MOV Check List

DEPT: ELECTRICAL
EQUIPMENT TAG NO(KKS CODE)
MOV NAME
MOTOR FEEDER NO.
Sr.No

:
:
:

Activity Description

Reference Document

1.
1

Check availability of all


documents related to equipment
a.user manual
b.o&m manual
c. on site test report
d. factory test report
e. drawings

Physical verification / as
per specifications

2.
2

Check rating/Type of Enclosure


of Motor

Physical verification / as
per drawing

3.
4

Ensure motor foundation bolts


are tightened properly and no
damage to motor base

Physical verification / as
per drawing

4.
5
5.

Check the freeness of rotor

Physical verification

Ensure the external and internal


Power and control cable
tightness at both ends

Physical verification

6.
7

Ensure Vermin Proofing

Physical verification /as


per vendor document

7.
8

Check no damage to the


terminal box

Physical verification

8.
9

Ensure double earthing of


motor done

Physical verification /as


per specifications

9.
11

Measure the individual phase


winding resistance. All the three
readings shall be approximately
equal
U1-U2:
V1-V2:
W1-W2:

Result
OK/NOT
OK

Date

Checked
By

Remarks

Physical verification /as


per vendor document

10.
Measure the phase insulation
resistance (with 500V insulation
tester) Reading > 5Mohms.

Physical verification

11.
14

Check the power


cable,glanding, lugging and
termination at motor side and
feeder side

Physical verification /as


per specifications

12.
17

Check for proper cable metallic


identification tags for power
cable

Physical verification /as


per specifications /cable
schedule

13.
19

Ensure motor protection


settings are done and enabled as
per recommended settings
( Setting should be recorded)

As per recommended
setting chart

14.
22

Verify the proper rating of


power and control
fuses,MCB,MCCB

Physical verification /as


per drawings

15.
23

Confirm the test conducted on


incoming power cables

As per on site test report


/as per specifications

16.
24

Confirm the incoming supply


voltage level and phase
sequence

Physical verification /as


per specifications

17.
26

Trial run the motor and check


the vibration, noise, heating of
the motor

Physical verification /as


per specifications

18.
27
19.

Check the current in various


phases and record

Physical verification /as


per specifications

Check for any abnormality

Physical verification

20.
28

Approach to MOV should be


proper

Physical verification

Misc. Punch Point :


S.No.

Equipment
No.

Punch Point

Remarks

Checked By :
Verified By