 31-May-14

BRIDGE SUPER-STRUCTURE PROGRESS SCHEDULE (BOX GIRDER)


ACTIVITY (LHS)
EXPANSION JOINT

SUPER-STRUCTURE (BRIDGE 4 - LHS)SUPER-STRUCTURE (BRIDGE 3 - LHS)


AB1 L
AB2 L
P1L
P2L
P3L
P3L
P4L
P5L
-

N/A

N/A

N/A

CONCRETE BARRIER

Grouting

Prestressing

TOP SLAB (DECK)


WEB:
W1
W2
W3
W4
BOTTOM SLAB

ACTIVITY (RHS)
EXPANSION JOINT

16-Dec-14
16-Dec-14
16-Dec-14
16-Dec-14
7-Dec-14

16-Dec-14
16-Dec-14
16-Dec-14
16-Dec-14
7-Dec-14

16-Dec-14
16-Dec-14
16-Dec-14
16-Dec-14
7-Dec-14

N/A

N/A

N/A
-

Grouting

12/13/2014

Prestressing

12/7/2014

W1
W2
W3
W4
BOTTOM SLAB

16-Dec-14
16-Dec-14
16-Dec-14
16-Dec-14
7-Dec-14

Dec-14

WEB:

SUPER-STRUCTURE (BRIDGE 1 - RHS)SUPER-STRUCTURE (BRIDGE 2 - RHS)


AB1 R
AB2 R
P1R
P2R
P3R
P3R
P4R
P5R

CONCRETE BARRIER

TOP SLAB (DECK)

N/A

26-Nov-14
10-Nov-14
10-Nov-14
10-Nov-14
10-Nov-14
28-Oct-14

26-Nov-14
10-Nov-14
10-Nov-14
10-Nov-14
10-Nov-14
28-Oct-14

RENARDET S.A. & PARTNERS

26-Nov-14
10-Nov-14
10-Nov-14
10-Nov-14
10-Nov-14
28-Oct-14

N/A

26-Nov-14
10-Nov-14
10-Nov-14
10-Nov-14
10-Nov-14
28-Oct-14

Page 11

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

9. MSE Walls Progress Schedule


MSE WALL MONTHLY SCHEDULE (FOUNDATION @ APPROACH 1)
PREVIOUS

Elevation

El. 20.40

El. 21.20

El. 22.00

El. 22.80
El. 22.00

THIS MONTH

LA S T M O N T H

LOCATION (LHS)
FROM
TO
22+702.653
22+760
22+760

22+825

22+825

22+840

22+840

22+880

22+880

22+908.387

22+908.387 22+969.478
22+969.478

23+000

23+000

23+025

23+025

23+070

23+070

23+140

23+140

23+164.573

23+164.573 23+237.536
23+237.536 23+270.762

DATE

Elevation

FOUNDATION

2-Oct-14
3-Oct-14
30-Sep-14
1-Oct-14
13-Jul-14
14-Jul-14
6-Jul-14
13-Jul-14
10-Aug-14
11-Aug-14
3-Jul-14
5-Jul-14
4-Aug-14
5-Aug-14
20-Jul-14
21-Jul-14
17-Jul-14
18-Jul-14
30-Jun-14
1-Jul-14
16-Jun-14
17-Jun-14
23-Jun-14
24-Jun-14
17-Jun-14
18-Jun-14

El. 20.40

El. 21.20

El. 22.00

El. 22.80

El. 22.00

Elevation
El. 22.00

LOCATION (RHS)
FROM
TO
22+718.936
22+810
22+810

22+893.032

22+893.032

22+976.294

22+976.294

23+040

23+040

23+088.046

23+088.046

23+130

23+130

23+191.774

23+191.774

23+270.800

LOCATION (AB 1)
FROM
TO

DATE
FOUNDATION

17-Sep-14
18-Sep-14
9-Aug-14
10-Aug-14
13-Aug-14
14-Aug-14
18-Aug-14
19-Aug-14
26-Jul-14
27-Jul-14
21-Jul-14
22-Jul-14
7-Jul-14
10-Jul-14
26-Jun-14
27-Jun-14

DATE
FOUNDATION

23+270.762 (L) 23+270.800 (R )

26-Jun-14
27-Jun-14

MSE WALL MONTHLY SCHEDULE (FOUNDATION @ APPROACH 2)


Elevation

El. 23.30

El. 24.10

El. 24.90

LOCATION (LHS)
FROM
TO
23+508.239
23+520
23+520

23+580.877

23+580.877

23+650

23+650

23+735

23+735

23+790

23+790

23+827.635

23+827.635 23+949.895

RENARDET S.A. & PARTNERS

DATE
FOUNDATION

15-Sep-14
16-Sep-14
20-Aug-14
21-Aug-14
26-Aug-14
27-Aug-14
1-Sep-14
2-Sep-14
19-Sep-14
20-Sep-14
10-Oct-14
11-Oct-14
15-Oct-14
16-Oct-14

Elevation
El. 23.30

Elevation

El. 23.30

El. 24.10

LOCATION (AB 2)
FROM
TO

DATE
FOUNDATION

23+508.239 (L) 23+508.197 (R )

RHS
FROM

15-Sep-14
16-Sep-14

DATE

23+508.197

TO
23+607.634

23+607.634

23+740

23+740

23+750

23+750

23+950.153

FOUNDATION

8-Sep-14
9-Sep-14
22-Sep-14
23-Sep-14
16-Oct-14
17-Oct-14
3-Nov-14
4-Nov-14

Page 12

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

MSE WALL MONTHLY SCHEDULE (PANELS FIXING @ APPROACH 1)


P R E V IO US
M ON T H

PREVIOUS

ELEV.
31.600
30.800
30.000
29.200
28.400
27.600
26.800
26.000
25.200
24.400
23.600
22.800
22.000
21.200
20.400

ELEV.
32.400
31.600
30.800
30.000
29.200
28.400
27.600
26.800
26.000
25.200
24.400
23.600
22.800
22.000
21.200
20.400

THIS MONTH

LHS (AB 1), from Sta. 22+702.653 to Sta. 23+270.762


22+825

22+908.387

22+969.478

22+991

23+084

23+164.573

23+237.536

23+270.762

22+727
25-Nov-14 25-Nov-14
10-Nov-14 10-Nov-14 10-Nov-14
27-Dec-14 22-Sep-14 22-Sep-14 22-Sep-14
27-Nov-14 3-Sep-14 3-Sep-14 3-Sep-14
28-Aug-14 28-Aug-14 28-Aug-14
-

22+922
9-Dec-14
4-Dec-14
5-Nov-14
29-Oct-14
21-Sep-14
11-Sep-14
28-Aug-14
-

22+975
28-Dec-14
22-Dec-14
16-Dec-14
9-Dec-14
4-Dec-14
5-Nov-14
29-Oct-14
17-Sep-14
24-Aug-14
-

28-Dec-14
22-Dec-14
16-Dec-14
18-Nov-14
20-Oct-14
16-Sep-14
4-Sep-14
27-Aug-14
9-Aug-14
-

13-Nov-14
19-Oct-14
18-Oct-14
20-Sep-14
9-Sep-14
4-Sep-14
26-Aug-14
18-Aug-14
13-Aug-14
28-Jul-14
-

13-Nov-14
1-Oct-14
24-Sep-14
18-Sep-14
15-Sep-14
28-Aug-14
19-Aug-14
6-Aug-14
24-Jul-14
-

13-Nov-14
1-Oct-14
24-Sep-14
18-Sep-14
15-Sep-14
28-Aug-14
19-Aug-14
6-Aug-14
24-Jul-14
13-Jul-14
-

22+810
22+791
20-Dec-14
15-Dec-14
27-Nov-14
-

22+840

22+880

RHS (AB 1), from Sta. 22+718.936 to Sta. 23+270.800


AB 1 Face
22+893.03222+976.294 23+035 23+088.04623+191.77423+270.8002 3 +2 7 0 .7 6 2 ( L)2 3 +2 7 0 .8 ( R )
23+116
23+005
24-Dec-14 24-Dec-14
16-Nov-14 30-Sep-14 28-Sep-14 28-Sep-14
22+941 24-Dec-14 24-Dec-14 30-Sep-14 24-Sep-14 24-Sep-14 24-Sep-14
22-Dec-14 22-Dec-14 27-Sep-14 18-Sep-14 19-Sep-14 19-Sep-14
31-Dec-14 16-Nov-14 16-Nov-14 13-Sep-14 13-Sep-14 11-Sep-14 11-Sep-14
1-Dec-14 20-Oct-14 20-Oct-14 2-Sep-14 31-Aug-14 28-Aug-14 28-Aug-14
22+833
18-Nov-14 18-Oct-14 18-Oct-14 24-Aug-14 18-Aug-14 18-Aug-14 18-Aug-14
23-Oct-14 20-Sep-14 20-Sep-14 13-Aug-14 6-Aug-14 7-Aug-14 7-Aug-14
20-Dec-14 25-Sep-14 8-Sep-14 8-Sep-14 9-Aug-14 24-Jul-14 24-Jul-14 24-Jul-14
15-Dec-14 18-Sep-14 21-Aug-14 18-Aug-14
13-Jul-14 13-Jul-14 13-Jul-14
23-Sep-14 26-Aug-14
4-Sep-14
-

MSE WALL MONTHLY SCHEDULE (PANELS FIXING @ APPROACH 2)


LHS (AB 2), from Sta. 23+508.239 to Sta. 23+949.895

ELEV.

23+520

23+580

23+650

23+703

23+730

29.700
28.900
28.100
27.300
26.500
25.700
24.900
24.100
23.300

22-Dec-14
6-Dec-14
8-Nov-14
29-Oct-14
13-Oct-14
25-Sep-14
-

22-Dec-14
6-Dec-14
8-Nov-14
29-Oct-14
13-Oct-14
25-Sep-14
-

24-Dec-14
22-Dec-14
6-Dec-14
15-Nov-14
1-Nov-14
26-Sep-14
-

24-Dec-14
22-Dec-14
6-Dec-14
15-Nov-14
1-Nov-14
26-Sep-14
-

24-Dec-14
22-Dec-14
6-Dec-14
24-Nov-14
16-Nov-14
13-Nov-14
-

ELEV.
28.900
28.100
27.300
26.500
25.700
24.900
24.100
23.300

23+827

23+949

31-Dec-14
27-Dec-14
22-Dec-14 22-Dec-14
20-Dec-14 20-Dec-14
-

AB 2 Face RHS (AB 2), from Sta. 23+508.197 to Sta. 23+950.153


2 3 +5 0 8 ( R )
23+607
23+690
23+740
23+950
22-Dec-14 22-Dec-14 28-Dec-13 28-Dec-13
16-Dec-14 6-Dec-14 10-Dec-13 24-Dec-13
26-Nov-14 26-Nov-14 8-Dec-14 29-Nov-14 29-Nov-14
5-Nov-14
5-Nov-14 11-Nov-14 25-Nov-14 25-Nov-14 22-Dec-14
16-Oct-14 16-Oct-14 15-Oct-14 15-Oct-14 21-Nov-14
30-Sep-14 30-Sep-14 9-Oct-14
2 3 +5 0 8 ( L)

RENARDET S.A. & PARTNERS

Page 13

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

10. Box Culverts Progress Schedule


Note: Precast RCBC were used for all 1 cell - 2.0m x 1.5m locations.

PREVIOUS

THIS MONTH

LAST MONTH

BASE SLAB

WALL

TOP SLAB

NO.

STATION

TYPE & DIMENSION

LENGTH (m)

SKEW ( )

F/P &
BLINDING

Rebars

Concrete

Rebars

Concrete

Rebars

Concrete

Bituminous Paint
(2 Coats)

1
LHS
RHS
RHS
2

21+260
Block 1
Block 2
Block 3
21+485
Block 1a
Block 1b
Block 2a
Block 2b
Block 2C
21+838
Block 1a
Block 1b
Block 2
Block 3
Block 3a
Block 4a
Block 4b
Block 5
Block 6
Block 6a
21+972.4
Block 1
Block 2
Block 3
Block 4
Block 5
Block 6
Block 7
Block 8
Block 9
Block 10
Block 11

3 cells - 2.0 x 1.5


3 cells - 2.0 x 1.5
3 cells - 2.0 x 1.5
3 cells - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
2 x 4 cells (8) - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5

25.546
19.526
14.473
6.000
39.750
3.000
17.290
7.710
10.000
11.730
52.210
5.000
17.600
22.600
5.000
6.970
5.000
17.600
22.600
5.000
6.970
57.629
28.038
28.031
28.026
28.022
28.019
28.018
28.019
28.022
28.026
28.031
28.038

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

19-Oct-14
19-Oct-14
1-Jul-14
1-Jul-14
19-Oct-14
21-Jul-14
3-Jul-14
3-Jul-14
3-Jul-14
21-Jul-14
3-Jul-14
3-Jul-14
3-Jul-14
24-May-14
24-May-14
17-May-14
18-May-14
18-May-14
18-May-14
18-May-14
26-May-14
26-May-14
28-May-14
28-May-14

26-Oct-14
4-Nov-14
31-Aug-14
31-Aug-14
25-Oct-14
4-Sep-14
4-Sep-14
20-Aug-14
8-Dec-14
10-Sep-14
10-Sep-14
23-Sep-14
21-Dec-14
5-Jun-14
9-Jul-14
25-May-14
12-Jul-14
29-May-14
31-Jul-14
10-Jun-14
9-Aug-14
15-Jun-14
17-Aug-14
19-Jun-14

27-Oct-14
4-Nov-14
31-Aug-14
31-Aug-14
25-Oct-14
5-Sep-14
5-Sep-14
20-Aug-14
8-Dec-14
12-Sep-14
12-Sep-14
24-Sep-14
21-Dec-14
5-Jun-14
10-Jul-14
25-May-14
13-Jul-14
29-May-14
31-Jul-14
10-Jun-14
10-Aug-14
15-Jun-14
18-Aug-14
19-Jun-14

9-Nov-14
15-Nov-14
31-Aug-14
31-Aug-14
25-Oct-14
13-Oct-14
13-Oct-14
30-Oct-14
16-Dec-14
18-Oct-14
18-Oct-14
24-Oct-14
27-Dec-14
24-Jun-14
3-Aug-14
3-Jun-14
5-Aug-14
8-Jun-14
12-Aug-14
1-Jul-14
25-Aug-14
7-Jul-14
14-Sep-14
20-Jul-14

9-Nov-14
15-Nov-14
31-Aug-14
31-Aug-14
25-Oct-14
13-Oct-14
13-Oct-14
30-Oct-14
16-Dec-14
19-Oct-14
19-Oct-14
25-Oct-14
27-Dec-14
24-Jun-14
4-Aug-14
3-Jun-14
6-Aug-14
8-Jun-14
13-Aug-14
1-Jul-14
26-Aug-14
8-Jul-14
14-Sep-14
20-Jul-14

9-Nov-14
15-Nov-14
31-Aug-14
31-Aug-14
25-Oct-14
13-Oct-14
13-Oct-14
30-Oct-14
16-Dec-14
18-Oct-14
18-Oct-14
24-Oct-14
27-Dec-14
15-Jul-14
13-Aug-14
23-Jun-14
18-Aug-14
2-Jul-14
27-Aug-14
23-Jul-14
9-Sep-14
4-Aug-14
24-Sep-14
2-Sep-14

9-Nov-14
15-Nov-14
31-Aug-14
31-Aug-14
25-Oct-14
13-Oct-14
13-Oct-14
30-Oct-14
16-Dec-14
19-Oct-14
19-Oct-14
25-Oct-14
27-Dec-14
16-Jul-14
14-Aug-14
23-Jun-14
19-Aug-14
2-Jul-14
28-Aug-14
24-Jul-14
10-Sep-14
5-Aug-14
25-Sep-14
3-Sep-14

26-Nov-14
26-Nov-14
1-Sep-14
1-Sep-14
25-Oct-14
26-Nov-14
26-Nov-14
26-Nov-14
26-Nov-14
26-Nov-14
26-Nov-14
16-Aug-14
8-Sep-14
8-Sep-14
1-Oct-14
1-Oct-14
1-Oct-14
5-Oct-14
26-Nov-14
26-Nov-14
26-Nov-14
25-Sep-14

LHS
RHS
3
LHS
RHS
LHS
RHS
4

LHS

11 x 4 cells (44) - 3.0 x 2.0

1 x 4 cells - 3.0 x 2.0


1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0

RENARDET S.A. & PARTNERS

Page 14

Project: Upgrading of Falaj Al Qabail Roundabout

NO.

RHS

RHS

5
LHS
RHS
LHS
RHS
LHS
RHS

STATION

TYPE & DIMENSION

LENGTH (m)

SKEW ( )

Block 12
Block 13
Block 14
Block 15
Block 16
Block 17
Block 18
Block 19
Block 20
Block 21
Block 22
Block 23
Block 24
Block 25
Block 26
Block 27
Block 28
Block 29
Block 30
Block 31
Block 32
Block 33
22+655
(9 cells)
Block 1
Block 2
Block 3
Block 4
Block 4a
Block 5
Block 6
Block 7
Block 8
Block 9
Block 10
Block 11
Block 12

1 x 4 cells - 3.0 x 2.0


1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
2 x 4 cells (8) - 2.0 x 2.0

21.015
21.010
21.006
21.003
21.001
21.000
21.001
21.003
21.006
21.010
21.015
6.635
6.782
6.819
7.217
7.975
8.571
9.267
9.949
10.260
10.262
10.265
95.482

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
45 R

1 cell - 2.0 x 2.0


1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 cell - 2.0 x 2.0
1 cell - 2.0 x 2.0
1 cell - 2.0 x 2.0
1 cell - 2.0 x 2.0

9.675
32.711
32.711
11.850
13.130
19.035
32.711
32.711
10.95
25.03
32.711
32.711
4.960

45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R

RENARDET S.A. & PARTNERS

Monthly Progress Report December 2014

BASE SLAB

WALL

TOP SLAB

F/P &
BLINDING

Rebars

Concrete

Rebars

Concrete

Rebars

Concrete

Bituminous Paint
(2 Coats)

10-Aug-14
27-Jul-14
27-Jul-14
25-Jul-14
16-Jun-14
16-Jun-14
12-Jun-14
12-Jun-14
8-Jun-14
8-Jun-14
8-Jun-14
24-Nov-14
30-Jun-14
24-Jun-14
11-Sep-14
24-Nov-14
29-Jun-14
24-Jun-14
24-Nov-14
28-Jun-14
29-Jun-14
-

25-Aug-14
22-Sep-14
12-Oct-14
23-Aug-14
27-Jul-14
14-Sep-14
24-Oct-14
16-Oct-14
29-Sep-14
1-Sep-14
25-Jun-14
29-Nov-14
6-Aug-14
21-Jul-14
12-Oct-14
4-Dec-14
27-Jul-14
28-Aug-14
13-Dec-14
20-Aug-14
3-Aug-14
-

26-Aug-14
22-Sep-14
12-Oct-14
23-Aug-14
27-Jul-14
15-Sep-14
24-Oct-14
17-Oct-14
30-Sep-14
2-Sep-14
25-Jun-14
29-Nov-14
7-Aug-14
21-Jul-14
13-Oct-14
4-Dec-14
28-Jul-14
28-Aug-14
13-Dec-14
23-Aug-14
4-Aug-14
-

2-Sep-14
29-Sep-14
15-Oct-14
8-Sep-14
14-Aug-14
23-Sep-14
30-Oct-14
21-Oct-14
1-Oct-14
21-Sep-14
30-Jul-14
4-Dec-14
1-Sep-14
17-Aug-14
22-Oct-14
8-Dec-14
13-Sep-14
24-Sep-14
18-Dec-14
2-Oct-14
2-Oct-14
-

3-Sep-14
29-Sep-14
15-Oct-14
8-Sep-14
14-Aug-14
24-Sep-14
31-Oct-14
21-Oct-14
1-Oct-14
21-Sep-14
30-Jul-14
4-Dec-14
2-Sep-14
18-Aug-14
22-Oct-14
8-Dec-14
14-Sep-14
26-Sep-14
18-Dec-14
3-Oct-14
3-Oct-14
-

1-Oct-14
18-Oct-14
26-Oct-14
18-Sep-14
3-Sep-14
14-Oct-14
7-Nov-14
30-Oct-14
21-Oct-14
30-Sep-14
16-Sep-14
10-Dec-14
1-Sep-14
17-Aug-14
22-Oct-14
18-Dec-14
13-Sep-14
24-Sep-14
24-Dec-14
2-Oct-14
2-Oct-14
-

1-Oct-14
19-Oct-14
27-Oct-14
19-Sep-14
4-Sep-14
15-Oct-14
7-Nov-14
30-Oct-14
21-Oct-14
30-Sep-14
17-Sep-14
10-Dec-14
2-Sep-14
18-Aug-14
22-Oct-14
18-Dec-14
14-Sep-14
26-Sep-14
24-Dec-14
3-Oct-14
3-Oct-14
-

26-Nov-14
26-Nov-14
26-Nov-14
26-Nov-14
26-Nov-14
26-Nov-14
26-Nov-14
26-Nov-14
26-Nov-14
26-Nov-14
25-Sep-14
13-Oct-14
13-Oct-14
13-Oct-14
13-Oct-14
13-Oct-14
13-Oct-14
-

Page 15

Project: Upgrading of Falaj Al Qabail Roundabout

NO.

