Project mission
Project client
Project manager
Ramon Enriquez
Reporting period
27.02.15 31.03.15
Week 4
Control indicators
Control
indicators
Original
Budget
Actual
Cost
Remain
Budget
5,000
1,500
3,500
Planned
Actual
Forecast
Start date
27.02.15
06.03.15
06.03.15
Finish date
29.03.15
27.03.15
Duration
4 weeks
4 weeks
Comments
As of 16 March 2015
Comments
Initial meeting on Feb. 26, 2015. Alignment of online
interview (via Google forms): on-going data gathering
1-1
Management:
Product design (existing menu) 100% complete
Existing service process 30% complete
Current layout 60% complete
Inventory management 50% complete
Maintenance 40% complete
Support required: