Beruflich Dokumente
Kultur Dokumente
CONSULTANT:
CONTRACTOR:
Table of Contents
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
QA/QC REPORTS...................................................................................................................................................... 33
17.
18.
19.
Page 1
1. Project Particulars
Client:
Consultant:
Contractor:
30.10.2013
Mobilization Period:
60 Days
Construction Period:
548 Days
Completion date:
29.06.2015
R.O. 17,884,403.000
Amount of Contingencies:
R.O. 1,402,155.613
R.O. 16,482,247.387
7.98%
6.02%
55.53%
51.41%
Page 2
2. Scope of Work
This project is located in Batinah Region on existing Batinah Highway in the Wilayat Sohar and
consists of construction of an interchange in place of existing roundabout along with allied works.
Total length of the project along Batinah highway is about 4.0 km which shall be converted from four
lanes to six lanes with tapering back to 4lanes, all as shown on plans. Also included in the scope of
work is the construction of service roads, pedestrian underpasses.
The work also includes expropriation of properties, relocation/protection of services (sewerage,
telephone, electricity, water, irrigation) road lighting works and traffic signals.
Major items within the scope of work consist of but not limited to the following:
Page 3
Page 4
Page 5
Date
09.11.2014
to
14.11.2014
24.11.2014
Page 6
Designation
Date of
Joining
2.
Muneer Abdul
Resident Engineer
19.03.2014
3.
Hussein Shah
Material Engineer
04.01.2014
4.
Ernesto B. Paredes
Bridge Engineer
16.04.2014
5.
Sande H Tangaras
Civil Engineer
08.06.2014
6.
Danilo
Quantity Surveyor
19.06.2014
6.
Mohamed Safie
Land Surveyor
04.01.2014
7.
Aseef Iqbal
Site Inspector
10.02.2014
8.
Site Inspector
30.03.2014
9.
Material Inspector
01.04.2014
Secretary
13.04.2014
Page 7
6. Progress S-Curve
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT PROJECT - OMAN
MONTHLY CL 14 PLANNED VS. ACTUAL MANHOURS
12
120.00
MONTHS
2013
2014
Jan
Feb
Mar
Apr
May
Jun
Actual Cumulative
2015
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
0.01
0.25
1.42
4.23
7.25
10.06
9.42
9.73
10.21
9.79
8.49
5.72
4.55
3.56
2.79
3.83
3.55
3.47
1.67
0.11
0.14
0.23
0.28
1.71
3.18
6.84
9.16
9.14
9.08
7.69
7.98
8.32
6.96
6.50
4.68
3.59
3.34
4.42
0.28
Oct
Sep
Aug
Jul
Jun
May
Apr
Mar
2015
Dec
CUMULATIVE PROGRESS
Feb
2014
MONTHLY PROGRESS
Nov
Sep
Jun
2013
Jan
0.00
Dec
Oct
20.00
Aug
Jul
40.00
May
Apr
60.00
Mar
Feb
80.00
Jan
% Cumulative
100.00
Dec
% MONTHLY
10
0.18
1.01
3.20
5.35
5.18
7.36
7.30
9.33
6.20
6.02
Jul
Aug
3.29
-
1.64
-
Sep
1.11
-
Oct
0.62
-
0.01
0.26
1.67
5.91
13.15
23.21
32.64
42.37
52.58
62.37
70.86
76.59
81.13
84.69
87.48
91.31
94.86
98.33
100.00
100.00
100.00
100.00
100.00
0.11
0.25
0.48
0.76
2.47
5.64
12.48
21.64
30.78
39.87
47.55
55.53
63.86
70.81
77.31
81.99
85.59
88.93
93.35
96.64
98.27
99.38
100.00
0.28
0.45
1.46
4.66
10.01
15.19
22.55
29.86
39.18
45.39
51.41
REV.:
0
PERIOD ENDING:
Nov-14
Item
Description
Road Diversions
Budgeted
Man-Hrs
#REF!
Wtd.
%
#REF!
Plan/
Actual
2013
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
CL14 Plan %
0.30
8.67
19.23
26.89
31.77
36.64
41.51
46.39
51.26
56.13
61.01
65.88
70.76
75.63
80.50
85.38
90.25
95.13
100.00
100.00
100.00
100.00
100.00
80.93
84.74
88.56
92.37
96.18
100.00
100.00
100.00
100.00
100.00
100.00
100.00
80.66
87.59
88.57
100.00
100.00
100.00
Revised Plan %
Actual
CL14 Plan %
Clearing &
Removal of
Obstructions
#REF!
Embankment
#REF!
#REF!
#REF!
#REF!
Subbase &
Aggregate Base
#REF!
Bituminous
Pavement
#REF!
Concrete for
Box Culvert
/Underpas
#REF!
Concrete for
Bridge
#REF!
Drainage Works
#REF!
#REF!
46.60
50.41
54.23
58.04
51.21
56.24
60.13
65.67
69.96
0.00
0.38
20.37
47.70
48.33
48.33
48.33
48.33
#REF!
48.33
48.33
48.33
29.85
78.13
78.13
78.13
78.13
78.13
Actual
10.09
10.09
17.59
19.52
77.42
69.96
70.18
70.18
70.18
83.49
84.12
0.00
0.00
0.78
0.00
Revised Plan %
Actual
Revised Plan %
Revised Plan %
0.00
0.00
-
0.00
0.00
-
1.01
0.00
-
9.21
5.00
0.00
-
6.58
4.35
29.30
5.00
0.00
-
16.76
4.89
45.91
29.38
41.37
58.64
Revised Plan %
66.60
0.00
-
0.00
-
0.00
-
0.00
-
82.85
3.32
12.89
28.83
43.89
60.03
5.27
14.93
29.52
47.15
47.31
56.90
62.24
64.59
67.94
69.08
69.08
4.26
8.17
16.03
32.68
53.13
67.05
67.47
53.23
0.00
62.16
0.00
74.91
0.00
78.29
11.07
91.86
26.27
98.62
41.98
115.33
59.98
1.26
0.00
74.18
0.00
-
0.00
-
0.00
-
0.00
-
0.08
-
3.19
7.77
-
3.58
61.86
48.33
78.13
84.75
74.82
75.05
67.47
78.73
17.42
65.67
59.91
78.13
84.75
90.03
82.85
67.90
79.90
31.37
69.48
77.84
78.13
85.24
95.24
93.48
68.32
79.90
51.32
73.30
90.27
78.13
92.34
95.95
98.64
68.32
85.20
75.82
77.11
94.93
78.13
92.34
100.00
100.00
100.00
100.00
100.00
95.95
96.09
98.30
99.46
99.54
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
68.32
81.11
93.02
97.11
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
75.82
87.25
87.25
98.60
100.00
100.00
100.00
100.00
100.00
100.00
51.97
86.66
90.05
93.03
100.00
89.45
75.82
98.36
92.60
75.82
5.42
19.32
-
31.22
-
44.94
0.08
51.98
8.44
52.14
22.42
90.14
46.57
90.14
51.97
Actual
CL14 Plan %
#REF!
#REF!
MSE walls
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
0.00
0.23
1.43
2.97
10.17
51.47
63.06
74.26
75.97
0.26
2.64
7.33
20.62
35.14
50.06
62.76
68.40
72.78
Actual
0.48
1.26
5.59
14.93
27.72
40.08
55.38
66.20
71.35
Revised Plan %
0.00
0.00
0.00
0.00
4.02
0.00
Revised Plan %
Actual
0.00
0.00
0.00
15.21
0.01
0.00
2.50
0.00
34.62
71.33
6.05
0.00
14.73
0.38
18.14
1.21
22.33
2.63
26.30
3.42
30.75
4.23
34.14
5.50
46.19
6.08
6.08
8.09
26.17
57.85
36.38
14.39
13.24
16.19
16.72
27.56
21.22
41.44
0.00
0.00
2.80
0.00
Actual
0.00
0.00
0.00
Revised Plan %
Actual
Revised Plan
Actual Cum
0.11
-
4.43
6.16
0.00
-
99.96
59.51
Actual
92.89
49.64
0.00
84.50
39.02
83.46
29.64
0.00
83.38
22.09
81.40
13.76
0.00
69.26
74.07
7.75
Revised Plan %
Revised Plan %
57.89
77.37
2.77
17.23
9.87
0.00
-
0.13
5.52
2.61
33.36
4.98
6.42
65.07
17.87
8.31
80.79
43.85
61.59
72.98
7.02
20.33
10.67
12.36
14.45
93.82
81.15
100.00
100.00
100.00
100.00
100.00
74.67
83.42
84.04
84.30
87.32
95.58
98.11
99.44
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
85.14
87.00
93.50
100.00
100.00
100.00
100.00
100.00
100.00
100.00
99.76
100.00
100.00
100.00
100.00
100.00
100.00
94.70
98.41
100.00
100.00
100.00
100.00
34.35
78.53
83.94
82.40
99.38
94.70
84.42
88.97
99.76
94.70
85.35
92.13
94.70
92.86
98.55
100.00
100.00
100.00
100.00
100.00
38.29
50.60
59.52
72.89
81.07
96.39
83.55
86.89
90.26
95.34
98.27
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
2.30
17.26
33.64
49.01
64.70
79.88
95.44
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
17.63
25.69
35.90
49.03
65.95
72.27
72.29
0.17
0.79
1.43
5.65
70.94
75.04
94.02
96.43
49.13
80.05
0.99
13.41
21.84
30.56
0.33
2.34
9.42
17.07
23.51
9.26
13.38
16.87
17.75
20.45
14.38
26.70
32.94
100.00
100.00
100.00
100.00
100.00
100.00
31.40
41.66
47.49
47.55
47.55
83.28
93.95
97.61
100.00
100.00
100.00
0.25
0.48
0.76
2.47
5.64
12.48
21.64
30.78
39.87
47.55
55.53
63.86
70.81
77.31
81.99
85.59
88.93
93.35
96.64
98.27
99.38
100.00
0.28
0.45
1.46
4.66
10.01
15.19
22.55
29.86
39.18
45.39
51.41
May
Jun
Jul
Aug
Sep
Oct
Nov
Jun
Jul
Aug
2014
2013
Jan
Feb
Mar
Apr
2015
Dec
Jan
Feb
Mar
Apr
May
Sep
Oct
0.01
0.25
1.42
4.23
7.25
10.06
9.42
9.73
10.21
9.79
8.49
5.72
4.55
3.56
2.79
3.83
3.55
3.47
1.67
0.11
0.14
0.23
0.28
1.71
3.18
6.84
9.16
9.14
9.08
7.69
7.98
8.32
6.96
6.50
4.68
3.59
3.34
4.42
3.29
1.64
1.11
0.62
CUMULATIVE PROGRESS
36.51
Dec
MONTHLY PROGRESS
23.65
Actual
CL14 Plan %
#REF!
0.00
Revised Plan %
CL14 Plan %
#REF!
TOTAL
42.78
44.11
Actual
Incidental
Construction
38.97
43.00
7.40
CL14 Plan %
35.16
37.31
-
CL14 Plan %
30.90
22.36
-
CL14 Plan %
24.18
13.03
-
CL14 Plan %
17.58
6.62
-
Actual
CL14 Plan %
#REF!
0.00
9.30
CL14 Plan %
Structural
Excavation
2015
Revised Plan %
CL14 Plan %
4.11
2014
0.28
0.18
1.01
3.20
5.35
5.18
7.36
7.30
9.33
6.20
6.02
0.01
0.26
1.67
5.91
13.15
23.21
32.64
42.37
52.58
62.37
70.86
76.59
81.13
84.69
87.48
91.31
94.86
98.33
100.00
100.00
100.00
100.00
100.00
0.11
0.25
0.48
0.76
2.47
5.64
12.48
21.64
30.78
39.87
47.55
55.53
63.86
70.81
77.31
81.99
85.59
88.93
93.35
96.64
98.27
99.38
100.00
0.28
0.45
1.46
4.66
10.01
15.19
22.55
29.86
39.18
45.39
51.41
Description
Unit
BOQ Qty.
(Revised)
Actual
Qty.
%
Completion
M2
162,000
129,901
80.19%
M3
340,000
155,167
45.64%
M3
28,700
6,449
22.47%
M3
15,000
12,805
85.37%
M3
13,805
3,991
28.91%
ton
4,900
2,477
50.55%
Working Piles
M3
2,826
2,826
100.00%
M3
5,210
0.00
0.00%
MSE Walls
M2
13,200
7,389
55.97%
11
LM
4,530
1,035
22.85%
ACTIVITY
AB1 L
PEDESTAL/POT
BEARING
9-Nov-14
9-Nov-14
15-Nov-14
AB2 L
24-Jul-14
6.920
29-Jun-14
1.440
17-May-14
29-Sep-14 4-Sep-14
6.920
6.920
15-Sep-14 10-Aug-14
1.248
1.225
4-Sep-14 23-Jun-14
N/A
-
8-May-14
25-Aug-14 11-Jun-14
1-May-14
17-Aug-14 3-Jun-14
2nd Lift
Height (m)
1st Lift
Height (m)
BIT. PAINTING
PILE CAP (Pier &
Abut.)
ACTIVITY
AB1 R
PEDESTAL/POT
BEARING
9-Nov-14
P5L
13-Aug-14 19-Aug-14
6.920
6.920
23-Jul-14 7-Aug-14
1.153
1.210
28-May-14 26-Jun-14
N/A
-
PIER
PIER
2nd Lift
Height (m)
1st Lift
Height (m)
BIT. PAINTING
PILE CAP (Pier &
Abut.)
AB2 R
N/A
-
9-Jun-14 28-Jun-14
6.920
6.920
20-May-14 11-Jun-14
0.366
0.423
12-May-14 25-May-14
22-Jun-14
6.920
26-May-14
0.649
8-May-14
20-Sep-14 10-Jul-14
6.920
6.920
10-Sep-14 22-Jun-14
0.461
0.438
4-Sep-14 31-May-14
N/A
-
9-Oct-14
4-May-14 13-May-14
30-Apr-14
27-Aug-14 20-May-14
27-Apr-14 7-May-14
22-Apr-14
20-Aug-14 14-May-14
2-Oct-14
P5R
EXPANSION JOINT
CONCRETE BARRIER
WEB:
W1
W2
W3
W4
BOTTOM SLAB
(BASE)
ACTIVITY (RHS)
EXPANSION JOINT
CONCRETE BARRIER
26-Nov-14
26-Nov-14
26-Nov-14
26-Nov-14
W1
10-Nov-14
10-Nov-14
10-Nov-14
10-Nov-14
W2
10-Nov-14
10-Nov-14
10-Nov-14
10-Nov-14
W3
10-Nov-14
10-Nov-14
10-Nov-14
10-Nov-14
W4
10-Nov-14
10-Nov-14
10-Nov-14
10-Nov-14
28-Oct-14
28-Oct-14
28-Oct-14
28-Oct-14
WEB:
BOTTOM SLAB
(BASE)
Page 11
FROM
TO
DATE
2-Oct-14
3-Oct-14
30-Sep-14
22+760
22+825
1-Oct-14
13-Jul-14
22+825
22+840
El. 20.40
14-Jul-14
6-Jul-14
22+840
22+880
13-Jul-14
22+880 22+908.387 10-Aug-14
11-Aug-14
22+908.38722+969.478 3-Jul-14
El. 21.20
5-Jul-14
4-Aug-14
22+969.478 23+000
5-Aug-14
20-Jul-14
23+000
23+025
21-Jul-14
17-Jul-14
23+025
23+070
El. 22.00
18-Jul-14
30-Jun-14
23+070
23+140
1-Jul-14
22+702.653
23+140
Elevation
FOUNDATION
/BLINDING
22+760
23+164.573 16-Jun-14
17-Jun-14
23+164.57323+237.536 23-Jun-14
El. 22.80
24-Jun-14
23+237.53623+270.762 17-Jun-14
El. 22.00
18-Jun-14
PREVIOUS
P R E V IO US
M ON T H
El. 20.40
El. 21.20
El. 22.00
El. 22.80
El. 22.00
LOCATION (RHS)
FROM
TO
22+718.936
22+810
22+810
22+893.032
22+893.032 22+976.294
22+976.294
23+040
23+040
23+088.046
23+088.046
23+130
23+130
23+191.774
23+191.774 23+270.800
LOCATION (AB 1)
Elevation
El. 22.00
FROM
TO
DATE
FOUNDATION
/BLINDING
17-Sep-14
18-Sep-14
9-Aug-14
10-Aug-14
13-Aug-14
14-Aug-14
18-Aug-14
19-Aug-14
26-Jul-14
27-Jul-14
21-Jul-14
22-Jul-14
7-Jul-14
10-Jul-14
26-Jun-14
27-Jun-14
DATE
FOUNDATION
/BLINDING
THIS MONTH
Page 12
ELEV.