STATION

TYPE & DIMENSION

LENGTH (m)

SKEW ( )

23+492
(5 cells)
Block 1
Block 2
Block 3
Block 4
Block 5
Block 6
Block 7
Block 8

1 x 4 cells (4) - 3.0 x 2.0


1 cell - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 cell - 3.0 x 2.0
1 cell - 3.0 x 2.0
1 cell - 3.0 x 2.0
1 cell - 3.0 x 2.0

79.065

15 R

6.457
31.546
31.546
7.982
7.039
31.546
31.546
5.525

15 R
15 R
15 R
15 R
15 R
15 R
15 R
15 R

23+756.5
Block 1
Block 2
Block 3a
Block 3b
Block 4
23+997
Block 1
Block 2a
Block 2b
Block 3a
Block 3b
Block 4a
Block 4b
24+235
Block 1a
Block 1b
Block 2a
Block 2b
Block 2c
24+570
Block 1
Block 2a
Block 2b

1 cell - 2.0 x 1.5


1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5

67.550
12.090
20.180
14.430
8.700
12.090
70.268
16.128
4.933
13.860
16.300
4.942
7.848
6.197
59.106
15.566
15.000
8.900
15.600
4.020
51.953
25.846
13.500
12.587

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

LHS
RHS
LHS
RHS
7
LHS
RHS
8
LHS

RHS
9
LHS
RHS
10
LHS
RHS

RENARDET S.A. & PARTNERS

Monthly Progress Report December 2014

BASE SLAB

WALL

TOP SLAB

F/P &
BLINDING

Rebars

Concrete

Rebars

Concrete

Rebars

Concrete

Bituminous Paint
(2 Coats)

24-Jun-14
24-Jun-14
9/172014
24-Jun-14
24-Jun-14
17-Sep-14

9-Jul-14
14-Jul-14
23-Sep-14
5-Aug-14
6-Aug-14
28-Sep-14

9-Jul-14
15-Jul-14
24-Sep-14
5-Aug-14
6-Aug-14
28-Sep-14

30-Jul-14
3-Aug-14
28-Sep-14
-

30-Jul-14
3-Aug-14
28-Sep-14
-

9 & 20/8/2014
11 & 25/8/2014

9 & 23/8/2014
11 & 26/8/2014

12-Jul-14
12-Jul-14
11-Aug-14
8-Jul-14
8-Jul-14
10-Aug-14
10-Aug-14

23-Jul-14
23-Jul-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
26-Aug-14

23-Jul-14
23-Jul-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
26-Aug-14

2-Oct-14
11-Oct-14
23-Jul-14
23-Jul-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
26-Aug-14

2-Oct-14
11-Oct-14
23-Jul-14
23-Jul-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
26-Aug-14

16-Aug-14
21-Aug-14
1-Oct-14
28-Aug-14
31-Aug-14
11-Oct-14
23-Jul-14
23-Jul-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
26-Aug-14

17-Aug-14
21-Aug-14
2-Oct-14
28-Aug-14
1-Sep-14
11-Oct-14
23-Jul-14
23-Jul-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
26-Aug-14

6-Sep-14
6-Sep-14
18-Oct-14
4-7/9/2014
4-7/9/2014
18-Oct-14
24-Jul-14
24-Jul-14
28-Aug-14
24-Jul-14
24-Jul-14
31-Aug-14
31-Aug-14

12-Jul-14
12-Jul-14
10-Aug-14
14-Aug-14
14-Aug-14
24-Nov-14

23-Jul-14
23-Jul-14
26-Aug-14
25-Aug-14
25-Aug-14
1-Dec-14

23-Jul-14
23-Jul-14
26-Aug-14
25-Aug-14
25-Aug-14
1-Dec-14

23-Jul-14
23-Jul-14
26-Aug-14
25-Aug-14
25-Aug-14
1-Dec-14

23-Jul-14
23-Jul-14
26-Aug-14
25-Aug-14
25-Aug-14
1-Dec-14

23-Jul-14
23-Jul-14
26-Aug-14
25-Aug-14
25-Aug-14
1-Dec-14

23-Jul-14
23-Jul-14
26-Aug-14
25-Aug-14
25-Aug-14
1-Dec-14

24-Jul-14
24-Jul-14
31-Aug-14
31-Aug-14
31-Aug-14
6-Dec-14

Page 16

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

VEHICLE UNDERPASS PROGRESS SCHEDULE (BARREL)


NO.

STATION

1
LHS
RHS
2
LHS
RHS

21+300
Block 1
Block 2
24+600
Block 1
Block 2

TYPE & DIMENSION LENGTH (m) SKEW ( )

2 cells - 4.0 x 3.0


2 cells - 4.0 x 3.0
2 cells - 4.0 x 3.0
2 cells - 4.0 x 3.0
2 cells - 4.0 x 3.0
2 cells - 4.0 x 3.0

37.700
15.780
21.900
44.051
21.620
22.411

0
0
0
0
0
0

F/P &
BLINDING

BASE SLAB
Rebars

Concrete

WALL
Rebars

Concrete

TOP SLAB
Rebars

Concrete

Bitu. Paint (2
Coats)

19-Oct-14 26-Oct-14 27-Oct-14 1-Nov-14 2-Nov-14 12-Nov-14 2-Nov-14 26-Nov-14


22-Oct-14 3-Nov-14 3-Nov-14 11-Nov-14 12-Nov-14 19-Nov-14 20-Nov-14
PREVIOUS
MONTH

PREVIOUS

THIS MONTH

PEDESTRIAN UNDERPASS PROGRESS SCHEDULE (BARREL)


NO.

STATION

23+284.40, SOL-1
1
LHS
Block 1
RHS
Block 2
24+360, SOL-1
2
LHS
Block 1
LHS
Block 2
RHS
Block 3
RHS
Block 4
0+050, SOL-3
3
LHS
Block 1
LHS
Block 2
LHS
Block 3
RHS
Block 4

TYPE & DIMENSION LENGTH (m) SKEW ( )

1 cells - 4.0 x 4.0


1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0

RENARDET S.A. & PARTNERS

59.614
9.000
20.777
22.777
7.000
83.223
17.721
17.721
17.721
30.000

0
0
0
0
0
0
0
0
0
0
0
0
0

F/P &
BLINDING

BASE SLAB
Rebars

Concrete

WALL
Rebars

Concrete

TOP SLAB
Rebars

Concrete

15-Sep-14 1-Oct-14 1-Oct-14 19-Oct-14 19-Oct-14 30-Oct-14 31-Oct-14


9-Dec-14 15-Dec-14 15-Dec-14 21-Dec-14 21-Dec-14 30-Dec-14 30-Dec-14
25-Nov-14 2-Dec-14 2-Dec-14 14-Dec-14 14-Dec-14 25-Dec-14 25-Dec-14

Page 17

Bitu. Paint (2
Coats)

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

11. Progress Status of Utility Crossing Ducts


DRAWING
S.NO.

PIPE

SETOUT/EX
CV/BED INSTALLAT CONCRET BACKFILLI

NO. OF

CHAINAGE
NO.

