PRIMAVERA PROJECT PLANNER Tetra Pak Lahore-II

REPORT DATE 26JAN10 RUN NO. 972 RESOURCE LOADING REPORT START DATE 10NOV09 FIN DATE 15MAY10
09:48
DATA DATE 18JAN10 PAGE NO. 1
ALL QUANTITY FOR WEEKS TOTAL USAGE FOR WEEK

9NOV 16NOV 23NOV 30NOV 7DEC 14DEC 21DEC 28DEC 4JAN 11JAN 18JAN 25JAN 1FEB
ACT ID DESC TOTAL 2009 2009 2009 2009 2009 2009 2009 2009 2010 2010 2010 2010 2010

Project Start Phase

TPAKPRO002 PVC Pipe with accessories 40000 40000


TPAKPRO004 Back Boxes 856 285 571
TPAKPRO006 Switches & Switched Sockets 856 856
TPAKPRO008 Junction Box 298 248 50
TPAKPRO010 Cable Ladders 4647 1549 1549 1549
TPAKPRO012 Aluminium Cable Channel 44 6 19 19
TPAKPRO014 Front Line Cable Trunking on Wall 63 5 29 29
TPAKPRO016 Push Buttons 57 19 29 10
TPAKPRO018 Safety Breakers 160 73 88
TPAKPRO020 Dimmers 8 4 4
TPAKPRO022 Patch Panel 3 2 2
TPAKPRO024 Data Outlet 255 116 139
TPAKPRO026 CAT6, 4 pair UTP / Fiber Cable 11544 5772 5772
TPAKPRO028 Patch Chord 457 183 274
TPAKPRO030 U-shaped Bar for Lighting 50x50mm 1944 778 1167
TPAKPRO032 Floor Out Let Box 27 7 20
TPAKPRO034 Photo Electric Relay 5 1 4
TPAKPRO036 Earthing Rods 27 7 20
TPAKPRO038 Hot Galvanised Steel Conductor 525 75 450
TPAKPRO040 Bare Copper Conductor 1263 180 1082
TPAKPRO042 Copper Earthing Bar 7 1 3 3
TPAKPRO044 Street Lighting Poles 8 8
TPAKPRO046 BMS Equipment 67 31 37
TPAKPRO048 Fire Alarm Equipment 264 120 144
TPAKPRO050 Fire Alarm Power & Control Cable 3458 865 2594
TPAKPRO052 FM200 Gas, Cylinder, Nozzles, Solenoid etc 165 41 123
TPAKPRO054 FM200 Piping 2 1 2
TPAKPRO056 Card Access Control System Equipment 77 19 58
TPAKPRO058 Power & Control Cable for Card Access System 1150 164 986
TPAKPRO060 CCTV System Equipment 8 2 6
TPAKPRO062 Power & Control Cable for CCTV 6160 880 5280
TPAKPRO064 GI Pipe 9333 1333 8000
TPAKPSP002 Mobilization 0 0
TPAKPSP004 Start of construction drawings 144 72 72
TPAKPSP006 Start of shop drawings 148 49 49 49
TPAKSUB002 PVC Pipe with accessories 1 1
TPAKSUB004 Back Boxes 1 1
TPAKSUB006 Switches & Switched Sockets 1 1
TPAKSUB008 Junction Box 1 1 1
TPAKSUB010 Cable Ladders
TPAKSUB012 Aluminium Cable Channel 1 1
TPAKSUB014 Front Line Cable Trunking on Wall 1 1
TPAKSUB016 Push Buttons 1 1
TPAKSUB018 Safety Breakers 1 1 0
TPAKSUB020 Dimmers 1 1
TPAKSUB022 Patch Panel 1 1 0

PRIMAVERA PROJECT PLANNER Tetra Pak Lahore-II


REPORT DATE 26JAN10 RUN NO. 972 RESOURCE LOADING REPORT START DATE 10NOV09 FIN DATE 15MAY10
09:48
DATA DATE 18JAN10 PAGE NO. 2
ALL QUANTITY FOR WEEKS TOTAL USAGE FOR WEEK