22+840
22+880
22+908.387
22+969.478
34.800
34.000
33.200
32.400
31.600
30.800
30.000
29.200
28.400
27.600
26.800
26.000
25.200
24.400
23.600
22.800
22.000
21.200
20.400
10-Nov-14
22-Sep-14
3-Sep-14
28-Aug-14
-
25-Nov-14
10-Nov-14
22-Sep-14
3-Sep-14
28-Aug-14
-
25-Nov-14
10-Nov-14
22-Sep-14
3-Sep-14
28-Aug-14
-
30-Nov-14
18-Nov-14
20-Oct-14
5-Nov-14 5-Nov-14 16-Sep-14
29-Oct-14 29-Oct-14 4-Sep-14
21-Sep-14 17-Sep-14 27-Aug-14
11-Sep-14 24-Aug-14 9-Aug-14
28-Aug-14
-
ELEV.
33.200
32.400
31.600
30.800
30.000
29.200
28.400
27.600
26.800
26.000
25.200
24.400
23.600
22.800
22.000
21.200
20.400
22+991
23+084
P R E V IO US
M ON T H
23+164.573
23+237.536
23+270.762
13-Nov-14
19-Oct-14
18-Oct-14
20-Sep-14
9-Sep-14
4-Sep-14
26-Aug-14
18-Aug-14
13-Aug-14
28-Jul-14
-
13-Nov-14
1-Oct-14
24-Sep-14
18-Sep-14
15-Sep-14
28-Aug-14
19-Aug-14
6-Aug-14
24-Jul-14
-
1-Oct-14
24-Sep-14
18-Sep-14
15-Sep-14
28-Aug-14
19-Aug-14
6-Aug-14
24-Jul-14
13-Jul-14
-
AB 1 Face
23+270.80
0
30-Sep-14
24-Sep-14
18-Sep-14
13-Sep-14
31-Aug-14
18-Aug-14
6-Aug-14
24-Jul-14
13-Jul-14
-
2 3 +2 7 0 .7 6 2
( L)
2 3 +2 7 0 .8 0 0
(R )
28-Sep-14
24-Sep-14
19-Sep-14
11-Sep-14
28-Aug-14
18-Aug-14
7-Aug-14
24-Jul-14
13-Jul-14
-
28-Sep-14
24-Sep-14
19-Sep-14
11-Sep-14
28-Aug-14
18-Aug-14
7-Aug-14
24-Jul-14
13-Jul-14
-
THIS MONTH
Page 13
FROM
TO
LOCATION (AB 2)
DATE
FOUNDATION
/BLINDING
15-Sep-14
16-Sep-14
El. 23.30
23+520
23+580.87720-Aug-14
21-Aug-14
26-Aug-14
23+580.87723+650
23+508.239 23+520
Elevation
El. 23.30
1-Sep-14
2-Sep-14
19-Sep-14
23+735
23+790
20-Sep-14
23+790
23+827.63510-Oct-14
11-Oct-14
23+827.63523+949.89515-Oct-14
El. 24.90
16-Oct-14
23+650
23+735
TO
23+508.197 (R15-Sep-14
)
23+508.239 (L)
16-Sep-14
FROM
27-Aug-14
El. 24.10
FROM
DATE
FOUNDATIO
N /BLINDING
DATE
FOUNDATIO
N /BLINDING
TO
23+508.197 23+607.6348-Sep-14
9-Sep-14
22-Sep-14
23+607.63423+740
23-Sep-14
16-Oct-14
23+740
23+750
El. 24.10
17-Oct-14
23+750
23+950.1533-Nov-14
4-Nov-14
El. 23.30
ELEV.
23+520
23+580.877
23+650
23+703
23+730
23+827.635
23+949.895
29.700
28.900
28.100
27.300
26.500
25.700
24.900
24.100
23.300
8-Nov-14
29-Oct-14
13-Oct-14
25-Sep-14
-
8-Nov-14
29-Oct-14
13-Oct-14
25-Sep-14
-
15-Nov-14
1-Nov-14
26-Sep-14
-
15-Nov-14
1-Nov-14
26-Sep-14
-
24-Nov-14
16-Nov-14
13-Nov-14
-
ELEV.
29.700
28.900
28.100
27.300
26.500
25.700
24.900
24.100
23.300
AB 2 Face
RHS (AB
23+607.634
26-Nov-14
19-Nov-14
5-Nov-14
11-Nov-14
16-Oct-14
15-Oct-14
30-Sep-14
9-Oct-14
-
2 3 +5 0 8 .2 3 9 ( L)2 3 +5 0 8 .19 7 ( R )
26-Nov-14
5-Nov-14
16-Oct-14
30-Sep-14
PREVIOUS
P R E V IO US
M ON T H
Page 14
WALL
TOP SLAB
NO.
STATION
LENGTH (m)
SKEW ( )
F/P &
BLINDING
Rebars
Concrete
Rebars
Concrete
Rebars
Concrete
1
LHS
RHS
RHS
2
21+260
Block 1
Block 2
Block 3
21+485
Block 1a
Block 1b
Block 2a
Block 2b
Block 2C
21+838
Block 1a
Block 1b
Block 2
Block 3
Block 4a
Block 4b
Block 5
Block 6
21+972.4
Block 1
Block 2
Block 3
Block 4
Block 5
Block 6
Block 7
Block 8
Block 9
Block 10
Block 11
Block 12
Block 13
Block 14
Block 15
Block 16
Block 17
Block 18
Block 19
Block 20
Block 21
Block 22
25.546
19.526
14.473
6.000
39.750
3.000
17.290
7.710
10.000
11.730
57.210
5.000
17.600
22.600
11.970
5.000
17.600
22.600
11.970
57.629
28.038
28.031
28.026
28.022
28.019
28.018
28.019
28.022
28.026
28.031
28.038
21.015
21.010
21.006
21.003
21.001
21.000
21.001
21.003
21.006
21.010
21.015
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
19-Oct-14
19-Oct-14
1-Jul-14
1-Jul-14
19-Oct-14
21-Jul-14
3-Jul-14
3-Jul-14
21-Jul-14
3-Jul-14
3-Jul-14
24-May-14
24-May-14
17-May-14
18-May-14
18-May-14
18-May-14
18-May-14
26-May-14
26-May-14
28-May-14
28-May-14
10-Aug-14
27-Jul-14
27-Jul-14
25-Jul-14
16-Jun-14
16-Jun-14
12-Jun-14
12-Jun-14
8-Jun-14
8-Jun-14
8-Jun-14
26-Oct-14
4-Nov-14
31-Aug-14
31-Aug-14
25-Oct-14
4-Sep-14
4-Sep-14
20-Aug-14
10-Sep-14
10-Sep-14
23-Sep-14
5-Jun-14
9-Jul-14
25-May-14
12-Jul-14
29-May-14
31-Jul-14
10-Jun-14
9-Aug-14
15-Jun-14
17-Aug-14
19-Jun-14
25-Aug-14
22-Sep-14
12-Oct-14
23-Aug-14
27-Jul-14
14-Sep-14
24-Oct-14
16-Oct-14
29-Sep-14
1-Sep-14
25-Jun-14
27-Oct-14
4-Nov-14
31-Aug-14
31-Aug-14
25-Oct-14
5-Sep-14
5-Sep-14
20-Aug-14
12-Sep-14
12-Sep-14
24-Sep-14
5-Jun-14
10-Jul-14
25-May-14
13-Jul-14
29-May-14
31-Jul-14
10-Jun-14
10-Aug-14
15-Jun-14
18-Aug-14
19-Jun-14
26-Aug-14
22-Sep-14
12-Oct-14
23-Aug-14
27-Jul-14
15-Sep-14
24-Oct-14
17-Oct-14
30-Sep-14
2-Sep-14
25-Jun-14
9-Nov-14
15-Nov-14
31-Aug-14
31-Aug-14
25-Oct-14
13-Oct-14
13-Oct-14
30-Oct-14
18-Oct-14
18-Oct-14
24-Oct-14
24-Jun-14
3-Aug-14
3-Jun-14
5-Aug-14
8-Jun-14
12-Aug-14
1-Jul-14
25-Aug-14
7-Jul-14
14-Sep-14
20-Jul-14
2-Sep-14
29-Sep-14
15-Oct-14
8-Sep-14
14-Aug-14
23-Sep-14
30-Oct-14
21-Oct-14
1-Oct-14
21-Sep-14
30-Jul-14
9-Nov-14
15-Nov-14
31-Aug-14
31-Aug-14
25-Oct-14
13-Oct-14
13-Oct-14
30-Oct-14
19-Oct-14
19-Oct-14
25-Oct-14
24-Jun-14
4-Aug-14
3-Jun-14
6-Aug-14
8-Jun-14
13-Aug-14
1-Jul-14
26-Aug-14
8-Jul-14
14-Sep-14
20-Jul-14
3-Sep-14
29-Sep-14
15-Oct-14
8-Sep-14
14-Aug-14
24-Sep-14
31-Oct-14
21-Oct-14
1-Oct-14
21-Sep-14
30-Jul-14
9-Nov-14
15-Nov-14
31-Aug-14
31-Aug-14
25-Oct-14
13-Oct-14
13-Oct-14
30-Oct-14
18-Oct-14
18-Oct-14
24-Oct-14
15-Jul-14
13-Aug-14
23-Jun-14
18-Aug-14
2-Jul-14
27-Aug-14
23-Jul-14
9-Sep-14
4-Aug-14
24-Sep-14
2-Sep-14
1-Oct-14
18-Oct-14
26-Oct-14
18-Sep-14
3-Sep-14
14-Oct-14
7-Nov-14
30-Oct-14
21-Oct-14
30-Sep-14
16-Sep-14
9-Nov-14
15-Nov-14
31-Aug-14
31-Aug-14
25-Oct-14
13-Oct-14
13-Oct-14
30-Oct-14
19-Oct-14
19-Oct-14
25-Oct-14
16-Jul-14
14-Aug-14
23-Jun-14
19-Aug-14
2-Jul-14
28-Aug-14
24-Jul-14
10-Sep-14
5-Aug-14
25-Sep-14
3-Sep-14
1-Oct-14
19-Oct-14
27-Oct-14
19-Sep-14
4-Sep-14
15-Oct-14
7-Nov-14
30-Oct-14
21-Oct-14
30-Sep-14
17-Sep-14
LHS
RHS
3
LHS
RHS
LHS
RHS
4
LHS
RHS
Bituminous Paint
(2 Coats)
1-Sep-14
1-Sep-14
25-Oct-14
16-Aug-14
8-Sep-14
8-Sep-14
1-Oct-14
1-Oct-14
1-Oct-14
5-Oct-14
25-Sep-14
25-Sep-14
NO.
