Sie sind auf Seite 1von 11

S B EC 2 8 2 3

C O N S TR U C TIO N
M EA S U R EM EN T II

G RO UP 3
P R E-S TR ESS ED
C O N C R ETE
W O RKS

TA K IN G -O FF LIS T
NO

ITEM

UNIT OF
MEASUREME
NT

SMM CLAUSE

Preambles

Precast pre-stress
concrete system

No

F.34/F.17.1

Precast concrete beam

No

F.17.1

Ducting

F.39.1

Vents

No

F.39.3

Tendons

No

F.40.1

Anchorage

No

F.40.2

Filling of anchorage pocket No

F.39.4

Pream bles

Precast pre-stress concrete system


Clause F.34.5

DRAWING NO 9
Notes 5 (ii)

Precast concrete beam


Clause F.17.1 & F.17.2

Ducting
Clause
F.39.1

t and grooves for


PVC sheeting, cement grou
tendons each average size

Refer Drawing No 9
Stressing end anchorage details

Vents
F.39.3

assume

Tendons
F.40.1

Anchorage
F.40.2

Anchorage
F.40.2

Filling ofanchorage pocket


F.39.4