9NOV 16NOV 23NOV 30NOV 7DEC 14DEC 21DEC 28DEC 4JAN 11JAN 18JAN 25JAN 1FEB
ACT ID DESC TOTAL 2009 2009 2009 2009 2009 2009 2009 2009 2010 2010 2010 2010 2010

Project Start Phase

TPAKSUB024 Data Outlet 1 1 0


TPAKSUB026 CAT6, 4 pair UTP Cable 1 1
TPAKSUB028 Patch Chord 1 1
TPAKSUB030 U-shaped Bar for Lighting 50x50mm 1 1
TPAKSUB032 Floor Out Let Box 1 1
TPAKSUB034 Photo Electric Relay 1 1
TPAKSUB036 Earthing Rods 1 1
TPAKSUB038 Hard Galvanised Steel Conductor 1 1
TPAKSUB040 Bare Copper Conductor 1 1
TPAKSUB042 Copper Earthing Bar 1 1
TPAKSUB044 Street Lighting Poles 1 1
TPAKSUB046 BMS Equipment
TPAKSUB048 Fire Alarm Equipment
TPAKSUB050 Fire Alarm Power & Control Cable 1 1
TPAKSUB052 FM200 Gas, Cylinder, Nozzles, Solenoid etc
TPAKSUB054 FM200 Piping
TPAKSUB056 Card Access Control System Equipment 1 0 1
TPAKSUB058 Power & Control Cable for Card Access System 1 1
TPAKSUB060 CCTV System Equipment
TPAKSUB062 Power & Control Cable for CCTV 1 1
TPAKSUB064 GI Pipe 1 1
TOTAL 10 84057 41998 14092 27967

Production Building-20 Basement

TPAKPBB005 Conduiting 2800 933 1120 747


TPAKPBB010 Installation of Back Boxes 2022 156 933 933
TPAKPBB015 Installation of U-shaped Bar (50x50mm) 236 79 158
TPAKPBB020 Wiring 233 233
TPAKPBB025 Installation of Switches
TPAKPBB030 Installation of Push Buttons
TPAKPBB035 Installation of Dimmers
TPAKPBB040 Installation of Light Fixtures
TPAKPBB045 Testing & Commissioning
TPAKPBB050 Conduiting 3287 967 1160 1160
TPAKPBB055 Installation of Back Boxes 54 27 27
TPAKPBB057 Inst. of Front Line Cable Trunking on wall
TPAKPBB060 Installation of Cable Ladders 311 78 233
TPAKPBB065 Installation of Steel Channels
TPAKPBB070 Installation of Cable Trunking
TPAKPBB075 Wiring
TPAKPBB080 Installation of Sockets
TPAKPBB085 Installation of DB's
TPAKPBB090 Installation of Safety Breakers
TPAKPBB095 Installation UPS
TPAKPBB100 LT Cable Laying
TPAKPBB105 Cable Terminations
TPAKPBB110 Testing & Commissioning

PRIMAVERA PROJECT PLANNER Tetra Pak Lahore-II


REPORT DATE 26JAN10 RUN NO. 972 RESOURCE LOADING REPORT START DATE 10NOV09 FIN DATE 15MAY10
09:48
DATA DATE 18JAN10 PAGE NO. 3
ALL QUANTITY FOR WEEKS TOTAL USAGE FOR WEEK

9NOV 16NOV 23NOV 30NOV 7DEC 14DEC 21DEC 28DEC 4JAN 11JAN 18JAN 25JAN 1FEB
ACT ID DESC TOTAL 2009 2009 2009 2009 2009 2009 2009 2009 2010 2010 2010 2010 2010