RHS
5
LHS
RHS
LHS
RHS
LHS
RHS
6
LHS
RHS
LHS
RHS
STATION
LENGTH (m)
SKEW ( )
Block 23
Block 24
Block 25
Block 26
Block 27
Block 28
Block 29
Block 30
Block 31
Block 32
Block 33
22+655
(9 cells)
Block 1
Block 2
Block 3
Block 4
Block 4a
Block 5
Block 6
Block 7
Block 8
Block 9
Block 10
Block 11
Block 12
23+492
(5 cells)
Block 1
Block 2
Block 3
Block 4
Block 5
Block 6
Block 7
Block 8
6.635
6.782
6.819
7.217
7.975
8.571
9.267
9.949
10.260
10.262
10.265
95.482
0
0
0
0
0
0
0
0
0
0
0
45 R
9.675
32.711
32.711
11.850
13.130
19.035
32.711
32.711
10.95
25.03
32.711
32.711
4.960
79.065
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
15 R
6.457
31.546
31.546
7.982
7.039
31.546
31.546
5.525
15 R
15 R
15 R
15 R
15 R
15 R
15 R
15 R
BASE SLAB
WALL
TOP SLAB
F/P &
BLINDING
Rebars
Concrete
Rebars
Concrete
Rebars
Concrete
Bituminous Paint
(2 Coats)
24-Nov-14
30-Jun-14
24-Jun-14
11-Sep-14
24-Nov-14
29-Jun-14
24-Jun-14
24-Nov-14
28-Jun-14
29-Jun-14
24-Jun-14
24-Jun-14
9/172014
24-Jun-14
24-Jun-14
17-Sep-14
29-Nov-14
6-Aug-14
21-Jul-14
12-Oct-14
27-Jul-14
28-Aug-14
20-Aug-14
3-Aug-14
9-Jul-14
14-Jul-14
23-Sep-14
5-Aug-14
6-Aug-14
28-Sep-14
29-Nov-14
7-Aug-14
21-Jul-14
13-Oct-14
28-Jul-14
28-Aug-14
23-Aug-14
4-Aug-14
9-Jul-14
15-Jul-14
24-Sep-14
5-Aug-14
6-Aug-14
28-Sep-14
1-Sep-14
17-Aug-14
22-Oct-14
13-Sep-14
24-Sep-14
2-Oct-14
2-Oct-14
30-Jul-14
3-Aug-14
28-Sep-14
-
2-Sep-14
18-Aug-14
22-Oct-14
14-Sep-14
26-Sep-14
3-Oct-14
3-Oct-14
30-Jul-14
3-Aug-14
28-Sep-14
-
9 & 20/8/2014
11 & 25/8/2014
9 & 23/8/2014
11 & 26/8/2014
2-Oct-14
11-Oct-14
2-Oct-14
11-Oct-14
1-Sep-14
17-Aug-14
22-Oct-14
13-Sep-14
24-Sep-14
2-Oct-14
2-Oct-14
16-Aug-14
21-Aug-14
1-Oct-14
28-Aug-14
31-Aug-14
11-Oct-14
-
2-Sep-14
18-Aug-14
22-Oct-14
14-Sep-14
26-Sep-14
3-Oct-14
3-Oct-14
17-Aug-14
21-Aug-14
2-Oct-14
28-Aug-14
1-Sep-14
11-Oct-14
-
13-Oct-14
13-Oct-14
13-Oct-14
13-Oct-14
13-Oct-14
13-Oct-14
6-Sep-14
6-Sep-14
18-Oct-14
4-7/9/2014
4-7/9/2014
18-Oct-14
-
NO.
STATION
LENGTH (m)
SKEW ( )
23+756.5
Block 1
Block 2
Block 3a
Block 3b
Block 4
23+997
Block 1
Block 2a
Block 2b
Block 3a
Block 3b
Block 4a
Block 4b
24+235
Block 1a
Block 1b
Block 2a
Block 2b
Block 2c
24+570
Block 1
Block 2a
Block 2b
67.550
12.090
20.180
14.430
8.700
12.090
70.268
16.128
4.933
13.860
16.300
4.942
7.848
6.197
59.106
15.566
15.000
8.900
15.600
4.020
51.953
25.846
13.500
12.587
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
LHS
RHS
8
LHS
RHS
9
LHS
RHS
10
LHS
RHS
BASE SLAB
WALL
Rebars
Concrete
Rebars
Concrete
Rebars
Concrete
Bituminous Paint
(2 Coats)
12-Jul-14
12-Jul-14
11-Aug-14
8-Jul-14
8-Jul-14
10-Aug-14
10-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
26-Aug-14
24-Jul-14
24-Jul-14
28-Aug-14
24-Jul-14
24-Jul-14
31-Aug-14
31-Aug-14
12-Jul-14
12-Jul-14
10-Aug-14
14-Aug-14
14-Aug-14
24-Nov-14
23-Jul-14
23-Jul-14
26-Aug-14
25-Aug-14
25-Aug-14
-
23-Jul-14
23-Jul-14
26-Aug-14
25-Aug-14
25-Aug-14
-
23-Jul-14
23-Jul-14
26-Aug-14
25-Aug-14
25-Aug-14
-
23-Jul-14
23-Jul-14
26-Aug-14
25-Aug-14
25-Aug-14
-
23-Jul-14
23-Jul-14
26-Aug-14
25-Aug-14
25-Aug-14
-
23-Jul-14
23-Jul-14
26-Aug-14
25-Aug-14
25-Aug-14
-
24-Jul-14
24-Jul-14
31-Aug-14
31-Aug-14
31-Aug-14
-
Note: Precast RCBC were used for all 1 cell - 2.0m x 1.5m
PREVIOUS
TOP SLAB
F/P &
BLINDING
PREVIOUS MONTH
THIS MONTH
STATION
LENGTH (m)
SKEW ( )
1
LHS
RHS
2
LHS
RHS
21+300
Block 1
Block 2
24+600
Block 1
Block 2
37.700
15.780
21.900
44.051
21.620
22.411
0
0
0
0
0
0
F/P &
BLINDING
BASE SLAB
Rebars
Concrete
WALL
Rebars
Concrete
TOP SLAB
Rebars
Concrete
Bituminous
Paint (2 Coats)
STATION
23+284.40, SOL-1
1
LHS
Block 1
RHS
Block 2
2 24+360, SOL-1
LHS
Block 1
LHS
Block 2
RHS
Block 3
RHS
Block 4
3 0+050, SOL-3
LHS
Block 1
LHS
Block 2
LHS
Block 3
RHS
Block 4
LENGTH (m)
SKEW ( )
59.614
9.000
20.777
22.777
7.000
83.223
17.721
17.721
17.721
30.000
0
0
0
0
0
0
0
0
0
0
0
0
0
PREVIOUS
F/P &
BLINDING
BASE SLAB
Rebars
15-Sep-14 1-Oct-14
11/55/2014
-
PREVIOUS
MONTH
Concrete
1-Oct-14
-
WALL
Rebars
Concrete
TOP SLAB
Rebars
Concrete
THIS MONTH
Bituminous
Paint (2 Coats)
PIPE
DRAWING No.