DIA TYPE

WAYS STAGE

CCC/FQI/IR/06
SERVICE ROAD-3

0+030

200 UPVC

CCC/FQR/IR/11 SOL-2

0+150

300 UPVC

CCC/FQR/IR/10 SOL-3

0+300

200 UPVC

CCC/FQR/WA/05 SR1

0+600

300 UPVC

4A

CCC/FQI/SL/01

21+160

150 UPVC

CCC/FQI/EL/01

21+360

150 UPVC

CCC/FQI/IR/01

21+460

300 UPVC

CCC/FQI/EL/02

21+660

150 UPVC

CCC/FQI/IR/02

21+780

300 UPVC

CCC/FQI/EL/03

21+880

150 UPVC

10

CCC/FQI/EL/04

22+260

150 UPVC

11

CCC/FQI/EL/05

22+510

150 UPVC

12

CCC/FQI/IR/03

22+520

200 UPVC

13

CCC/FQI/IR/04
22+520 LHS 200 UPVC
JUNCTION CROSSING

14

CCC/FQI/IR/05
22+587 LHS 200 UPVC
JUNCTION CROSSING

15

CCC/FQI/EL/06

150 UPVC

16

CCC/FQI/WA/02
JUNCTION

23+008 LHS 300 UPVC

17

CCC/FQI/WA/01

23+020

900

18

CCC/FQI/EL/07

23+060

150 UPVC

19

CCC/FQI/EL/13

23+210

150 UPVC

20

CCC/FQI/EL/08

23+240

150 UPVC

21

CCC/FQI/EL/09

23+560

150 UPVC

22

CCC/FQI/EL/10

23+820

150 UPVC

23

CCC/FQI/WA/03

23+900

600

RC

23A

CCC/FQI/SL/11

23+960

UPVC

24

CCC/FQI/EL/11

23+980

150 UPVC

22+760

RC

RENARDET S.A. & PARTNERS

LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT

24-Sep-14

ION

24-Sep-14

18-Oct-14

NG

RFI REF.
LAYING

CONCRETE

BACKFILL

UTL-LAY- 104 UTL-CON-131A

15-May-14 15-May-14 18-May-14 12-Jun-14 UTL-LAY- 81 UTL-CON- 65


11-Jun-14 11-Jun-14 12-Jun-14 10-Jul-14 UTL-LAY- 104 UTL-CON- 83

UTL-BF- 01
UTL-BF- 20

19-May-14 19-May-14 20-May-14 4-Jun-14 UTL-LAY- 87 UTL-CON- 66


14-Jun-14 14/06/014 14-Jun-14 21-Jun-14 UTL-LAY- 108 UTL-CON- 84

UTL-BF- 03
UTL-BF- 21

19-May-14 19-May-14 20-May-14 31-May-14 UTL-LAY- 85 UTL-CON- 63


15-Jun-14 15-Jun-14 15-Jun-14
UTL-LAY- 107 UTL-CON- 85

UTL-BF- 02

20-May-14 20-May-14 25-May-14


15-Jun-14 15-Jun-14 15-Jun-14

4-Jun-14 UTL-LAY- 86 UTL-CON- 64


8-Jul-14 UTL-LAY- 109 UTL-CON- 87

UTL-BF- 05
UTL-BF- 23

25-May-14 25-May-14 25-May-14 4-Jun-14 UTL-LAY- 90 UTL-CON-68


16-Jun-14 16-Jun-14 17-Jun-14 10-Jul-14 UTL-LAY- 111 UTL-CON- 88

UTL-BF- 07
UTL-BF- 28

17-Jun-14
20-Jul-14

17-Jun-14
20-Jul-14

18-Jun-14
21-Jul-14

9-Jul-14 UTL-LAY- 112 UTL-CON- 89 UTL-BF- 33


27-Jul-14 UTL-LAY- 131 UTL-CON- 106 UTL-BF-44

19-Jun-14
20-Jul-14

19-Jun-14
20-Jul-14

19-Jun-14
21-Jul-14

6-Jul-14 UTL-LAY- 114 UTL-CON- 92 UTL-BF- 31


17-Jul-14 UTL-LAY- 132 UTL-CON- 107 UTL-BF-46

19-Jun-14
20-Jul-14

19-Jun-14
20-Jul-14

19-Jun-14
21-Jul-14

5-Jul-14 UTL-LAY- 113 UTL-CON- 91 UTL-BF- 30


17-Jul-14 UTL-LAY- 133 UTL-CON- 108 UTL-BF-45

26-May-14 26-May-14 26-May-14 8-Jun-14 UTL-LAY- 88 UTL-CON- 69


11-Jun-14 11-Jun-14 11-Jun-14 22-Jul-14 UTL-LAY-106 UTL-CON- 81

UTL-BF- 08
UTL-BF-26

16-Jun-14
8-Jul-14

20-Jul-14 UTL-LAY- 102 UTL-CON27-Jul-14 UTL-LAY- 125 UTL-CON-99

UTL-BF-19
UTL-BF-42

25-May-14 25-May-14 26-May-14 14-Jun-14 UTL-LAY- 91 UTL-CON- 71


11/06/201 11-Jun-14 11-Jun-14 23-Jun-14 UTL-LAY- 105 UTL-CON- 82

UTL-BF- 06
UTL-BF- 25

27-May-14 27-May-14 27-May-14 17-Jun-14 UTL-LAY- 92 UTL-CON- 72

UTL-BF- 09

28-May-14 28-May-14 28-May-14 17-Jun-14 UTL-LAY- 93 UTL-CON- 70

UTL-BF- 10

16-Jun-14
8-Jul-14

16-Jun-14
9-Jul-14

29-May-14 29-May-14 29-May-14 17-Jun-14 UTL-LAY- 94 UTL-CON- 73 UTL-BF- 11


30-Jul-14 12-Aug-14 30-Jul-14 26-Aug-14 UTL-LAY-142 UTL-CON- 115 UTL-BF-48
29-May-14
14-Jul-14

2-Jun-14
14-Jul-14

2-Jun-14
14-Jul-14

17-Jun-14 UTL-LAY- 95 UTL-CON- 75 UTL-BF- 15


20-Aug-14 UTL-LAY- 124 UTL-CON- 102 UTL-BF- 36

29-May-14
14-Jul-14

2-Jun-14
14-Jul-14

2-Jun-14
15-Jul-14

17-Jun-14 UTL-LAY-97 UTL-CON- 76 UTL-BF- 13


20-Aug-14 UTL-LAY- 127 UTL-CON- 101 UTL-BF- 38

10-Aug-14
27-Oct-14
29-May-14
6-Aug-14

11-Aug-14
27-Oct-14
2-Jun-14
6-Aug-14

11-Aug-14 26-Aug-14 UTL-LAY-149AUTL-CON- 120A UTL-BF- 58


27-Oct-14
UTL-LAY- 206 UTL-CON- 153
3-Jun-14 19-Jun-14 UTL-LAY- 98 UTL-CON- 77 UTL-BF- 14
9-Aug-14 13-Aug-14 UTL-LAY- 134-R1
UTL-CON- 109A UTL-BF- 53

Page 18

Project: Upgrading of Falaj Al Qabail Roundabout


DRAWING
S.NO.

PIPE

Monthly Progress Report December 2014


SETOUT/EX
CV/BED INSTALLAT CONCRET BACKFILLI

NO. OF

CHAINAGE
DIA TYPE WAYS STAGE
24+000

600

26

CCC/FQI/IR/07

24+020

300 UPVC

27

CCC/FQI/EL/12

24+120

150 UPVC

28

CCC/FQI/EL/14

24+220

150 UPVC

29

CCC/FQI/IR/08

24+340

300 UPVC

30

CCC/FQI/EL/15

24+520

150 UPVC

31

CCC/FQI/EL/16

24+820

150 UPVC

32

CCC/FQI/IR/09

24+960

300 UPVC

33

CCC/FQI/EL/17

25+160

150 UPVC

34

CCC/FQI/NAW.2

21+870

100 UPVC

35

CCC/FQI/NAW.3

23+580

100 UPVC

36

CCC/FQI/NAW.4

24+720

100 UPVC

37

CCC/FQI/OMANTEL.1

22+810

100 UPVC

38

CCC/FQI/OMANTEL.2 0+140 SOL-3 100 UPVC

39

CCC/FQI/SL/03 Rev A

22+820

150 UPVC

40

CCC/FQI/SL/04

22+990

150 UPVC

41

CCC/FQI/SL/02

22+080

150 UPVC

42

CCC/FQI/EL/19

23+740

150 UPVC

42

CCC/FQI/SL/01

24+850

150 UPVC

43

CCC/FQI/SD/07

21+500

450

44

CCC/FQI/SD/08

21+560

450

CONC PIPE

45

CCC/FQI/SD/09

21+620

450

CONC PIPE

MIDDLE

MIDDLE

47

CCC/FQI/SD

CCC/FQI/EL/21

23+400

23+965

600

CONC PIPE

CCC/FQI/WA/04

46

RC

LEFT
MIDDLE
RIGHT
LEFT
2
MIDDLE
RIGHT
LEFT
3
MIDDLE
RIGHT
LEFT
3
MIDDLE
RIGHT
LEFT
2
MIDDLE
RIGHT
LEFT
3
MIDDLE
RIGHT
LEFT
3
MIDDLE
RIGHT
LEFT
2
MIDDLE
RIGHT
LEFT
3
MIDDLE
RIGHT
LEFT
2
MIDDLE
RIGHT
LEFT
2
MIDDLE
RIGHT
LEFT
2
MIDDLE
RIGHT
LEFT
4
MIDDLE
RIGHT
LEFT
4
MIDDLE
RIGHT
LEFT
4
MIDDLE
RIGHT
LEFT
4
MIDDLE
RIGHT
LEFT
4
MIDDLE
RIGHT
LEFT
2
MIDDLE
RIGHT
LEFT
2-4WAY MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT

25

CONC PIPE

NO.

ION

200 UPVC

RENARDET S.A. & PARTNERS

NG

RFI REF.
LAYING

CONCRETE

BACKFILL

LEFT

3-Jun-14
11-Aug-14

4-Jun-14
4-Jun-14 23-Jun-14 UTL-LAY- 99 UTL-CON- 78 UTL-BF- 16
11-Aug-14 19-Aug-14 26-Aug-14 UTL-LAY-140 R1
UTL-CON-114 UTL-BF- 52

4-Jun-14
23-Jul-14

5-Jun-14
24-Jul-14

10-Jun-14 23/06/201 UTL-LAY- 100 UTL-CON- 79 UTL-BF- 17


19-Aug-14 26-Aug-14 UTL-LAY-139 UTL-CON-112-R1UTL-BF- 47

9-Jun-14
6-Aug-14

9-Jun-14
6-Aug-14

10-Jun-14 23-Jun-14 UTL-LAY- 101 UTL-CON- 80 UTL-BF- 18


6-Aug-14 26-Aug-14 UTL-LAY-138-R1
UTL-CON-111-B UTL-BF- 56

5-Jul-14
4-Des-14
16-Jul-14
27-Oct-14

5-Jul-14
5-Jul-14 19-Aug-14 UTL-LAY- 123 UTL-CON- 94 UTL-BF- 39R1
14-Dec-14 14-Dec-14
UTL-LAY- 222 UTL-CON- 97 R1..
.
16-Jul-14 17-Jul-14 6-Nov-14 UTL-LAY- 130 UTL-CON- 105 UTL-BF- 41R1
27-Oct-14 27-Oct-14 27-Oct-14 UTL-LAY-190R1UTL-CON- 148 UTL-BF- 72

14-Sep-14
27-Oct-14

14-Sep-14
30-Oct-14

14-Oct-14 20-Oct-14 UTL-LAY- 166 UTL-CON-125 UTL-BF-81


27-Oct-14 10-Dec-14 UTL-LAY- 205 UTL-CON- 150 UTL-BF-99

16-Sep-14
27-Oct-14

20-Sep-14
27-Oct-14

27-Oct-14

3-Nov-14

10-Nov-14 11-Nov-14 7-Dec-14 UTL-LAY- 211 UTL-CON- 155 UTL-BF-106

UTL-LAY- 173
9-Nov-14 UTL-LAY- 203 UTL-CON- 149 UTL-BF-100

21-May-14 21-May-14 21-May-14 4-Jun-14 UTL-LAY- 89 UTL-CON- 67


16-Jun-14 16-Jun-14 18-Jun-14 10-Jul-14 UTL-LAY- 110 UTL-CON- 90

UTL-BF- 04
UTL-BF- 29

29-May-14 31-May-14 31-May-14 17-Jun-14 UTL-LAY- 96 UTL-CON- 74


10-Jul-14
10-Jul-14 13-Aug-14 26-Aug-14 UTL-LAY- 120 R1
UTL-CON- 95

UTL-BF- 12
UTL-BF- 49

21-Jul-14
8-Aug-14
16-Sep-14
7-Jul-14
12-Aug-14

4-Aug-14 5-Aug-14
9-Aug-14 9-Aug-14 22-Sep-14
16-Sep-14 16-Sep-14
8-Jul-14
8-Jul-14
13-Aug-14 14-Aug-14 15-Aug-14

9-Jul-14
12-Aug-14
12-Oct-14
2-Jul-14
10-Jul-14
22-Jul-14
30-Aug-14
27-Nov-14

9-Jul-14
9-Jul-14
UTL-LAY- 116 UTL-CON-100
13-Aug-14 14-Aug-14 25-Sep-14 UTL-LAY-151 UTL-CON-121 UTL-BF-81
13-Oct-14 12-Oct-14 8-Nov-14 UTL-LAY-187 UTL-CON-137 UTL-BF-99
3-Jul-14
3-Jul-14
UTL-LAY-122 UTL-CON-93R1
10-Jul-14 14-Jul-14
UTL-LAY-126 UTL-CON-103
22-Jul-14 23-Jul-14 20-Aug-14 UTL-LAY-136 UTL-CON-110 UTL-BF- 50
31-Aug-14 14-Sep-14 30-Sep-14 UTL-LAY-158 UTL-CON-96 UTL-BF-64
14-Dec-14 23-Dec-14 UTL-EXC-63 UTL-CON-162 UTL-BF-115
24-Nov-14
SL-CON-54
9/7/2014 14-Oct-14 27-Oct-14 UTL-LAY-162 UTL-CON-124 UTL-BF-69
27-Oct-14
4-Nov-14 UTL-LAY-162R1
UTL-BF-94
28-Oct-14 17-Nov-14 17-Nov-14 UTL-LAY-207 UTL-CON-152 UTL-BF-92
17-Sep-14 30-Sep-14 8-Nov-14 UTL-LAY-174 UTL-CON-127 UTL-BF-83R1
18-Oct-14 14-Oct-14
UTL-LAY-188 UTL-CON-138
27-Oct-14 27-Oct-14
UTL-LAY-204 UTL-CON-151
2-Oct-14
2-Oct-14
UTL-LAY-184 UTL-CON-135

9/7/2014
14-Sep-14
9/16/2014
16-Sep-14
14-Oct-14
27-Oct-14
2-Oct-14

UTL-LAY-137-R1
UTL-CON- 118
UTL-LAY-148AUTL-CON- 117 UTL-BF- 57
UTL-LAY-172 UTL-CON- 126
UTL-LAY-103AUTL-CON-98
UTL-LAY-150 UTL-CON-122A UTL-BF- 37A

2-Oct-14

2-Oct-14

2-Oct-14

UTL-LAY-164 R1
UTL-CON-134

2-Oct-14

2-Oct-14

2-Oct-14

UTL-LAY-185 UTL-CON-136

4-Nov-14

4-Nov-14

UTL-EXC-55

RIGHT
LEFT

RIGHT
2

LEFT
MIDDLE
RIGHT

UTL-CON-156 not done

Page 19

Project: Upgrading of Falaj Al Qabail Roundabout


DRAWING
S.NO.