Production Building-20 Basement

TPAKPBB115 Conduiting 2800 400 1200 1200


TPAKPBB120 Installation of Back Boxes 10 2 7
TPAKPBB125 Installation of 4-pair RJ45 Outlet
TPAKPBB130 Cable Laying
TPAKPBB135 Installation of Patch Panel
TPAKPBB145 Installation of Fiber Patch Panels
TPAKPBB150 Installation of Patch Chords
TPAKPBB155 Laying of Back Bone Fiber Cables
TPAKPBB160 Termination of Cables
TPAKPBB165 Testing & Commissioning
TPAKPBB255 Installation of Sensors
TPAKPBB260 Installation of Actuators other Devices
TPAKPBB265 Installation of Control Cabinets
TPAKPBB270 Testing & Commissioning
TPAKPBB275 Conduiting 650 130 390 130
TPAKPBB280 Installation of Back Boxes 22 3 19
TPAKPBB285 Cable Laying
TPAKPBB290 Installation of Devices
TPAKPBB300 Termination of Cables
TPAKPBB305 Testing & Commissioning
TOTAL (NEW 12425 2586 4992 4847

Production Building-20 Rooms / Hall

TPAKPBB325 Conduiting 240 240


TPAKPBB330 Cable Laying
TPAKPBB335 Installation of Field Control Panel
TPAKPBB340 Installation of Devices
TPAKPBB345 Testing & Commissioing
TPAKPBG005 Conduiting 1820 140 840 840
TPAKPBG010 Installation of Back Boxes 7 7
TPAKPBG015 Installation of U-shaped Bar (50x50mm) 70 70
TPAKPBG020 Wiring
TPAKPBG025 Installation of Switches
TPAKPBG030 Installation of Push Buttons
TPAKPBG035 Installation of Dimmers
TPAKPBG040 Installation of Light Fixtures
TPAKPBG045 Testing & Commissioning
TPAKPBG050 Conduiting 3770 290 1740 1740
TPAKPBG055 Installation of Back Boxes 54 13 40
TPAKPBG057 Inst. of Front Line Cable Trunking on wall
TPAKPBG060 Installation of Cable Ladders
TPAKPBG065 Installation of Steel Channels
TPAKPBG070 Installation of Cable Trunking
TPAKPBG075 Wiring
TPAKPBG080 Installation of Sockets
TPAKPBG085 Installation of DB's
TPAKPBG090 Installation of Safety Breakers

PRIMAVERA PROJECT PLANNER Tetra Pak Lahore-II


REPORT DATE 26JAN10 RUN NO. 972 RESOURCE LOADING REPORT START DATE 10NOV09 FIN DATE 15MAY10
09:48
DATA DATE 18JAN10 PAGE NO. 4
ALL QUANTITY FOR WEEKS TOTAL USAGE FOR WEEK

9NOV 16NOV 23NOV 30NOV 7DEC 14DEC 21DEC 28DEC 4JAN 11JAN 18JAN 25JAN 1FEB
ACT ID DESC TOTAL 2009 2009 2009 2009 2009 2009 2009 2009 2010 2010 2010 2010 2010

Production Building-20 Rooms / Hall

TPAKPBG095 Installation UPS


TPAKPBG100 LT Cable Laying
TPAKPBG105 Cable Terminations
TPAKPBG110 Testing & Commissioning
TPAKPBG115 Conduiting 1625 125 750 750
TPAKPBG120 Installation of Back Boxes 6 2 5
TPAKPBG125 Installation of 4-pair RJ45 Outlet
TPAKPBG130 Cable Laying 600 600
TPAKPBG135 Installation of Patch Panel
TPAKPBG145 Installation of Fiber Patch Panels
TPAKPBG150 Installation of Patch Chords
TPAKPBG155 Laying of Back Bone Fiber Cables
TPAKPBG160 Termination of Cables
TPAKPBG165 Testing & Commissioning
TPAKPBG170 Installation of Transformers
TPAKPBG175 Installation of Busway Power Distribution
TPAKPBG180 Installation of Flexible Drops @ Transformer
TPAKPBG185 Installation of Main LV Panel
TPAKPBG200 Control Cable Laying
TPAKPBG205 Cable Terminations
TPAKPBG210 Earthing of Equipment
TPAKPBG215 Construction of Earthing Pits
TPAKPBG220 Energization of Electrical System upto LV Panel
TPAKPBG255 Installation of Sensors
TPAKPBG260 Installation of Actuators & other Devices
TPAKPBG265 Installation of Control Cabinets
TPAKPBG270 Testing & Commissioning
TPAKPBG275 Conduiting 650 50 300 300
TPAKPBG280 Installation of Back Boxes
TPAKPBG285 Cable Laying
TPAKPBG287 Air Sampling Tubes / Pipies
TPAKPBG290 Installation of Devices
TPAKPBG295 Installation of Panels
TPAKPBG300 Termination of Cables
TPAKPBG305 Testing & Commissioning
TPAKPBG310 Installation of Schd40 Piping
TPAKPBG315 Installation of Gas Cylinders, Nozzle & Solenoid
TPAKPBG320 Testing & Commissioning
TPAKPBH005 Conduiting 1560 120 720 720
TPAKPBH010 Installation of Back Boxes 7 7
TPAKPBH015 Installation of U-shaped Bar (50x50mm)
TPAKPBH020 Wiring
TPAKPBH025 Installation of Switches
TPAKPBH030 Installation of Push Buttons
TPAKPBH035 Installation of Dimmers
TPAKPBH040 Installation of Light Fixtures
TPAKPBH045 Testing & Commissioning
TPAKPBH050 Conduiting 2600 200 1200 1200

PRIMAVERA PROJECT PLANNER Tetra Pak Lahore-II


REPORT DATE 26JAN10 RUN NO. 972 RESOURCE LOADING REPORT START DATE 10NOV09 FIN DATE 15MAY10
09:48
DATA DATE 18JAN10 PAGE NO. 5
ALL QUANTITY FOR WEEKS TOTAL USAGE FOR WEEK

9NOV 16NOV 23NOV 30NOV 7DEC 14DEC 21DEC 28DEC 4JAN 11JAN 18JAN 25JAN 1FEB
ACT ID DESC TOTAL 2009 2009 2009 2009 2009 2009 2009 2009 2010 2010 2010 2010 2010

Production Building-20 Rooms / Hall

TPAKPBH055 Installation of Back Boxes


TPAKPBH057 Inst. of Front Line Cable Trunking on wall
TPAKPBH060 Installation of Cable Ladders 42 42
TPAKPBH065 Installation of Steel Channels
TPAKPBH070 Installation of Cable Trunking
TPAKPBH075 Wiring
TPAKPBH080 Installation of Sockets
TPAKPBH085 Installation of DB's
TPAKPBH090 Installation of Safety Breakers
TPAKPBH100 LT Cable Laying
TPAKPBH105 Cable Terminations
TPAKPBH110 Testing & Commissioning
TPAKPBH115 Conduiting 1125 375 750
TPAKPBH120 Installation of Back Boxes
TPAKPBH125 Installation of 4-pair RJ45 Outlet
TPAKPBH130 Cable Laying
TPAKPBH150 Installation of Patch Chords
TPAKPBH160 Termination of Cables
TPAKPBH165 Testing & Commissioning
TPAKPBH275 Conduiting
TPAKPBH280 Installation of Back Boxes
TPAKPBH285 Cable Laying
TPAKPBH287 Air Sampling Tubes / Pipes
TPAKPBH290 Installation of Devices
TPAKPBH300 Termination of Cables
TPAKPBH305 Testing & Commissioning
TPAKPBM005 Conduiting 1540 700 840
TPAKPBM010 Installation of Back Boxes 1 1
TPAKPBM015 Installation of U-shaped Bar (50x50mm)
TPAKPBM020 Wiring
TPAKPBM025 Installation of Switches
TPAKPBM030 Installation of Push Buttons
TPAKPBM035 Installation of Dimmers
TPAKPBM040 Installation of Light Fixtures
TPAKPBM045 Testing & Commissioning
TPAKPBM050 Conduiting 3190 1450 1740
TPAKPBM055 Installation of Back Boxes
TPAKPBM057 Inst. of Front Line Cable Trunking on wall 32 32
TPAKPBM060 Installation of Cable Ladders
TPAKPBM065 Installation of Steel Channels
TPAKPBM070 Installation of Cable Trunking
TPAKPBM075 Wiring
TPAKPBM080 Installation of Sockets
TPAKPBM085 Installation of DB's
TPAKPBM090 Installation of Safety Breakers
TPAKPBM095 Installation UPS
TPAKPBM100 LT Cable Laying
TPAKPBM105 Cable Terminations

PRIMAVERA PROJECT PLANNER Tetra Pak Lahore-II

REPORT DATE 26JAN10 RUN NO. 972 RESOURCE LOADING REPORT START DATE 10NOV09 FIN DATE 15MAY10
09:48
DATA DATE 18JAN10 PAGE NO. 6
ALL QUANTITY FOR WEEKS TOTAL USAGE FOR WEEK

9NOV 16NOV 23NOV 30NOV 7DEC 14DEC 21DEC 28DEC 4JAN 11JAN 18JAN 25JAN 1FEB
ACT ID DESC TOTAL 2009 2009 2009 2009 2009 2009 2009 2009 2010 2010 2010 2010 2010

Production Building-20 Rooms / Hall

TPAKPBM110 Testing & Commissioning


TPAKPBM115 Conduiting 2750 1250 1500
TPAKPBM120 Installation of Back Boxes 12 3 9
TPAKPBM125 Installation of 4-pair RJ45 Outlet
TPAKPBM130 Cable Laying
TPAKPBM135 Installation of Patch Panel
TPAKPBM145 Installation of Fiber Patch Panels
TPAKPBM150 Installation of Patch Chords
TPAKPBM155 Laying of Back Bone Fiber Cables
TPAKPBM160 Termination of Cables
TPAKPBM165 Testing & Commissioning
TPAKPBM225 Installation of Hot Galvanized Steel Conductor
TPAKPBM230 Installation of Copper Earthing Bar
TPAKPBM235 Installation of Bare Copper Conductor
TPAKPBM240 Installation of Earthing Rods
TPAKPBM245 Construction of Earthing Pits
TPAKPBM250 Testing & Commissioning
TPAKPBM255 Installation of Sensors
TPAKPBM260 Installation of Actuators & other Devices
TPAKPBM265 Installation of Control Cabinets
TPAKPBM270 Testing & Commissioning
TPAKPBM275 Conduiting 1595 725 870
TPAKPBM280 Installation of Back Boxes
TPAKPBM285 Cable Laying
TPAKPBM287 Air Sampling Tubes / Pipes
TPAKPBM290 Installation of Devices
TPAKPBM295 Installation of Panels
TPAKPBM300 Termination of Cables
TPAKPBM305 Testing & Commissioning
TPAKPBM310 Installation of Schd40 Piping
TPAKPBM315 Installation of Gas Cylinders, Nozzle & Solenoid
TPAKPBM320 Testing & Commissioning
TOTAL (N00 23296 925 10068 12303

Ware House Phase-2, Building-30

TPAKWHB005 Conduiting 2361 694 833 833


TPAKWHB010 Installation of Back Boxes 36 16 20
TPAKWHB015 Installation of U-shaped Bar (50x50mm)
TPAKWHB020 Wiring
TPAKWHB025 Installation of Switches
TPAKWHB035 Installation of Dimmers
TPAKWHB040 Installation of Light Fixtures
TPAKWHB045 Testing & Commissioning
TPAKWHB050 Conduiting 1500 214 643 643
TPAKWHB055 Installation of Back Boxes 26 4 22
TPAKWHB060 Installation of Cable Ladders
TPAKWHB065 Installation of Steel Channels

PRIMAVERA PROJECT PLANNER Tetra Pak Lahore-II

REPORT DATE 26JAN10 RUN NO. 972 RESOURCE LOADING REPORT START DATE 10NOV09 FIN DATE 15MAY10
09:48
DATA DATE 18JAN10 PAGE NO. 7
ALL QUANTITY FOR WEEKS TOTAL USAGE FOR WEEK

9NOV 16NOV 23NOV 30NOV 7DEC 14DEC 21DEC 28DEC 4JAN 11JAN 18JAN 25JAN 1FEB
ACT ID DESC TOTAL 2009 2009 2009 2009 2009 2009 2009 2009 2010 2010 2010 2010 2010

Ware House Phase-2, Building-30

TPAKWHB075 Wiring
TPAKWHB080 Installation of Sockets
TPAKWHB085 Installation of DB's
TPAKWHB090 Installation of Safety Breakers
TPAKWHB100 LT Cable Laying
TPAKWHB105 Cable Terminations
TPAKWHB110 Testing & Commissioning
TPAKWHB115 Conduiting
TPAKWHB120 Installation of Back Boxes
TPAKWHB125 Installation of 4-pair RJ45 Outlet
TPAKWHB130 Cable Laying
TPAKWHB135 Installation of Patch Panel
TPAKWHB150 Installation of Patch Chords
TPAKWHB160 Termination of Cables
TPAKWHB165 Testing & Commissioning
TPAKWHB225 Installation of Hot Galvanized Steel Conductor
TPAKWHB230 Installation of Copper Earthing Bar
TPAKWHB235 Installation of Bare Copper Conductor
TPAKWHB240 Installation of Earthing Rods
TPAKWHB245 Construction of Earthing Pits
TPAKWHB250 Testing & Commissioning
TPAKWHB275 Conduiting
TPAKWHB280 Installation of Back Boxes
TPAKWHB285 Cable Laying
TPAKWHB290 Installation of Devices
TPAKWHB295 Installation of Panels
TPAKWHB300 Termination of Cables
TPAKWHB305 Testing & Commissioning
TOTAL (N01 3923 909 1496 1518

Cooling Plant Building-56

TPAKCPB005 Conduiting 467 67 200 200


TPAKCPB010 Installation of Back Boxes 11 11
TPAKCPB015 Installation of U-shaped Bar (50x50mm)
TPAKCPB020 Wiring
TPAKCPB025 Installation of Switches
TPAKCPB030 Installation of Push Buttons
TPAKCPB040 Installation of Light Fixtures
TPAKCPB045 Testing & Commissioning
TPAKCPB050 Conduiting 143 143
TPAKCPB055 Installation of Back Boxes
TPAKCPB060 Installation of Cable Ladders
TPAKCPB075 Wiring
TPAKCPB080 Installation of Sockets
TPAKCPB085 Installation of DB's
TPAKCPB090 Installation of Safety Breakers
TPAKCPB100 LT Cable Laying

PRIMAVERA PROJECT PLANNER Tetra Pak Lahore-II

REPORT DATE 26JAN10 RUN NO. 972 RESOURCE LOADING REPORT START DATE 10NOV09 FIN DATE 15MAY10
09:48
DATA DATE 18JAN10 PAGE NO. 8
ALL QUANTITY FOR WEEKS TOTAL USAGE FOR WEEK

9NOV 16NOV 23NOV 30NOV 7DEC 14DEC 21DEC 28DEC 4JAN 11JAN 18JAN 25JAN 1FEB
ACT ID DESC TOTAL 2009 2009 2009 2009 2009 2009 2009 2009 2010 2010 2010 2010 2010

Cooling Plant Building-56

TPAKCPB105 Cable Terminations


TPAKCPB110 Testing & Commissioning
TPAKCPB115 Conduiting
TPAKCPB120 Installation of Back Boxes
TPAKCPB125 Installation of 4-pair RJ45 Outlet
TPAKCPB130 Cable Laying
TPAKCPB160 Termination of Cables
TPAKCPB165 Testing & Commissioning
TPAKCPB170 Installation of Transformers
TPAKCPB175 Installation of Busway Power Distribution
TPAKCPB180 Installation of Flexible Drops @ Transformer
TPAKCPB190 11KV termination Kit
TPAKCPB200 Control Cable Laying
TPAKCPB210 Earthing of Equipment
TPAKCPB215 Construction of Earthing Pits
TPAKCPB220 Testing & Commissioning
TPAKCPB225 Installation of Hot Galvanized Steel Conductor
TPAKCPB230 Installation of Copper Earthing Bar
TPAKCPB235 Installation of Bare Copper Conductor
TPAKCPB240 Installation of Earthing Rods
TPAKCPB245 Construction of Earthing Pits
TPAKCPB250 Testing & Commissioning
TPAKCPB255 Installation of Sensors
TPAKCPB260 Installation of Actuators & other Devices
TPAKCPB265 Installation of Control Cabinets
TPAKCPB270 Testing & Commissioning
TPAKCPB275 Conduiting 200 200
TPAKCPB280 Installation of Back Boxes
TPAKCPB285 Cable Laying
TPAKCPB290 Installation of Devices
TPAKCPB295 Installation of Panels
TPAKCPB300 Termination of Cables
TPAKCPB305 Testing & Commissioning
TPAKCPB310 Installation of Schd40 Piping
TPAKCPB315 Installation of Gas Cylinders, Nozzle & Solenoid
TPAKCPB320 Testing & Commissioning
TOTAL 30 821 67 200 554

