LM2X Pre-Commissioning

PWP14

DC - UPS System Pre-Commissioning

GE ENERGY

GENERAL GUIDELINES
Purpose/Scope
This work package encompasses all

requirements for commissioning, both


mechanically and electrically, the DC/UPS
System.

Precautions
Personnel working with, on, or around the DC/UPS
System should review all applicable safety guidelines
and wear appropriate personal protective equipment.

Special Tooling - Equipment


Volt/ohm meter
Hydrometer
References
P&E 24 VDC Battery System
Vendors manual
Electrical calibration check sheet
Battery Discharge test sheet
Suggested Manpower and Duration
1 I&C Technician
1 Helper
Duration One Day

TASK START DATE

Contractor Representative

TASK COMPLETION DATE

Customer Representative

GE Representative

Printed Name:

Printed Name:

Printed Name:

Printed Title:

Printed Title:

Printed Title:

GE Representative
Signature/Date:

Rev 0

Signature/Date:

Signature/Date:

Page 1 of 2

LM2X Pre-Commissioning
GE ENERGY

DC - UPS System Pre-Commissioning

TASKS
1.

Inspect for visible damage to any cable or termination.

2.

Check for proper installation and cleanliness.

3.

Check for any equipment damage to chargers, batteries and bolts.

4.

Check size and current capacity of supply and load cables.

5.

Ensure battery systems are isolated from load and ventilation is unobstructed.

6.

Perform initial charge according to vendor recommendations.

7.

If solution is added, check battery specific gravity with hydrometer.

8.

Check for system ground faults.

9.

Check functioning of control switches.

10

Check functioning of solenoid valves.

11.

Verify Battery System Discharge Testing Results record has been updated.