PIPE

ION

DIA TYPE WAYS STAGE

CCC/FQI/Omantel/02 0+138.348 110 UPVC

CCC/FQI/SL/13

0+130

150 UPVC

CCC/FQI/Omantel/02

0+140

150 UPVC

CCC/FQI/SL/14

0+415

150 UPVC

SETOUT/EX
CV/BED INSTALLAT CONCRET BACKFILLI

NO. OF

CHAINAGE
NO.

2A

Monthly Progress Report December 2014

LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT

9/4/2014

LEFT 16-Sep-14
4

CCC/FQI/SL/15

0+054.459

150 UPVC

E
9/28/2014

NG

RFI REF.
LAYING

CONCRETE

UTL-LAY-159-BUTL-CON-132

17-Sep-14 30-Sep-14 18-Oct-14 UTL-LAY-167 UTL-CON-128

MIDDLE
RIGHT

CCC/FQI/SL/16

SOL-3 Ch.
0+300

150 UPVC

CCC/FQI/SL/17

SOL-3 Ch.
150 UPVC
0+427.623

RENARDET S.A. & PARTNERS

BACKFILL

LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT

Page 20

UTL-BF-78

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

12. Project Progress Strip Chart

RENARDET S.A. & PARTNERS

Page 21

Project: Upgrading of Falaj Al Qabail Roundabout


SUBGRADE IN CUT

Monthly Progress Report December 2014

21+150-21+500

COMPLETED

As of DEC 2014

LHS

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Subgra de
La yr 9
La yr 8
La yr 7
La yr 6
La yr 5
La yr 4
La yr 3
La yr 2

3 cell & U.pass

21+440

21+460

21+480

21+500

21+960

21+980

22+000

21+400
21+900

21+940

21+380
21+880

21+420

21+360
21+860

21+920

21+340
21+840

21+320

21+300

21+280

21+260

21+240

21+220

21+200

21+180

21+160

21+140

21+120

21+100

21+080

21+060

21+040

21+020

21+000

EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

RHS

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
l a yer 2
l a yer 3
l a yer 4
l a yer 5
l a yer 6
l a yer 7
l a yer 8
l a yer 9
Subgra de

3 cell & U.pass

GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

21+500-22+000

LHS

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
s ub gra de
La yer 9
La yer 8
La yer 7
La yer 6
La yer 5
La yer 4
La yer 3
La yer 2

21+820

21+800

21+780

21+760

21+740

21+720

21+700

21+680

21+660

21+640

21+620

21+600

21+580

21+560

21+540

21+520

21+500

EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

RHS

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
l a yer 2
l a yer 3
l a yer 4
l a yer 5
l a yer 6
l a yer 7
l a yer 8
l a yer 9
s ub gra de

top of embankment

3rd rock soil

GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

RENARDET S.A. & PARTNERS

Page 22

Project: Upgrading of Falaj Al Qabail Roundabout

22+000-22+500

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layr 10
Layr 9
Layr 8
Layr 7
Layr 6
Layr 5
Layr 4
Layr 3
Layr 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

As of DEC 2014

GSB
SUB GRADE LAYER

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
3rd rock soil
layer 4
layer 5
layer 6
layer 7
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

22+500

22+480

22+460

22+440

22+420

22+400

22+380

22+360

22+340

22+320

22+300

22+280

22+260

22+240

22+220

22+200

22+180

22+160

22+140

22+120

22+100

22+080

22+060

22+040

Subgrdae
embank 2
embank
3rd rock soil

22+020

22+000

LHS

COMPLETED

RHS

Monthly Progress Report December 2014

1st rock soil


2nd rock soil
3rd rock soil
4th rock soil
5th rock soil
6th rock soil
embankmen 1
embankment 2
SUBGRADE
GSB
abc 1st

RHS

10 th rock soil
7th layer roock soil

7th layer of rock


layer 15

4th rock soil


2nd rock soil

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
layer 6
layer 7
layer 8
layer 9
layer 10
SUB G
GSB 20 cm
GSB
ABC 1 ST 15 cm
ABC 1st
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

23+000

22+980

22+960

22+940

22+920

22+900

22+880

22+860

22+840

22+820

22+800

22+780

22+760

22+740

22+720

22+700

22+680

22+660

22+640

22+620

22+600

22+580

22+560

22+540

9 cell

22+520

22+500

LHS

22+500-23+000
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layer 10
Layer 9
Layer 8
Layer 7
Layer 6
Layer 5
Layer 4
Layer 3
Layer 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

2nd rock soil

RENARDET S.A. & PARTNERS

9 cell

4th rock soil


7th layer roock soil
10 rock soil
emabnkment layers

Page 23

layer 15
7th layer of rock

Project: Upgrading of Falaj Al Qabail Roundabout

23+500

23+480

23+460

23+440

23+420

23+400

23+380

sub grade

4th rock soil

24+000

23+980

23+960

23+940

23+920

23+900

23+880

23+860

23+840

23+820

2nd rock soil

23+800

23+780

23+760

23+740

23+720

23+700

23+680

23+660

23+640

23+620

23+600

23+580

23+560

23+540

23+500

Bridge

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
Bridge
5th layer rock soil
layer 6
layer 7
layer 8
Rock siol 11th layer
layer 9
layer 10
Rock soil 15 th layer
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

RENARDET S.A. & PARTNERS

23+360

23+340

23+320

23+300

23+280

23+260

23+240

23+220

23+200

23+180

23+160

23+140

23+120

23+100

23+080

23+060

23+040

23+020

Bridge

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
Embankment layer no 28
layer 5
3th layer of rock soil
layer 6
layer 15 of embankment
layer 7
7th layer of rock soil
layer 8
layer 9
10th layer of rock soil
layer 10
top embankment
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
23+500-24+000
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layer 10
Rock soil 15 th layer
Layer 9
Layer 8
Rock siol 11th layer
Layer 7
Layer 6
Layer 5
5th rock soil
Bridge
Layer 4
Layer 3
Layer 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

23+520

RHS
LHS
RHS

As of DEC 2014

23+000-23+500

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layr 10
Layr 9
Layr 8
Layr 7
7th layer of rock soil
Layr 6
layer 15 of embankment
Layr 5
3th layer of rock soil
Layr 4
Embankment layer no 28
Layr 3
Layr 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

23+000

LHS

COMPLETED

Monthly Progress Report December 2014

2nd rock soil


4th rock soil

top embankment

Page 24

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

top sub grade

2nd rock soil

24+260

24+280

24+300

24+320

24+340

24+360

24+380

24+400

24+420

24+440

24+460

24+480

24+500

24+760

24+780

24+800

24+820

24+840

24+860

24+880

24+900

24+920

24+940

24+960

24+980

25+000

24+220

24+200

24+180

24+160

24+140

24+120

24+100

24+060

24+040

24+240

l a yer 2
l a yer 3
l a yer 4
l a yer 5
l a yer 6
l a yer 7
l a yer 8
l a yer 9
l a yer 10

24+740

RHS

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1

24+020

1st rock

24+000

EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

24+080

LHS

La yer 10
La yer 9
La yer 8
La yer 7
La yer 6
La yer 5
La yer 4
La yer 3
La yer 2

As of DEC 2014

24+000-24+500

COMPLETED
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm

2nd rock soil

top embankment

GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
24+500-25+000

LHS

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
La yer 10
La yer 9
La yer 8
La yer 7
La yer 6
La yer 5
La yer 4
La yer 3
La yer 2

RHS

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1

24+720

24+700

24+680

24+660

24+640

24+620

24+600

24+580

24+560

24+540

24+520

24+500

EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

Subgrade in cut

l a yer 2
l a yer 3
l a yer 4
l a yer 5
l a yer 6
l a yer 7
l a yer 8
l a yer 9
l a yer 10

GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

RENARDET S.A. & PARTNERS

GSB

Page 25

Project: Upgrading of Falaj Al Qabail Roundabout

COMPLETED

Monthly Progress Report December 2014

As of DEC 2014

25+000-25+500

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm

LHS

Layr 10
Layr 9
Layr 8
Layr 7
Layr 6
Layr 5
Layr 4
Layr 3
Layr 2

OGL SURVEY
BED PREPRATION

sub grade in cut

EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5

RHS

layer 6
layer 7
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

RENARDET S.A. & PARTNERS

Page 26

25+460

25+440

25+420

25+400

25+380

25+360

25+340

25+320

25+300

25+280

25+200

25+180

25+160

25+140

25+120

25+100

25+080

25+060

25+040

25+020

25+000

OGL SURVEY

25+260

BED PREPRATION

25+223
End of the project
25+240

EMBANKMENT Layer 1

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

13. Financial Status of Payments


Sl. No.

DESCRIPTION

PAYMENT FOR
THE MONTH OF

GROSS
AMOUNT
(R.O.)

GROSS
NET AMOUNT
AMOUNT
CLAIMED
CLAIMED (R.O.)
(R.O.)

DATE
SUBMITTED

AMOUNT
DATE CERTIFIED
CERTIFIED (R.O.)

AMOUNT
RECEIVED
(R.O.)