NO. OF
CHAINAGE
STAGES
DIA
TYPE
WAYS
CCC/FQI/IR/06
SERVICE ROAD-3
0+030
200
UPVC
CCC/FQR/IR/11 SOL2
0+150
300
UPVC
CCC/FQR/IR/10 SOL3
0+300
200
UPVC
CCC/FQR/WA/05
SR-1
0+600
300
UPVC
CCC/FQI/SL/01
21+160
150
UPVC
CCC/FQI/EL/01
21+360
150
UPVC
CCC/FQI/IR/01
21+460
300
UPVC
CCC/FQI/EL/02
21+660
150
UPVC
CCC/FQI/IR/02
21+780
300
UPVC
10
CCC/FQI/EL/03
21+880
150
UPVC
11
CCC/FQI/EL/04
22+260
150
UPVC
12
CCC/FQI/EL/05
22+510
150
UPVC
13
CCC/FQI/IR/03
22+520
200
UPVC
22+520 LHS
200
UPVC
22+587 LHS
200
UPVC
22+760
150
UPVC
14
15
CCC/FQI/IR/04
JUNCTION
CROSSING
CCC/FQI/IR/05
JUNCTION
CROSSING
16
CCC/FQI/EL/06
17
CCC/FQI/WA/02
JUNCTION
23+008 LHS
300
UPVC
18
CCC/FQI/WA/01
23+020
900
RC
19
CCC/FQI/EL/07
23+060
150
UPVC
20
CCC/FQI/EL/13
23+210
150
UPVC
21
CCC/FQI/EL/08
23+240
150
UPVC
22
CCC/FQI/EL/09
23+560
150
UPVC
23
CCC/FQI/EL/10
23+820
150
UPVC
24
CCC/FQI/WA/03
23+900
600
RC
25
CCC/FQI/SL/11
23+960
150
UPVC
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
SETOUT/EX
INSTALLA CONCRET BACKFILLI
CV/BED
TION
E
NG
PREP
RFI REF.
LAY
CONCRETE
BACKFILL
9/24/14
9/24/14
10/18/14
UTL-LAY- 104
UTL-CON-131A
5/15/14
6/11/14
5/15/14
6/11/14
5/18/14
6/12/14
6/12/14 UTL-LAY- 81
7/10/14 UTL-LAY- 104
UTL-CON- 65
UTL-CON- 83
UTL-BF- 01
UTL-BF- 20
5/19/14
5/19/14
6/14/14 14/06/014
5/20/14
6/14/14
6/4/14 UTL-LAY- 87
6/21/14 UTL-LAY- 108
UTL-CON- 66
UTL-CON- 84
UTL-BF- 03
UTL-BF- 21
5/19/14
6/15/14
5/19/14
6/15/14
5/20/14
6/15/14
5/31/14 UTL-LAY- 85
UTL-LAY- 107
UTL-CON- 63
UTL-CON- 85
UTL-BF- 02
5/20/14
6/15/14
5/20/14
6/15/14
5/25/14
6/15/14
6/4/14 UTL-LAY- 86
7/8/14 UTL-LAY- 109
UTL-CON- 64
UTL-CON- 87
UTL-BF- 05
UTL-BF- 23
5/25/14
6/16/14
5/25/14
6/16/14
5/25/14
6/17/14
6/4/14 UTL-LAY- 90
7/10/14 UTL-LAY- 111
UTL-CON-68
UTL-CON- 88
UTL-BF- 07
UTL-BF- 28
6/17/14
7/20/14
6/17/14
7/20/14
6/18/14
7/21/14
UTL-CON- 89
UTL-CON- 106
UTL-BF- 33
UTL-BF-44
6/19/14
7/20/14
6/19/14
7/20/14
6/19/14
7/21/14
UTL-CON- 92
UTL-CON- 107
UTL-BF- 31
UTL-BF-46
6/19/14
7/20/14
6/19/14
7/20/14
6/19/14
7/21/14
UTL-CON- 91
UTL-CON- 108
UTL-BF- 30
UTL-BF-45
5/26/14
6/11/14
5/26/14
6/11/14
5/26/14
6/11/14
6/8/14 UTL-LAY- 88
7/22/14 UTL-LAY-106
UTL-CON- 69
UTL-CON- 81
UTL-BF- 08
UTL-BF-26
6/16/14
7/8/14
6/16/14
7/8/14
6/16/14
7/9/14
UTL-CONUTL-CON-99
UTL-BF-19
UTL-BF-42
5/25/14
11/06/201
5/25/14
6/11/14
5/26/14
6/11/14
6/14/14 UTL-LAY- 91
6/23/14 UTL-LAY- 105
UTL-CON- 71
UTL-CON- 82
UTL-BF- 06
UTL-BF- 25
5/27/14
5/27/14
5/27/14
6/17/14 UTL-LAY- 92
UTL-CON- 72
UTL-BF- 09
5/28/14
5/28/14
5/28/14
6/17/14 UTL-LAY- 93
UTL-CON- 70
UTL-BF- 10
5/29/14
7/30/14
5/29/14
8/12/14
5/29/14
7/30/14
6/17/14 UTL-LAY- 94
8/26/14 UTL-LAY-142
UTL-CON- 73
UTL-CON- 115
UTL-BF- 11
UTL-BF-48
5/29/14
7/14/14
6/2/14
7/14/14
6/2/14
7/14/14
6/17/14 UTL-LAY- 95
8/20/14 UTL-LAY- 124
UTL-CON- 75
UTL-CON- 102
UTL-BF- 15
UTL-BF- 36
5/29/14
7/14/14
6/2/14
7/14/14
6/2/14
7/15/14
6/17/14 UTL-LAY-97
8/20/14 UTL-LAY- 127
UTL-CON- 76
UTL-CON- 101
UTL-BF- 13
UTL-BF- 38
8/10/14
10/27/14
8/11/14
10/27/14
8/11/14
10/27/14
8/26/14 UTL-LAY-149A
UTL-LAY- 206
S.
NO.
PIPE
DRAWING No.
NO. OF
CHAINAGE
STAGES
DIA
TYPE
WAYS
26
CCC/FQI/EL/11
23+980
150
UPVC
27
CCC/FQI/WA/04
24+000
600
RC
28
CCC/FQI/IR/07
24+020
300
UPVC
29
CCC/FQI/EL/12
24+120
150
UPVC
30
CCC/FQI/EL/14
24+220
150
UPVC
31
CCC/FQI/IR/08
24+340
300
UPVC
32
CCC/FQI/EL/15
24+520
150
UPVC
33
CCC/FQI/EL/16
24+820
150
UPVC
34
CCC/FQI/IR/09
24+960
300
UPVC
35
CCC/FQI/EL/17
25+160
150
UPVC
36
CCC/FQI/NAW.2
21+870
100
UPVC
37
CCC/FQI/NAW.3
23+580
100
UPVC
38
CCC/FQI/NAW.4
24+720
100
UPVC
39
CCC/FQI/OMANTEL
.1
22+810
100
UPVC
40
CCC/FQI/OMANTEL
0+140 SOL-3
.2
100
UPVC
41
CCC/FQI/SL/03 Rev
A
22+820
150
UPVC
42
CCC/FQI/SL/04
22+990
150
UPVC
CCC/FQI/SL/02
22+080
150
UPVC
44
CCC/FQI/EL/19
23+740
150
UPVC
45
CCC/FQI/SL/01
24+850
150
UPVC
46
CCC/FQI/SD/07
21+500
450
CONC PIPE
43
2-4WAY
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
SETOUT/EX
INSTALLA CONCRET BACKFILLI
CV/BED
TION
E
NG
PREP
RFI REF.
