The Culinary institute

of Bahrain

Ahmad Alsharif
Noof AlBinAli

201200112
201101076

Agenda Content
Project Activity
Project Network Diagram
Gantt Chart
PRM
Budgeting

WBS Outline Format

Detailed Activities

Project Activity List


WBS Outline Format
1 Establishing Culinary Institute of Bahrain
1.1 Authorisation and license
1.1.1 Ministry of Industry and
Commerce
1.1.2 Ministry of Health

1.2 Renting the Villa


1.2.1 Browsing Villas
1.2.2 Villa Selection
1.2.3 Rental contract

1.3 Equipment
1.3.1 Sharp Mini Fridges
1.3.2 Braun Blenders
1.3.3 Bosch Dishwasher

Identifying The Detailed Activities


1. Establishing Culinary Institute of Bahrain
1.1Gaining authorization and license
1.1.1Arranging an appointment with
Ministry of Industry and Commerce
1.1.2 Arranging an appointment with
Ministry of Health

1.2 Renting the Villa


1.2.1 Searching for a villa in different
locations
1.2.2 Choosing most suitable villa
1.2.3 Signing the contract of the villa

1.3 Equipment
1.3.1 Purchasing Sharp Mini Fridges
1.3.2 Purchasing Braun Blenders
1.3.3 Purchasing Bosch Dishwasher

Updated Constrains and


Assumptions

Updated WBS

Preparation of Project
Activities
The four steps to conducting
the PND:
1. The preparation of the project
activities.

Identification of Predecessor
and Dependent Activity
2. Identifying the final activity of the project.
3. Identifying the predecessors.

CPM Forward Pass

CPM Backward Pass

Gantt Chart
Developed by Hendry Gantt
The advantages of Gantt Chart:
Increases efficiency and motivation
Effective method of communication

Gantt Chart

Gantt Chart

Personal Resource
Method

PRM/Pert

E = (O + 4M +
P)/6

PERT
Example 2:

Thank you

If a pot is cooking, the friendship will