LM2500+ G4 LSPT Pre-Commissioning

PWP15

High Voltage System Pre-Commissioning

GE ENERGY

GENERAL GUIDELINES
Purpose/Scope
This work package encompasses all

requirements for commissioning the High


Voltage System.
Precautions
Personnel working with, on, or around the High Voltage
System should observe all applicable electrical safety
guidelines and wear appropriate personal protective
equipment.
GE Energy I&C Representatives do not perform work
on equipment or systems with voltage ratings above 600
VAC. The customer is responsible for providing
qualified individuals or entities capable of installing,
testing and commissioning these systems.

Special Tooling - Equipment


High pot machine
Doble machine
Hot sticks with gloves
References
LM2X O&M manuals
Manufacturers recommended testing
Accepted codes and standards
Cable dielectric test sheet
Dry Type Transformers Megger and Inspection
Bus Duct Checklist
Suggested Manpower and Duration
2 Electricians
1 I&C Technician
1 Helper
Duration One Day

TASK START DATE

Contractor Representative

TASK COMPLETION DATE

Customer Representative

GE Representative

Printed Name:

Printed Name:

Printed Name:

Printed Title:

Printed Title:

Printed Title:

GE Representative
Signature/Date:

Rev 0

Signature/Date:

Signature/Date:

Page 1 of 2

LM2500+ G4 LSPT Pre-Commissioning


GE ENERGY

PWP15

High Voltage System Pre-Commissioning

LINE and NEUTRAL SIDE CUBICLES


1.

Check secondary connections of current transformers.

2.

Perform insulation-resistance test.

3.

Verify ratio of current transformers.

4.

Check polarity of current transformers.

5.

Perform fuse continuity test.

6.

Perform circuit burden and function test.

7.

Check inside cleanliness of neutral and lineside cubicles.

8.

Check primary connections to generator.

9.

Check grounding connections.

10.

Check operation of cubicle heaters and thermostats.

INITIALS

DATE

NOTICE
THE CUSTOMER IS RESPONSIBLE FOR PROVIDING A QUALIFIED PERSON OR
ORGANIZATION TO PERFORM SECONDARY INJECTION TESTING OF THE
GENERATOR PROTECTION SYSTEM.

GENERATOR PROTECTIVE PANEL


11.

Check generator protection panel settings.

12.

Test generator protection panel with secondary injection.

13.

Verify trip signal to AVR and generator breaker.

14.

Verify Insulation Resistance Test Results record has been updated.

Rev 0

INITIALS

DATE

Page 2 of 2