LAY
CONCRETE
BACKFILL
5/29/14
8/6/14
6/2/14
8/6/14
6/3/14
8/9/14
6/3/14
8/11/14
6/4/14
8/11/14
6/4/14
8/19/14
6/4/14
7/23/14
6/5/14
7/24/14
6/9/14
8/6/14
6/9/14
8/6/14
6/10/14
8/6/14
7/5/14
7/5/14
7/5/14
7/16/14
10/27/14
7/16/14
10/27/14
7/17/14
10/27/14
UTL-BF- 41R1
UTL-BF- 72
9/14/14
10/27/14
9/14/14
10/30/14
10/14/14
10/27/14
UTL-CON-125
UTL-CON- 150
UTL-BF-81
9/16/14
10/27/14
9/20/14
10/27/14
10/27/14
UTL-LAY- 173
11/9/14 UTL-LAY- 203
UTL-CON- 149
UTL-BF-100
11/3/14
11/10/14
11/4/14
UTL-CON- 155
UTL-BF-106
5/21/14
6/16/14
5/21/14
6/16/14
5/21/14
6/18/14
6/4/14 UTL-LAY- 89
7/10/14 UTL-LAY- 110
UTL-CON- 67
UTL-CON- 90
UTL-BF- 04
UTL-BF- 29
5/29/14
7/10/14
5/31/14
7/10/14
5/31/14
8/13/14
6/17/14 UTL-LAY- 96
UTL-CON- 74
8/26/14 UTL-LAY- 120 R1 UTL-CON- 95
UTL-BF- 12
UTL-BF- 49
7/21/14
8/8/14
9/16/14
7/7/14
8/12/14
8/4/14
8/9/14
9/16/14
7/8/14
8/13/14
8/5/14
8/9/14
9/16/14
7/8/14
8/14/14
UTL-LAY-137-R1
9/22/14 UTL-LAY-148A
UTL-LAY-172
UTL-LAY-103A
8/15/14 UTL-LAY-150
7/9/14
8/12/14
10/12/14
7/2/14
7/10/14
7/22/14
8/30/14
11/27/14
7/9/14
8/13/14
10/13/14
7/3/14
7/10/14
7/22/14
8/31/14
7/9/14
8/14/14
10/12/14
7/3/14
7/14/14
7/23/14
9/14/14
11/27/14
UTL-LAY- 116
9/25/14 UTL-LAY-151
11/8/14 UTL-LAY-187
UTL-LAY-122
UTL-LAY-126
8/20/14 UTL-LAY-136
9/30/14 UTL-LAY-158
11/29/14 UTL-EXC-63
UTL-CON-100
UTL-CON-121
UTL-CON-137
UTL-CON-93R1
UTL-CON-103
UTL-CON-110
UTL-CON-96
UTL-CON-162
9/7/14
9/15/14
10/27/14
9/16/14
10/14/14
10/27/14
9/7/14
9/15/14
10/28/14
9/17/14
10/18/14
10/27/14
10/14/14
10/27/14
11/4/14
11/17/14
11/8/14
UTL-LAY-162
UTL-LAY-162R1
UTL-LAY-207
UTL-LAY-174
UTL-LAY-188
UTL-LAY-204
UTL-CON-124
10/2/14
10/2/14
10/2/14
UTL-LAY-184
UTL-CON-135
10/2/14
10/2/14
10/2/14
UTL-LAY-164 R1 UTL-CON-134
10/2/14
10/2/14
10/2/14
UTL-LAY-185
11/17/14
9/30/14
10/14/14
10/27/14
6/19/14 UTL-LAY- 98
UTL-CON- 77
UTL-BF- 14
8/13/14 UTL-LAY- 134-R1 UTL-CON- 109A UTL-BF- 53
6/23/14 UTL-LAY- 99
UTL-CON- 78
8/26/14 UTL-LAY-140 R1 UTL-CON-114
UTL-BF- 16
UTL-BF- 52
UTL-CON- 79
UTL-BF- 17
UTL-CON-112-R1 UTL-BF- 47
UTL-CON- 94
UTL-BF- 39R1
UTL-CON- 118
UTL-CON- 117 UTL-BF- 57
UTL-CON- 126
UTL-CON-98
UTL-CON-122A UTL-BF- 37A
UTL-CON-152
UTL-CON-127
UTL-CON-138
UTL-CON-151
UTL-BF-81
UTL-BF-99
UTL-BF- 50
UTL-BF-64
UTL-BF-115
UTL-BF-69
UTL-BF-94
UTL-BF-92
UTL-BF-83R1
MIDDLE
RIGHT
CCC/FQI/SD/08
21+560
CONC PIPE
47
LEFT
450
MIDDLE
RIGHT
CCC/FQI/SD/09
21+620
CONC PIPE
48
LEFT
450
UTL-CON-136
MIDDLE
RIGHT
CCC/FQI/SD
23+400
CONC PIPE
49
LEFT
600
MIDDLE
RIGHT
50
CCC/FQI/EL/21
23+965
200
UPVC
LEFT
MIDDLE
RIGHT
11/4/14
UTL-EXC-55
Page 20
CCC/FQI/Omantel/
02
0+138.348
110
UPVC
CCC/FQI/SL/13
0+130
150
UPVC
CCC/FQI/Omantel/
02
0+140
150
UPVC
CCC/FQI/SL/14
0+415
150
UPVC
CCC/FQI/SL/15
0+054.459
150
UPVC
CCC/FQI/SL/16
150
UPVC
CCC/FQI/SL/17
150
UPVC
2A
Existing
Road front
SOL-3 Ch.
Existing
Road front
SOL-3 Ch.
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
9/4/14
9/16/14
9/28/14
9/17/14
9/30/14
UTL-LAY-159-B
10/18/14 UTL-LAY-167
UTL-CON-132
UTL-CON-128
UTL-BF-78
SERVICE ROAD-01
1
CCC/FQI/SL/07
0+530
150
UPVC
CCC/FQI/SL/06
0+060
150
UPVC
CCC/FQI/SL/08
0+600
100
UPVC
CCC/FQI/OMANTEL
/04
0+472.8
100
UPVC
CCC/FQI/OMANTEL
/05
0+550
100
UPVC
CCC/FQI/OMANTEL
/06
0+648.103
100
UPVC
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
SERVICE ROAD-02
1
CCC/FQI/SL/10
1+050
150
UPVC
CCC/FQI/SL/12
1+530
150
UPVC
150
UPVC
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
SERVICE ROAD-03
1
CCC/FQI/SL/23
0+020
CCC/FQI/SL/24
0+120
CCC/FQI/SL/08
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
Page 21
21+150-21+500
COMPLETED
As of November 2014
LHS
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Subgra de
La yr 9
La yr 8
La yr 7
La yr 6
La yr 5
La yr 4
La yr 3
La yr 2
21+280
21+300
21+320
21+340
21+360
21+380
21+400
21+420
21+440
21+460
21+480
21+500
21+780
21+800
21+820
21+840
21+860
21+880
21+900
21+920
21+940
21+960
21+980
22+000
21+260
21+240
21+220
21+200
21+180
21+160
21+140
21+120
21+100
21+080
21+060
21+040
21+020
21+000
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY
RHS
OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
l a yer 2
l a yer 3
l a yer 4
l a yer 5
l a yer 6
l a yer 7
l a yer 8
l a yer 9
Subgra de
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
21+500-22+000
LHS
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
s ub gra de
La yer 9
La yer 8
La yer 7
La yer 6
La yer 5
La yer 4
La yer 3
La yer 2
RHS
OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
l a yer 2
l a yer 3
l a yer 4
l a yer 5
l a yer 6
l a yer 7
l a yer 8
l a yer 9
s ub gra de
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
21+760
21+740
21+720
21+700
21+680
21+660
21+640
21+620
21+600
21+580
21+560
21+540
21+520
21+500
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY
22+000-22+500
22+500
22+480
22+460
22+440
22+420
22+400
22+380
22+360
22+340
22+320
22+300
22+280
22+260
22+240
22+220
22+200
22+180
22+160
22+140
22+120
22+100
22+080
22+060
22+040
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layer 10
Layer 9
Layer 8
Layer 7
Layer 6
Layer 5
Layer 4
Layer 3
Layer 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY
22+020
RHS
OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
layer 6
layer 7
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
As of November 2014
22+000
LHS
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layr 10
Layr 9
Layr 8
Layr 7
Layr 6
Layr 5
Layr 4
Layr 3
Layr 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY
LHS
COMPLETED
SUBGRADE
22+500-23+000
5th layer of r
layer 15
RHS
OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
layer 6
layer 7
layer 8
layer 9
layer 10
SUB G
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
23+000
22+980
22+960
22+940
22+920
22+900
22+880
22+860
22+840
22+820
22+800
22+780
22+760
22+740
22+720
22+700
22+680
22+660
22+640
22+620
22+600
22+580
22+560
22+540
22+520
22+500
layer 15
5th layer of r
Page 24
As of November 2014
23+400
23+420
23+900
23+920
23+500
23+380
23+880
24+000
23+360
23+860
23+480
23+340
23+840
23+980
23+320
23+820
23+460
23+300
23+800
23+960
23+280
23+780
23+440
23+260
23+760
23+940
23+240
23+740
23+220
23+200
23+180
23+160
23+140
23+120
23+100
23+080
23+060
23+040
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layer 10
Layer 9
Layer 8
Layer 7
Layer 6
Layer 5
Layer 4
Layer 3
Layer 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY
23+020
OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
layer 6
layer 15 of embankment
layer 7
5th layer of rock soil
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
23+000
LHS
RHS
23+000-23+500
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layr 10
Layr 9
5th layer of rock soil
Layr 8
layer 15 of embankment
Layr 7
Layr 6
Layr 5
Layr 4
Layr 3
Layr 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY
LHS
COMPLETED
layer no 28
rock siol layer no 3
23+500-24+000
RHS
OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
layer 6
layer 7
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
23+720
23+700
23+680
23+660
23+640
23+620
23+600
23+580
23+560
23+540
23+520
23+500
Page 25
24+000-24+500
COMPLETED
As of November 2014
LHS
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
La yer 10
La yer 9
La yer 8
La yer 7
La yer 6
La yer 5
La yer 4
La yer 3
La yer 2
24+400
24+420
24+900
24+920
24+500
24+380
24+880
25+000
24+360
24+860
24+480
24+340
24+840
24+980
24+320
24+820
24+460
24+300
24+800
24+960
24+280
24+780
24+440
24+260
24+760
24+940
24+240
24+740
24+220
24+200
24+180
24+160
24+140
24+120
24+100
24+080
24+060
24+040
24+020
24+000
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY
RHS
OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
l a yer 2
l a yer 3
l a yer 4
l a yer 5
l a yer 6
l a yer 7
l a yer 8
l a yer 9
l a yer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
24+500-25+000
LHS
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
La yer 10
La yer 9
La yer 8
La yer 7
La yer 6
La yer 5
La yer 4
La yer 3
La yer 2
24+720
24+700
24+680
24+660
24+640
24+620
24+600
24+580
24+560
24+540
24+520
24+500
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY
RHS
OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
l a yer 2
l a yer 3
l a yer 4
l a yer 5
l a yer 6
l a yer 7
l a yer 8
l a yer 9
l a yer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
Page 26
COMPLETED
25+000-25+500
As of November 2014
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
LHS
Layr 10
Layr 9
Layr 8
Layr 7
Layr 6
Layr 5
Layr 4
Layr 3
Layr 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
RHS
layer 6
layer 7
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
Page 27
25+500
25+480
25+460
25+440
25+420
25+400
25+380
25+360
25+340
25+320
25+300
25+280
25+260
25+240
25+220
25+200
25+180
25+160
25+140
25+120
25+100
25+080
25+060
25+040
25+020
25+000
OGL SURVEY
DESCRIPTION
PAYMENT FOR
THE MONTH OF
GROSS
AMOUNT
(R.O.)
GROSS
NET AMOUNT
AMOUNT
CLAIMED
CLAIMED (R.O.)
(R.O.)
DATE
SUBMITTED
AMOUNT
DATE CERTIFIED
CERTIFIED (R.O.)
AMOUNT
RECEIVED
(R.O.)
DATE
PAYMENT DUE
DATE
PAYMENT
RECEIVED
Dec-13
1,648,225
1,648,225
1,648,225
23-Nov-13
1,648,225
29-Jan-14
1,648,225
6-Feb-14
Jan-14
2,291,277
643,052
514,442
12-Feb-14
514,442
02-Apr-14
513,608
10-Apr-14
Feb&Mar-14
2,808,644
517,367
504,147
06-Apr-14
434,917
03-May-14
414,674
6-Aug-14
Apr-14
3,315,692
507,048
417,900
08-May-14
407,538
05-Jun-14
395,257
6-Aug-14
May-14
4,109,460
793,768
650,802
05-Jun-14
445,708
04-Jul-14
374,172
6-Aug-14
Jun-14
4,293,764
184,304
382,116
15-Jul-14
382,116
16-Jul-14
418,721
9-Sep-14
Jul&Aug-14
5,749,546
1,455,782
1,164,626
14-Sep-14
1,123,023
18-Sep-14
1,123,023
19-Oct-14
Sep-14
6,857,752
1,108,206
928,167
21-Oct-14
928,805
06-Nov-14
Oct-14
10
Nov-14
11
Dec-14
12
Jan-15
13
Feb-15
14
Mar-15
15
Apr-15
16
May-15
17
Jun-15
18
Jul-15
19
Aug-15
20
Sep-15
21
Oct-15
6,857,752
6,210,425
5,884,774
4,887,679
DESCRIPTION
CCC
HIRED
TOTAL
AVAILABLE
AT SITE
COMPRESSOR
AIR COMPRESSOR
GENERATOR
CRANES
2
1
3
-
6
-
DIESEL TANKER
FLAT TRAILER
10
HIAB TRUCK
11
12
TIPPER TRUCKS
11
15
13
14
15
BOBCAT
16
EXCAVATOR
17
18
19
DOZER D9N/D8R
20
TELEHANDLER
21
22
23
DYNAPAC S/ROLLER
24
E/WORK ROLLER
25
MOTOR GRADER
26
27
28
PAVER MACHINE
29
1
-
30
DYNA TRUCK
31
MAINTENANCE TRUCKS
32
33
34
TOYOTA COROLLA/CIVIC/YARIS
35
TOYOTA PICKUP/ISUZU
36
37
38
Total
12
12
13
NISSAN PATHFINDER/X-TRAIL
75
120
45
2014
PLANNED TOTAL PER MONTH
REVISED PLANNED TOTAL PER MONTH
PLANNED CUMULATIVE
ACTUAL TOTAL PER MONTH
ACTUAL CUMULATIVE
2015
Jan-14
Feb-14
Mar-14
Apr-14
May-14
Jun-14
Jul-14
47
68
87
95
93
47
33
33
115
55
88
202
66
154
297
68
222
390
77
299
107
68
458
86
385
110
87
545
88
473
Aug-14 Sep-14
108
95
640
100
573
102
93
733
109
682
Oct-14
Nov-14
Dec-14
Apr-15
May-15 Jun-15
100
107
840
112
794
98
110
950
120
914
87
108
1,058
82
102
1,160
66
87
1,445
53
82
1,527
79
100
1,260
77
98
1,358
41
79
1,606
Jul-15
Aug-15
Sep-15
Oct-15
Total
1500
77
1,683
66
1,749
53
1,802
41
1,843
914
140
112
107
108
102
98
100
108
68
100
98
93
87
88
110
87
82
77
79
82
87
77
86
77
66
53
53
41
47
60
79
66
68
55
66
68
80
41
33
40
20
PROJECT MONTHS
Oct-15
Sep-15
Aug-15
Jul-15
Jun-15
May-15
Apr-15
Mar-15
Feb-15
Jan-15
Dec-14
Nov-14
Oct-14
Sep-14
Aug-14
Jul-14
Jun-14
May-14
Apr-14
Mar-14
Feb-14
Jan-14
No. of EQUIPMENT
100
95
87
100
93
95
107
110
120
102
109
120
NATIONALS
TOTAL
ACTUAL
BUDGET
ACTUAL
BUDGET
ACTUAL
A - MANAGEMENT ***
B - COMMERCIAL STAFF *
C - ENGINEERS
22
24
24
29
1 - SKILLED CRAFTSMEN
144
68
212
2 - SEMI-SKILLED/UNSKILLED
500
53
553
E - ENGINEERING TECHNICIANS
**
706
G - SUBCONTRACTORS
Number of Personnel employed by Subcontractor on Company Work :
44
130
836
2013
Jan-14
34
Feb-14
186
Mar-14
375
Apr-14
586
May-14
791
23
36
50
52
57
11
Oct-14
701
Nov-14
480
Dec-14
381
Jan-15
269
Feb-15
246
Mar-15
307
Apr-15
307
May-15
305
Jun-15
149
Jul-15
Aug-15
Sep-15
Oct-15
Total
8301
565
756
754
750
700
652
667
554
516
387
297
276
365
271
135
92
51
7788
59
59
60
61
63
61
61
57
51
47
44
35
30
63
84
84
83
78
72
74
61
57
43
33
31
40
30
15
10
858
854
854
764
541
442
326
297
354
351
340
179
425
638
848
851
914
627
840
838
833
778
725
741
616
573
429
330
306
406
68
291
715
1,353
2,202
3,052
3,910
4,764
5,618
6,383
6,923
7,365
7,691
7,988
8,342
8,693
9,033
9,212
550
581
603
691
709
756
734
773
767
765
18
26
46
49
54
57
64
69
68
70
71
71
340
391
596
630
657
748
773
825
802
843
838
836
340
731
1,327
1,957
2,614
3,362
4,135
4,960
5,762
6,605
7,443
8,279
150
102
57
7616
663
0
8279
541
764
340
351
297
326
354
425
391
340
400
442
500
179
222
300
200
PROJECT MONTHS
Oct-15
0
Jun-15
Sep-15
0
May-15
Aug-15
0
Apr-15
Jul-15
0
Mar-15
0
Jan-15
Nov-14
Oct-14
Sep-14
Aug-14
Jul-14
Jun-14
May-14
Feb-14
Jan-14
Dec-13
Feb-15 0
0
Dec-14
11
57
100
8651
9,212
836
838
854
843
854
858
825
851
773
848
638
657
Apr-14
748
630
301
862
9215
365
Mar-14
596
Sep-14
793
11
800
No. of Men
Aug-14
794
222
600
Jul-14
799
322
900
700
2015
Jun-14
792
57
802
2014
Dec-13
6
Page 34
Page 35
Page 36
Page 37
MAR No.