DATE
PAYMENT DUE

DATE
PAYMENT
RECEIVED

PAYMENT APPLICATION No. 1


(ADVANCE PAYMENT)

Dec-13

1,648,225

1,648,225

1,648,225

23-Nov-13

1,648,225

29-Jan-14

1,648,225

6-Feb-14

PAYMENT APPLICATION No. 2

Jan-14

2,291,277

643,052

514,442

12-Feb-14

514,442

02-Apr-14

513,608

10-Apr-14

PAYMENT APPLICATION No. 3

Feb&Mar-14

2,808,644

517,367

504,147

06-Apr-14

434,917

03-May-14

414,674

6-Aug-14

PAYMENT APPLICATION No. 4

Apr-14

3,315,692

507,048

417,900

08-May-14

407,538

05-Jun-14

395,257

6-Aug-14

PAYMENT APPLICATION No. 5

May-14

4,109,460

793,768

650,802

05-Jun-14

445,708

04-Jul-14

374,172

6-Aug-14

PAYMENT APPLICATION No. 6

Jun-14

4,293,764

184,304

382,116

15-Jul-14

382,116

16-Jul-14

418,721

9-Sep-14

PAYMENT APPLICATION No. 7

Jul&Aug-14

5,749,546

1,455,782

1,164,626

14-Sep-14

1,123,023

18-Sep-14

1,123,023

19-Oct-14

PAYMENT APPLICATION No. 8

Sep-14

6,857,752

1,108,206

928,167

21-Oct-14

928,805

06-Nov-14

PAYMENT APPLICATION No. 9

Oct&Nov-14

8,550,924

1,693,172

1,398,920

17-Dec-14

10

PAYMENT APPLICATION No. 10

Dec-14

11

PAYMENT APPLICATION No. 11

Jan-15

12

PAYMENT APPLICATION No. 12

Feb-15

13

PAYMENT APPLICATION No. 13

Mar-15

14

PAYMENT APPLICATION No. 14

Apr-15

15

PAYMENT APPLICATION No. 15

May-15

16

PAYMENT APPLICATION No. 16

Jun-15

17

PAYMENT APPLICATION No. 17

Jul-15

18

PAYMENT APPLICATION No. 18

Aug-15

19

PAYMENT APPLICATION No. 19

Sep-15

20

PAYMENT APPLICATION No. 20

Oct-15
8,550,924

8,550,924

7,609,345

TOTAL AMOUNT (R.O.)

RENARDET S.A. & PARTNERS

29-Feb-00

5,884,774

Page 27

3-Jan-15

4,887,679

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

14. Details of Equipment Available At Site


Sl.
No.
1

DESCRIPTION

CCC

HIRED

TOTAL
AVAILABLE
AT SITE

COMPRESSOR

AIR COMPRESSOR

MILLER WELDING MECHINE

GENERATOR

CRANES

CRANES 30 TON / 25 TON / 70 TON


VEHICLES H.D.

2
1

3
-

5
-

DIESEL TANKER

FLAT TRAILER

10

HIAB TRUCK

11

P/MOVER + TIPPING TRAILER

12

TIPPER TRUCKS

11

15

13

WATER TANKER 5000 & 10000 GAL

14

EARTH MOVING PLANT

15

BOBCAT

16

EXCAVATOR

17

JCB 4CX / 3CX

18

SHOVEL / WHEEL LOADER

19

DOZER D9N/D8R

20

TELEHANDLER

21

CIVIL ENGINEERING EQUIPMENT

22

GREENE STABILIZER PLANT

23

DY NAPAC TY RE ROLLER

24

E/WORK ROLLER

25

MOTOR GRADER

26

TITAN PAVER MACHINE

27

TY RE / PTR ROLLER

28

PAVER MACHINE

29

L. D. VEHICLES & TRUCKS

30

DY NA TRUCK

31

MAINTENANCE TRUCKS

32

ASHOK LEY LAND BUS 55 SEAT

33

TOY OTA COASTER BUS 24 S

34

TOY OTA COROLLA/CIVIC/Y ARIS

35

TOY OTA PICKUP/ISUZU

36
37
38

12

12

13

NISSAN PATHFINDER/X-TRAIL

TOY OTA LAND CRUISER/FORTUNER

77

126

Total

RENARDET S.A. & PARTNERS

49

Page 28

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

2014
PLANNED TOTAL PER MONTH
REVISED PLANNED TOTAL PER MONTH
PLANNED CUMULATIVE
ACTUAL TOTAL PER MONTH
ACTUAL CUMULATIVE

2015

Jan-14

Feb-14

Mar-14

Apr-14

May-14

Jun-14

Jul-14

47

68

87

95

93

47
33
33

115
55
88

202
66
154

297
68
222

390
77
299

107
68
458
86
385

110
87
545
88
473

Aug-14 Sep-14

108
95
640
100
573

102
93
733
109
682

Oct-14

Nov-14

Dec-14

Jan-15 Feb-15 Mar-15

Apr-15

May-15 Jun-15

100
107
840
112
794

98
110
950
120
914

87
108
1,058
126
1,040

82
102
1,160

66
87
1,445

53
82
1,527

79
100
1,260

77
98
1,358

41
79
1,606

Jul-15

Aug-15

Sep-15

Oct-15

Total

1500
77
1,683

66
1,749

53
1,802

41
1,843
1040

112

102

98

100

108

68

100

98

93

87

88

REVISED PLANNED TOTAL PER MONTH

108

87
82

77

79

82

87

77

86

ACTUAL TOTAL PER MONTH

110

107

PLANNED TOTAL PER MONTH

77
66

53

53

41

47

60

79

66

68

55

66

68

80

41

33

40

20

PROJECT MONTHS

RENARDET S.A. & PARTNERS

Page 29

Oct-15

Sep-15

Aug-15

Jul-15

Jun-15

May-15

Apr-15

Mar-15

Feb-15

Jan-15

Dec-14

Nov-14

Oct-14

Sep-14

Aug-14

Jul-14

Jun-14

May-14

Apr-14

Mar-14

Feb-14

Jan-14

No. of EQUIPMENT

100
95

87

100

93

95

107

110

120

102
109

120

126

140

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

15. Details of Manpower Available At Site

EXPATRIATES

NATIONALS

TOTAL

STAFF & LABOUR


BUDGET

ACTUAL

BUDGET

ACTUAL

BUDGET

ACTUAL

A - MANAGEMENT ***

B - COMMERCIAL STAFF *

C - ENGINEERS

D - FOREMAN & C/H

22

24

E - ENGINEERING TECHNICIANS **

22

27

1 - SKILLED CRAFTSMEN

142

64

206

2 - SEMI-SKILLED/UNSKILLED

495

55

550

F - DAILY RATED EMPLOYEES :

TOTAL AS OF END OF THE MONTH

G - SUBCONTRACTORS
Number of Personnel employed by Subcontractor:

RENARDET S.A. & PARTNERS

698

127

825

46

Page 30

Project: Upgrading of Falaj Al Qabail Roundabout

2013

2014

Dec-13
6

Jan-14
34

Feb-14
186

Mar-14
375

Apr-14
586

May-14
791

23

36

50

52

57

Oct-14
701

Nov-14
480

Dec-14
381

Jan-15
269

Feb-15
246

Mar-15
307

Apr-15
307

May-15
305

Jun-15
149

Jul-15

Aug-15

Sep-15

Oct-15

Total
8301

565

756

754

750

700

652

667

554

516

387

297

276

365

271

135

92

51

7788

59

59

60

61

63

61

61

57

51

47

44

35

30

63

84

84

83

78

72

74

61

57

43

33

31

40

30

15

10

858

854

854

764

541

442

326

297

354

351

340

179

638

848

851
627

840

838

833

778

725

741

616

573

429

330

306

406

11

68

291

715

1,353

2,202

3,052

3,910

4,764

5,618

6,383

6,923

7,365

7,691

7,988

8,342

8,693

9,033

9,212

322

365

550

581

603

691

709

756

734

773

767

765

756
0

18

26

46

49

54

57

64

69

68

70

71

71

69

340

391

596

630

657

748

773

825

802

843

838

836

825

340

731

1,327

1,957

2,614

3,362

4,135

4,960

5,762

6,605

7,443

8,279

9,104

301

150

102

57

8372
732
9104

541

340

351

297

326

354

442

425

391
340

400

179

222

300

200

PROJECT MONTHS

RENARDET S.A. & PARTNERS

Page 31

Oct-15

Sep-15

Aug-15

Jul-15

Jun-15 0

May-15

Apr-15 0

Mar-15 0

Feb-15 0

Dec-14

Nov-14

Oct-14

Sep-14

Aug-14

Jul-14

Jun-14

May-14

Feb-14

Jan-14

Dec-13

Jan-15 0

11

57

100

8651
9,212

764

500

862
9215

825

836

838

854
843

854

858
825

851

914

REVISED - PLANNED - ( DIRECT + INDIRECT )

ACTUAL TOTAL PER MONTH - ( DIRECT + INDIRECT )

773

848

638
657
Apr-14

748
630
Mar-14

596

Sep-14
793

425

800

No. of Men

Aug-14
794

222

PLANNED TOTAL PER MONTH - ( DIRECT + INDIRECT )

600

Jul-14
799

57

900

700

2015

Jun-14
792

11

802

PLANNED TOTAL PER MONTH - ( DIRECT )


REVISED - PLANNED TOTAL PER MONTH - ( DIRECT )
PLANNED TOTAL PER MONTH - ( INDIRECT )
REVISED - PLANNED TOTAL PER MONTH-(INDIRECT)
PLANNED TOTAL PER MONTH - ( DIRECT + INDIRECT )
REVISED - PLANNED - ( DIRECT + INDIRECT )
PLANNED CUMULATIVE
ACTUAL TOTAL PER MONTH - ( DIRECT )
ACTUAL TOTAL PER MONTH - ( INDIRECT )
ACTUAL TOTAL PER MONTH - ( DIRECT + INDIRECT )
ACTUAL CUMULATIVE

Monthly Progress Report December 2014

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

16. QA/QC Reports

RENARDET S.A. & PARTNERS

Page 32

Project: Upgrading of Falaj Al Qabail Roundabout

RENARDET S.A. & PARTNERS

Monthly Progress Report December 2014

Page 33

Project: Upgrading of Falaj Al Qabail Roundabout

RENARDET S.A. & PARTNERS

Monthly Progress Report December 2014

Page 34

Project: Upgrading of Falaj Al Qabail Roundabout

RENARDET S.A. & PARTNERS

Monthly Progress Report December 2014

Page 35

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

17. Status of Material Approvals


Reference No.

MAR No.

