Beruflich Dokumente
Kultur Dokumente
ByBatch No-A2
Roll No. 17-32
To Remove Acidity/Alkalinity
1. Population
2. Purpose
3. Per Capita Demand According To Living Standard
Population Forecasting
Population Forecasting Can Be Done By Following Three
Method's1. Arithmetic Method
2. Geometric Method
3. Incremental Increase Method
1. Arithmetic method
Pn = P0+ nc
Where,
P0 = Initial population
Pn = Population in dh decade
n = No. of decades
c = Average increase
Year
Population
Difference
2001
23.23 lac
2011
36.02 lac
12.79
C=12.79
= 55.20 lac
2. Geometric Method
Pn =Po (1+r/100)
Pn = Po + (r + i)
= 36.02+12.79
= 48.81 lac
Design of Screening
Design Procedure
Assumption
a. Manually cleaned screen
b. Inclination of bars = 30
c. Size of bars = 50 X 6 X 6 mm3
d. Clear spacing between two bars = 10mm
e. Flow velocity of normal screen = 800mm/sec
= 0.8m/s (at peak flow)
Design
Population = 7, 50,000
Avg. rate of water Supply = 135 l/p/d
Avg. rate of water supply per day = 7, 50,000 X 135
= 101.25 MLD
Avg. rate of water supply in cumecs
={7, 50,000 X 135/ 1000 X 24 X 60 X 60 }
= 1.17 Cumec (D.W.F)
Max. Flow = 3 X DWF
= 3.51 Cumecs
Or
3 X 101.25 = 303.75 MLD
[303.75 X 106/1000 X 24 X 60 X 60]
= 3.51 m3/sec.
Now,
Net submerged area of the screen
=[3.51/0.8 ] = 4.4 m2
Submerged area of the screen = 4.4 X Sin 30
= 2.2 m2
Flow velocity in screen = {3.51/2.2}
= 1.6 m/s
Provide 40 bars =
Cross width of screen chamber = 40 X 0.006 (Rod area) + 41 X
0.003 (Gap area)
= .363 m
Liquid depth = Submerged Screen Area/Cross Width of Screen
Chamber
= 2.2 /0.363 =6.06 m
Providing free board = 0.25m
Total depth = 6.06+0.025 = 6.085 m
Now Slope
Hydraulic mean depth (m) = Area /Wetted perimeter
= {6.085 X .363 /(2 X 6.085) + 0.363}
= 0.176 m
Using mannings formula
Settling Tank
Coagulation
Alum Dose
Design criteria for alum dose=Alum required in particular season
is given that
Mansoon = 50mg/l
Winter = 20mg/l
Summer = 05 mg/l
Per day alum required for Summer season = 5 X 10-6 X 7,50,000X 135 X
103 kg/day
= 506.25 X 103 kg/day
For six months = 506.25 X 103 X 180
= 91.135 X 106 kg
No of bags if 1 bag contains 50 kg. Of alum
So no. of bags= {91.135 X 106 }/50 = 1.8225 X 106 bag
If 15 bags in each heap = 121,500 heaps
If area of one heap be 0.2m2 then total area required = 121,500 X 0.2
= 24300 m2
Lime-Soda Process
Design criteria
Design criteria for lime soda process
Molecular weight of
Caco3 = 40+12+48 = 100
Cao = 40+16
= 56
100 kg/l of Caco3 alkalinity required = 56mg/l of Cao
So 110 mg/l of Caco3 alkalinity required = {56 X 110}/100
=61.6 mg/l of cao
Lime required for magnesium
24 mg/l of magnesium required = 56mg/l of cao
1 mg/l of magnesium required = 56/ 24 mg/l of cao
Soda (Na2Co3)
100 mg/l of NCH required = 106 mg/l of No2Co3
161.6 mg/l of NCH required = {106 X 161.6}/100
= 65.59 mg/l of No2Co3
So Total quantity of lime required
= 92.23 X 7,50,000 X 135 X 10-6 kg per day
= 9338.28 kg/day
So for 180 days = 1.68 X 106 kg
If one bag contains 50 kg then no of bags = 33,617.808
~ 33,618 bags
15 bags in each heap so no. of heaps = 2241.2
~ 2242 heaps
If area of one heap is 0.2 m2 then total area required = 448.24
= 449 m2
Total quantity of soda required for 180 days
= 65.59 X 750000 X135 X 180 X10-6
= 6640.98 kg
6}/ 180
= 515666.66 kg/day
So daily no. of bags required = 10313.33 bags
~10314 bags
So no. of heaps = 10314/15
= 687.6
~ 688 heaps
Area required = 688 X 0.2
= 137.6 m2
Clariflocculator
Result
Clean drinking water
THANK YOU!
QUARRIES