Material/ Work
Manufacturer/Supplier/
Subcontractor
MOTC
Renardet
Submitte Remarks
Via Renardet
Comments
Letter
d To
By MOTC
Letter Ref. No.
Submitted
dated
Dated
Date
CCC/FQI/REN/MAS/001
MAS/CCC/FQI/BBC/001
22/12/2013
Renardet
APPROVED
01/04/2014
SO/FQI/CCC/087
07/04/2014
CCC/FQI/REN/MAS/002
MAS/CCC/FQI/GTI/002
Geotechnical Investigation
26/12/2013
Renardet
APPROVED
02/02/2014
SO/FQI/CCC/015
12/02/2014
CCC/FQI/REN/MAS/003
MAS/CCC/FQI/MSE/003
26/12/2013
Renardet
APPROVED
02/02/2014
SO/FQI/CCC/014
12/02/2014
CCC/FQI/REN/MAS/004
MAS/CCC/FQI/PVC/004
UPVC Pipes
Amiantit Oman
26/12/2013
Renardet
APPROVED
09/02/2014
SO/FQI/CCC/019
18/02/2014
CCC/FQI/REN/MAS/005
Amiantit Oman
26/12/2013
Renardet
APPROVED
09/02/2014
SO/FQI/CCC/020
18/02/2014
CCC/FQI/REN/MAS/006
MAS/CCC/FQI/PW/006
Piling Works
APCC LLC
26/01/2014
Renardet
APPROVED
19/02/2014
SO/FQI/CCC/026
25/02/2014
CCC/FQI/REN/MAS/007
MAS/CCC/FQI/MC/007
30/01/2014
Renardet
APPROVED
09/03/2014
SO/FQI/CCC/069
27/03/2014
CCC/FQI/REN/MAS/008
MAS/CCC/FQI/RS/008
Reinforcing Steel
02/02/2014
Renardet
APPROVED
20/03/2014
SO/FQI/CCC/063
24/03/2014
CCC/FQI/REN/MAS/009-1
MAS/CCC/FQI/PT/009-1
22/02/2014
Renardet
APPROVED
27/03/2014
SO/FQI/CCC/089
14/04/2014
CCC/FQI/REN/MAS/009-2
MAS/CCC/FQI/PT/009-2
22/02/2014
Renardet
APPROVED
27/03/2014
SO/FQI/CCC/090
14/04/2014
CCC/FQI/REN/MAS/009-3
MAS/CCC/FQI/PT/009-3
22/02/2014
Renardet
APPROVED
27/03/2014
SO/FQI/CCC/091
14/04/2014
CCC/FQI/REN/MAS/010A-Rev.1
MAS/CCC/FQI/PB/010A-Rev.1
Bridge Pot Bearings
Al Ammar International
07/05/2014
Renardet
Not Approved
---
REN/FQI/CCC/111
13/05/2014
CCC/FQI/REN/MAS/010B
MAS/CCC/FQI/PB/010B
11/05/2014
Renardet
APPROVED
25/05/2014
REN/FQI/CCC/122
31/05/2014
CCC/FQI/REN/MAS/011
Amiantit Oman
22/02/2014
Renardet
APPROVED
09/03/2014
SO/FQI/CCC/038
11/03/2014
CCC/FQI/REN/MAS/012
Amiantit Oman
22/02/2014
Renardet
APPROVED
25/03/2014
SO/FQI/CCC/064
26/03/2014
CCC/FQI/REN/MAS/013
MAS/CCC/FQI/BP/013
02/03/2014
Renardet
Not Approved
20/04/2014
REN/FQI/CCC/105
05/05/2014
CCC/FQI/REN/MAS/013A
MAS/CCC/FQI/BP/013A
17/06/2014
Renardet
APPROVED
03/07/2014
REN/FQI/CCC/146
13/07/2014
Al Ammar International
07/05/2014
Renardet
APPROVED
20/05/2014
REN/FQI/CCC/123
31/05/2014
09/11/2014
Renardet
02/03/2014
Renardet
APPROVED
23/03/2014
SO/FQI/CCC/077
02/04/2014
25/03/2014
Renardet
APPROVED
16/04/2014
REN/FQI/CCC/099
28/04/2014
CCC/FQI/REN/MAS/014A-Rev.1
MAS/CCC/FQI/EJ/014A-Rev.1
Bridge Expansion Joints
MAS/CCC/FQI/EJ/014B
CCC/FQI/REN/MAS/015
MAS/CCC/FQI/RC/015
CCC/FQI/REN/MAS/016 B
Reference No.
MAR No.
Material/ Work
Manufacturer/Supplier/
Subcontractor
MOTC
Renardet
Submitte Remarks
Via Renardet
Comments
Letter
d To
By MOTC
Letter Ref. No.
Submitted
dated
Dated
Date
CCC/FQI/REN/MAS/017
MAS/CCC/FQI/TW/017
Telephone Works
12/03/2014
Renardet
APPROVED
17/03/2014
SO/FQI/CCC/082
03/04/2014
CCC/FQI/REN/MAS/019
MAS/CCC/FQI/EW/019
Electrical Works
22/03/2014
Renardet
APPROVED
29/05/2014
REN/FQI/CCC/131
16/06/2014
CCC/FQI/REN/MAS/020
MAS/CCC/FQI/EC/020
MV & LV Cables
19/03/2014
Renardet
APPROVED
27/03/2014
SO/FQI/CCC/083
03/04/2014
CCC/FQI/REN/MAS/021
MAS/CCC/FQI/PS/021
Package Substation
22/03/2014
Renardet
----
CCC/FQI/REN/MAS/021A
MAS/CCC/FQI/PS/021A
Package Substation
16/09/2014
Renardet
APPROVED
as Noted
3/11/2014
REN/FQI/CCC/202
30/11/2014
CCC/FQI/REN/MAS/022
MAS/CCC/FQI/LL/022
27/03/2014
Renardet
APPROVED
14/08/2014
REN/FQI/CCC/158
17/08/2014
22/05/2014
Renardet
APPROVED
14/08/2014
REN/FQI/CCC/157
17/08/2014
CANCELLED
----
CCC/FQI/REN/MAS/023A
MAS/CCC/FQI/LP/023A
CCC/FQI/REN/MAS/024
MAS/CCC/FQI/FP/024
27/03/2014
Renardet
APPROVED
08/06/2014
REN/FQI/CCC/130
16/06/2014
CCC/FQI/REN/MAS/025
MAS/CCC/FQI/JS/025
27/03/2014
Renardet
APPROVED
16/04/2014
REN/FQI/CCC/100
28/04/2014
---
REN/FQI/CCC/119
27/05/2014
CCC/FQI/REN/MAS/026
MAS/CCC/FQI/GT/026
Geotextile
21/05/2014
Renardet
No meet the
HDS
CCC/FQI/REN/MAS/026A
MAS/CCC/FQI/GT/026A
15/06/2014
Renardet
APPROVED
14/08/2014
REN/FQI/CCC/159
17/08/2014
CCC/FQI/REN/MAS/027
MAS/CCC/FQI/MS/027
Masterseal 915
(formerly known as Masterflow 410 Plus)
10/08/2014
Renardet
APPROVED
as Noted
21/10/2014
REN/FQI/CCC/196
17/11/2014
CCC/FQI/REN/MAS/028
MAS/CCC/FQI/GG/028
17/08/2014
Renardet
APPROVED
25/09/2014
REN/FQI/CCC/192
15/10/2014
CCC/FQI/REN/MAS/030
MAS/CCC/FQI/FLC/030
02/10/2014
Renardet
CCC/FQI/REN/MAS/032
MAS/CCC/FQI/GR/032
Guardrails
29/10/2014
Renardet
CCC/FQI/REN/MAS/033
Oman Plast
03/11/2014
Renardet
15/11/2014
Renardet
Page 41
Page 42
Page 43
Page 44
Page 45
Page 46
Page 47