Material/ Work

Manufacturer/Supplier/
Subcontractor

MOTC
Renardet
Date
Submitte Remarks
Via Renardet
Comments
Letter
d To
Submitted
By MOTC
Letter Ref. No.
dated
Dated

CCC/FQI/REN/MAS/001

MAS/CCC/FQI/BBC/001

Bituminous Base Course

Tarmac Zawawi LLC Oman

22/12/2013

Renardet

APPROVED

01/04/2014

SO/FQI/CCC/087

07/04/2014

CCC/FQI/REN/MAS/002

MAS/CCC/FQI/GTI/002

Geotechnical Investigation

Swissboring & Company LLC

26/12/2013

Renardet

APPROVED

02/02/2014

SO/FQI/CCC/015

12/02/2014

CCC/FQI/REN/MAS/003

MAS/CCC/FQI/MSE/003

MSE Wall System

Freyssinet Arabian Sea LLC

26/12/2013

Renardet

APPROVED

02/02/2014

SO/FQI/CCC/014

12/02/2014

CCC/FQI/REN/MAS/004

MAS/CCC/FQI/PVC/004

UPVC Pipes

Amiantit Oman

26/12/2013

Renardet

APPROVED

09/02/2014

SO/FQI/CCC/019

18/02/2014

CCC/FQI/REN/MAS/005

MAS/CCC/FQI/HDPE/005

HDPE Pipes & Fittings

Amiantit Oman

26/12/2013

Renardet

APPROVED

09/02/2014

SO/FQI/CCC/020

18/02/2014

CCC/FQI/REN/MAS/006

MAS/CCC/FQI/PW/006

Piling Works

APCC LLC

26/01/2014

Renardet

APPROVED

19/02/2014

SO/FQI/CCC/026

25/02/2014

CCC/FQI/REN/MAS/007

MAS/CCC/FQI/MC/007

Bitnuminous Prime Coat (MC-70)

Emirates Lube Oil Co. (Muscat)

30/01/2014

Renardet

APPROVED

09/03/2014

SO/FQI/CCC/069

27/03/2014

CCC/FQI/REN/MAS/008

MAS/CCC/FQI/RS/008

Reinforcing Steel

Muscat Steel Industries

02/02/2014

Renardet

APPROVED

20/03/2014

SO/FQI/CCC/063

24/03/2014

CCC/FQI/REN/MAS/009-1

MAS/CCC/FQI/PT/009-1

Post Tensioning Work - Anchorage

Freyssinet Arabian Sea LLC

22/02/2014

Renardet

APPROVED

27/03/2014

SO/FQI/CCC/089

14/04/2014

CCC/FQI/REN/MAS/009-2

MAS/CCC/FQI/PT/009-2

Post Tensioning Work - Duct

Freyssinet Arabian Sea LLC

22/02/2014

Renardet

APPROVED

27/03/2014

SO/FQI/CCC/090

14/04/2014

CCC/FQI/REN/MAS/009-3

MAS/CCC/FQI/PT/009-3

Post Tensioning Work - Strand

Freyssinet Arabian Sea LLC

22/02/2014

Renardet

APPROVED

27/03/2014

SO/FQI/CCC/091

14/04/2014

CCC/FQI/REN/MAS/010A-R1 MAS/CCC/FQI/PB/010A-R1 Bridge Pot Bearings

Al Ammar International

07/05/2014

Renardet

Not Approved

---

REN/FQI/CCC/111

13/05/2014

CCC/FQI/REN/MAS/010B

MAS/CCC/FQI/PB/010B

Bridge Pot Bearings

Building Supplies & Services

11/05/2014

Renardet

APPROVED

25/05/2014

REN/FQI/CCC/122

31/05/2014

CCC/FQI/REN/MAS/011

MAS/CCC/FQI/HDPE/011

HDPE Water Pipes

Amiantit Oman

22/02/2014

Renardet

APPROVED

09/03/2014

SO/FQI/CCC/038

11/03/2014

CCC/FQI/REN/MAS/012

MAS/CCC/FQI/RCBC/012

Single cell Precast Box Culvert

Amiantit Oman

22/02/2014

Renardet

APPROVED

25/03/2014

SO/FQI/CCC/064

26/03/2014

CCC/FQI/REN/MAS/013

MAS/CCC/FQI/BP/013

Bituminous Paint Material (Rubberized) Al Inma Building Materilal LLC

02/03/2014

Renardet

Not Approved

20/04/2014

REN/FQI/CCC/105

05/05/2014

CCC/FQI/REN/MAS/013A

MAS/CCC/FQI/BP/013A

Bituminous Paint Material (Rubberized) Henkel Polybit Industries Ltd.

17/06/2014

Renardet

APPROVED

03/07/2014

REN/FQI/CCC/146

13/07/2014

APPROVED

20/05/2014

REN/FQI/CCC/123

31/05/2014

APPROVED

23/03/2014

SO/FQI/CCC/077

02/04/2014

CCC/FQI/REN/MAS/014A-R1 MAS/CCC/FQI/EJ/014A-R1 Bridge Expansion Joints

Al Ammar International

07/05/2014

Renardet

CCC/FQI/REN/MAS/014B

MAS/CCC/FQI/EJ/014B

Bridge Expansion Joints

Ocean Rubber Factory LLC

09/11/2014

Renardet

CCC/FQI/REN/MAS/014C

MAS/CCC/FQI/EJ/014C

Bridge Expansion Joints

Mageba (India)

02/12/2014

Renardet

MAS/CCC/FQI/RC/015

Reinforced Concrete Pipe


(450,600,700mm dia)

Amiantit Oman

02/03/2014

Renardet

CCC/FQI/REN/MAS/015

RENARDET S.A. & PARTNERS

Page 36

Project: Upgrading of Falaj Al Qabail Roundabout

Reference No.

MAR No.

Material/ Work

Monthly Progress Report December 2014

Manufacturer/Supplier/
Subcontractor

MOTC
Renardet
Date
Submitte Remarks
Via Renardet
Comments
Letter
d To
Submitted
By MOTC
Letter Ref. No.
dated
Dated

CCC/FQI/REN/MAS/016 B

MAS/CCC/FQI/WS/016 B

Water Stop G EE-25

Sika LLC Oman

25/03/2014

Renardet

APPROVED

16/04/2014

REN/FQI/CCC/099

28/04/2014

CCC/FQI/REN/MAS/017

MAS/CCC/FQI/TW/017

Telephone Works

National Telephone Services

12/03/2014

Renardet

APPROVED

17/03/2014

SO/FQI/CCC/082

03/04/2014

CCC/FQI/REN/MAS/019

MAS/CCC/FQI/EW/019

Electrical Works

United Engineering Projects

22/03/2014

Renardet

APPROVED

29/05/2014

REN/FQI/CCC/131

16/06/2014

CCC/FQI/REN/MAS/020

MAS/CCC/FQI/EC/020

MV & LV Cables

United Engineering Projects

19/03/2014

Renardet

APPROVED

27/03/2014

SO/FQI/CCC/083

03/04/2014

CCC/FQI/REN/MAS/021

MAS/CCC/FQI/PS/021

Package Substation

United Engineering Projects

22/03/2014

Renardet

----

CCC/FQI/REN/MAS/021A

MAS/CCC/FQI/PS/021A

Package Substation

Voltamp Energy SAOG

16/09/2014

Renardet

APPROVED
as Noted

3/11/2014

REN/FQI/CCC/202

30/11/2014

CCC/FQI/REN/MAS/022

MAS/CCC/FQI/LL/022

Street Lighting Luminaries

Majees Lighting Industries LLC

27/03/2014

Renardet

APPROVED

14/08/2014

REN/FQI/CCC/158

17/08/2014

CCC/FQI/REN/MAS/023A

MAS/CCC/FQI/LP/023A

Street Lighting Poles (Mid-Hinged)

Al Babtain Power &


Telecomunication Co.,

22/05/2014

Renardet

APPROVED

14/08/2014

REN/FQI/CCC/157

17/08/2014

CCC/FQI/REN/MAS/024

MAS/CCC/FQI/FP/024

Street Lighting Feeder Pillar

Stars Light LLC

27/03/2014

Renardet

APPROVED

08/06/2014

REN/FQI/CCC/130

16/06/2014

CCC/FQI/REN/MAS/025

MAS/CCC/FQI/JS/025

Joint Sealant (Polyseal)

Al Inma Building Materilal LLC

27/03/2014

Renardet

APPROVED

16/04/2014

REN/FQI/CCC/100

28/04/2014

---

REN/FQI/CCC/119

27/05/2014

CANCELLED

----

CCC/FQI/REN/MAS/026

MAS/CCC/FQI/GT/026

Geotextile

Modern East Trading & Con.

21/05/2014

Renardet

No meet the
HDS

CCC/FQI/REN/MAS/026A

MAS/CCC/FQI/GT/026A

Geotextile (Bonar NW16)

Bonar Technical Fabrics

15/06/2014

Renardet

APPROVED

14/08/2014

REN/FQI/CCC/159

17/08/2014

CCC/FQI/REN/MAS/027

MAS/CCC/FQI/MS/027

Masterseal 915
(formerly known as Masterflow 410
Plus)

OBasf The Chemical Company

10/08/2014

Renardet

APPROVED
as Noted

21/10/2014

REN/FQI/CCC/196

17/11/2014

CCC/FQI/REN/MAS/028

MAS/CCC/FQI/GG/028

Gully Gratings & Frames

RBA Ferro Industries PVT. Ltd.

17/08/2014

Renardet

APPROVED

25/09/2014

REN/FQI/CCC/192

15/10/2014

CCC/FQI/REN/MAS/030

MAS/CCC/FQI/FLC/030

MasterRoc FLC 100 (Cable Grout


Admixture)

BASF-The Chemical Company

02/10/2014

Renardet

CCC/FQI/REN/MAS/031

MAS/CCC/FQI/CG/031

Cebex Cable Grout Plus

Al Gurg Fosroc

22/12/2014

Renardet

CCC/FQI/REN/MAS/032

MAS/CCC/FQI/GR/032

Guardrails

GK Wire Industries LLC

29/10/2014

Renardet

CCC/FQI/REN/MAS/032A

MAS/CCC/FQI/GR/032A

Guardrails

United Metal Galvanizing Services24/12/2014

Renardet

CCC/FQI/REN/MAS/033

MAS/CCC/FQI/PVC-D/033

1/2" to 8" UPVC Pipe (Class D)

Oman Plast

03/11/2014

Renardet

CCC/FQI/REN/MAS/034

MAS/CCC/FQI/SS1H/034

Tack Coat (SS1H)

Bitu Trade Industrial LLC

15/11/2014

Renardet

RENARDET S.A. & PARTNERS

Page 37

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

18. Engineers Comments


The Planned progress as per the revised Project Execution Program for the month of
December is 8.32% and the Actual progress is 6.89% which shows 1.43% of delay
for the month of December. The actual cumulative progress up to December is
58.30% against Planned Cumulative Progress of 63.86% showing a lagging of
5.56%. The delayed progress is mainly due to the additional works undertaken
during the last few months which may increase in the coming months.
The second Box Girder of Superstructure is ready for casting deck slab and works
are in progress for third Box Girder.
Works for the 02 newly proposed Vehicular Underpasses are in progress.
Extension of Time for the Project Completion Date is approved for 109 days and
Variation Order No. 1 is under preparation for the increase or decrease of Project
Scope.
Utilities relocation works are in progress and affected by Land appropriation
problems.
Contractor requested for second Extension of Time to project completion date
which is under review.

RENARDET S.A. & PARTNERS

Page 38

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

19. Correspondence during the month


S.
No.

Date
Received

From

Reference
No

Subject

12/1/2014

CCC

12/1/2014

CCC

12/2/2014

CCC

12/3/2014

FQI-REN-TR319
FQI/RENARDE
T/282

Street lighting pull box chamber details


Rev.b
Asphalt Mix Design from AlTurki
Asphalt Plant- Sohar

CCC

FQI-REN-TR320
FQI/RENARDE
T/283

12/3/2014

CCC

FQI-REN-TR321

Retaining Wall plan , section& Elevation


@ ch .22+300.000 TO 22+486.700
12/22/2014 Approved
Monthly Progress Report No. 11 November 2014
Shop Drawing for Gantry and Cantilever
sign Layout Plan at ch .21+150 to 21+600
(Material
sheet 1 Test
to 9 )Certificates
Rev.A
for 37C15

12/4/2014

CCC

12/4/2014

CCC

FQI/RENARDE Anchor Block & Jaws - S/c Freysinnet


T/284
Arabian Sea LLC
Cross Section Drawings for SOL-5 (
FQI-REN-TR- Batinah Highway) from Ch.0+200 to
322
0+360, Rev.B

12/4/2014

CCC

FQI-REN-TR323

12/7/2014

CCC

FQI-REN-TR324

10

12/7/2014

CCC

FQI-REN-TR325
FQI/RENARDE
T/285
FQI/RENARDE
T/286
FQI/RENARDE
T/287
FQI-REN-TR326

12/7/2014

CCC

12

12/7/2014

CCC

13

12/8/2014

CCC

14

12/8/2014

CCC

15

12/8/2014

CCC

16

12/10/2014

CCC

17

12/10/2014

CCC

18

12/10/2014

CCC

19

12/11/2014

CCC

FQI-REN-TR327
FQI-REN-TR328
FQI-REN-TR329
FQI/RENARDE
T/288
FQI-REN-TR330
Structural Details for Road Signs

20

12/11/2014

CCC

FQI-REN-TR331

Remarks

12/1/2014 Approved

12/8/2014 Approved

Shop Drawings for pedstrian underpass


& section Details at ch.23+284_SOL-1 (
Sheet 1 of 10 ) Rev .b
12/8/2014
Bar Bending Schedule for Retaining wall
from ch.21+280.405 to 21+235.405, LHS ,
Rev0
12/8/2014
Shop Drawing for Pedestrian Upgrading
of falaj Alqabail RA at Sservice Road 1
Information of SR1 at ch.22+720 to
23+460, Rev .0- UEP
12/17/2014
Calibration test Certifaicates of Jacks &
Pressure Gauges - S/C Freyssinnet
Arabian sea LLC
Test Report for pot Bearing -S/C
Builging Supplies & services LLC
Calibration test Certifaicates Pressure
Gauges , Wika - S/C Fressinet Gulf LLC
Shop Drawing for Bridge Shoring (AB2P3)PE4R1-Sheet 1 to 3, Rev.A
12/13/2014
MSE Wall Elevation of wall SW-A 1 & SWA2 ( Abutment 1 & 2) Design SectionSC freyssint Arbian Sea LLC
12/10/2014
Sign & Road Marking layout plans from
21+150 to 25+223.009 & ch .0+000 to
Typical Road Marking Details ( Line &
Arrows ) - Rev.A
12/21/2014
Stressing Results for Bridge 1 , S/C
Freyssinet Arabian sea LLC

11

RENARDET S.A. & PARTNERS

Reply
date

Approved as Noted

Approved

Approved

Approved

Approved as Noted

Approved

12/16/2014 Approved

30 Meter Street Linghting Foundation


Co-Ordinates layout plan (SOL-2)-Rev.A 12/16/2014 Approved as Noted

Page 39

Project: Upgrading of Falaj Al Qabail Roundabout

Reference
No

Monthly Progress Report December 2014

S.
No.

Date
Received

From

21

12/14/2014

CCC

22

12/16/2014

CCC

23

12/17/2014

CCC

24

12/17/2014

CCC

25

12/17/2014

CCC

26

12/17/2014

CCC

27

12/17/2014

CCC

28

12/18/2014

CCC

29

12/21/2014

CCC

30

12/21/2014

CCC

31

12/21/2014

CCC

32

12/22/2014

CCC

33

12/22/2014

CCC

34

12/22/2014

CCC

35

12/23/2014

CCC

2 Way # 300 mm upvc ducts for Water


line @ ch.0+590(SR_1) -Rev.B
Curb Stone , Interlock Tiles & Guard
FQI-REN-TR- Rails Plans@ ch.21+150 to 21+600 (
333
sheet 0 1 of 09)
Approved Shop Drawing - From Majan
FQI/RENARDE Electric Co. Relocation of Existing 11
T/289
KVA Cable
FQI/RENARDE Calibration Certificate of Stressing Jack
T/290
( Freyssinet Gulf LLC)
FQI/RENARDE
T/291
Tiles Pattern
FQI/RENARDE
T/292
Interim Payment Application No.09
FQI/RENARDE ALTurki (AL tasnim) BBC & BWC Class BT/293
Mix Design
FQI-REN-TR- Retaining Wall plan ( SOL-3 )at@
334
ch.0+130 to 0+310 LHS ( Sheet 1 to 09 )
Original Test Reports for pot Bearings (
FQI/RENARDE Building Supplies & Services LLCT/294
Mageba)
FQI-REN-TR- 2 Way # 300mm upvc Irrigation Ducts @
335
ch . 0+145 ( SOL-2)
Approval for Cebex ( Cable Grout
CCC/FQI/REN Admixture) MAR .
/MAS/031
NO.MAS/CCC/FQI/CG/031
FQI-REN-AS
Relocation of Existing falaj Channel @
BUILT -TR-01 ch . 23+411.400
FQI-REN-TR- Omantel Cable New Location @
336
ch.0+015 to 0+140 RHS (SOL-3 )
FQI-REN-TR337
Bridge Drainage Inlet Cover
FQI-REN-TR- pedestrian underpass lighying plan at
338
ch.0+050
(SOL-3)
1 Way 100mm
& 1 way 150mm upvc

36

12/23/2014

CCC

FQI-REN-AS
BUILT -TR-02

37

12/23/2014

CCC

FQI-REN-AS
BUILT -TR-03

Subject

FQI-REN-TR332

38

12/23/2014

CCC

FQI-REN-AS
BUILT -TR-04

39

12/23/2014

CCC

FQI-REN-AS
BUILT -TR-05

40

12/23/2014

CCC

FQI-REN-AS
BUILT -TR-06

Ducts @ch .0+125.60( Sohar Airport


Cargo Access Road)
2 Way #100mm upvc Omantel Ducts @
ch. 0+011.10( Sohar Airport Cargo Access
Road)
Protwction of Existing water Line #
125mm & #200mm @ ch.0+016( Sohar
Airport Cargo Access Road )
2 Way #100mm upvc Electrical Ducts @
ch. 0+013.760( Sohar Airport Cargo
Access Road)
2Way #150mm upvc street lighting
Ducts @ ch.0+320( Sohar Airport Cargo
Access Road )

41

12/24/2014

CCC

FQI-REN-AS
BUILT -TR-07

Sohar Airport Cargo Acces Road ( Batina


Highway)
cross
Sections
Ch.0+010wall
Bar Bending
Schedule
foratRetaining

42

12/24/2014

CCC

FQI-REN-TR339

from ch.0+130.000 to 0+141.150 ( SOL-3 )


LHS ,

RENARDET S.A. & PARTNERS

Reply
date

Remarks

12/16/2014 Approved

12/22/2014 Approved

12/23/2014 Approved
12/23/2014 Approved
12/24/2014 Approved

Page 40

Project: Upgrading of Falaj Al Qabail Roundabout

S.
No.

Date
Received

From

43

12/24/2014

CCC

44

12/24/2014

CCC

45

12/28/2014

CCC

46

12/28/2014

CCC

47

12/28/2014

CCC

48

12/28/2014

CCC

49

12/28/2014

CCC

50

12/29/2014

CCC

51

12/30/2014

CCC

52

12/30/2014

CCC

53

12/30/2014

CCC

54

12/30/2014

CCC

55

12/31/2014

CCC

56

12/31/2014

CCC

57

12/31/2014

CCC

58

12/31/2014

CCC

59

12/31/2014

CCC

60

12/31/2014

CCC

61

12/31/2014

CCC

62

12/31/2014

CCC

Reference
No
FQI-REN-TR340
CCC/FQI/REN
/MAS/032A
FQI-REN-TR341
FQI-REN-TR342
FQI-REN-TR343
FQI-REN-TR344
FQI-REN-TR345

Monthly Progress Report December 2014

Subject

Reply
date

Remarks

Bar Bending Schedule for Deck Slab


from Abutment 1 to pier 3
12/28/2014 Rejected
Approval for Guardrails MAR .
NO.MAS/CCC/FQI/CG/032A
Bar Bending Schedule for Retaining
wall from 0+241.776 to 0+254.268 ( SOL3) LHS
Bar Bending Schedule for Underpass at
ch.23+284.40 (SOL-1) BLOCK#01 to 04
Typical Section ( Type -2 to Type -7)
Retaining Wall Reinforcement Details
SOL-1 (Batina Highway) Cross Section at
ch.25+080

Guard Rail Details ( W-Beam Type )


Additional Items of Works Not Covered
FQI/MOTC/12 Under BOQ
FQI/RENARDE
T/295
Prophets Birthday Holiday
FQI/RENARDE ALTurki (AL tasnim) BBC Class A-Mix
T/296
Design
FQI-REN-TR346
Structural Details for Road Signs
FQI-REN-TR- SR-1(Batina Highway ) cross section at
347
ch.0+000
Electrical Relocation Work at Falaj
FQI-REN-TR- AlQabail Roundabout for 11 KVA Cable
348
at SOL-03
Proposed of Existing 11 KVA Electrical
FQI-REN-TR- Cable @ch.0+277.100 to 1+002.900 LHS349
SR-02
FQI-REN-TR- Bar Bending Schedule for Underpass
350
Entrance at ch.23+284.40 (SOL-1) LHS
FQI-REN-TR- Bar Bending Schedule for Underpass
351
Entrance at ch.23+284.40 (SOL-1)RHS
Dimension & Details of 1 cell Box
FQI-REN-TR- Culvert ( 2.0*1.0-skew angle 0 )at
352
ch.25+170
FQI/RENARDE
T/297
Unit Built Rates
FQI/RENARDE Project Monthly Progress Videos &
T/298
Pictures
FQI-REN-TR- Access Door & Diapgragm Opening &
353
Bridge Barrier Reinforcement - Typical

RENARDET S.A. & PARTNERS

Page 41

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

Pouring of Concrete in Box Girder of Flyover Bridge No. 4

20. PROGRESS PHOTOGRAPHS

RENARDET S.A. & PARTNERS

Page 42

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

Superstructure of Bridge No. 1 after De-shuttering

Project Activities at a glance

RENARDET S.A. & PARTNERS

Page 43

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

Pouring of Concrete in Abutment Cap for Bridge No. 2

Post Tensioning of Box Girder in Bridge No. 1

RENARDET S.A. & PARTNERS

Page 44

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

Rounding of Median at the Start of Project

8 Cells Box Culvert Works in Progress

RENARDET S.A. & PARTNERS

Page 45

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

Aggregate Base Course Trail in Progress

Work in Progress in Buraimi Road

RENARDET S.A. & PARTNERS

Page 46

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report December 2014

Installation of Drainage Pipes

Installation of Future Service Ducts

RENARDET S.A. & PARTNERS

Page 47