Support Building-40

TPAKSPB005 Conduiting
TPAKSPB010 Installation of Back Boxes / Junction Boxes
TPAKSPB015 Installation of U-shaped Bar (50x50mm)
TPAKSPB020 Wiring
TPAKSPB025 Installation of Switches
TPAKSPB030 Installation of Push Buttons
TPAKSPB040 Installation of Light Fixtures
TPAKSPB045 Testing & Commissioning

PRIMAVERA PROJECT PLANNER Tetra Pak Lahore-II

REPORT DATE 26JAN10 RUN NO. 972 RESOURCE LOADING REPORT START DATE 10NOV09 FIN DATE 15MAY10
09:48
DATA DATE 18JAN10 PAGE NO. 9
ALL QUANTITY FOR WEEKS TOTAL USAGE FOR WEEK

9NOV 16NOV 23NOV 30NOV 7DEC 14DEC 21DEC 28DEC 4JAN 11JAN 18JAN 25JAN 1FEB
ACT ID DESC TOTAL 2009 2009 2009 2009 2009 2009 2009 2009 2010 2010 2010 2010 2010

Support Building-40

TPAKSPB050 Conduiting 933 133 400 400


TPAKSPB055 Installation of Back Boxes
TPAKSPB060 Installation of Cable Ladders
TPAKSPB075 Wiring
TPAKSPB080 Installation of Sockets
TPAKSPB085 Installation of DB's
TPAKSPB090 Installation of Safety Breakers
TPAKSPB100 LT Cable Laying
TPAKSPB105 Cable Terminations
TPAKSPB110 Testing & Commissioning
TPAKSPB115 Conduiting
TPAKSPB120 Installation of Back Boxes
TPAKSPB125 Installation of 4-pair RJ45 Outlet
TPAKSPB130 Cable Laying
TPAKSPB160 Termination of Cables
TPAKSPB165 Testing & Commissioning
TPAKSPB225 Installation of Hot Galvanized Steel Conductor
TPAKSPB230 Installation of Copper Earthing Bar
TPAKSPB235 Installation of Bare Copper Conductor
TPAKSPB240 Installation of Earthing Rods
TPAKSPB245 Construction of Earthing Pits
TPAKSPB250 Testing & Commissioning
TPAKSPB255 Installation of Sensors
TPAKSPB260 Installation of Actuators
TPAKSPB265 Installation of Control Cabinets
TPAKSPB270 Testing & Commissioning
TPAKSPB275 Conduiting 200 57 143
TPAKSPB280 Installation of Back Boxes 60 9 51
TPAKSPB285 Cable Laying
TPAKSPB290 Installation of Devices
TPAKSPB295 Installation of Panels
TPAKSPB300 Termination of Cables
TPAKSPB305 Testing & Commissioning
TOTAL (N02 1193 190 551 451

Pump House-52

TPAKPHB005 Conduiting
TPAKPHB010 Installation of Back Boxes
TPAKPHB020 Wiring
TPAKPHB025 Installation of Switches
TPAKPHB040 Installation of Light Fixtures
TPAKPHB045 Testing & Commissioning
TPAKPHB085 Installation of DB's
TPAKPHB090 Installation of Safety Breakers
TPAKPHB100 LT Cable Laying
TPAKPHB105 Cable Terminations
TPAKPHB110 Testing & Commissioning

PRIMAVERA PROJECT PLANNER Tetra Pak Lahore-II

REPORT DATE 26JAN10 RUN NO. 972 RESOURCE LOADING REPORT START DATE 10NOV09 FIN DATE 15MAY10
09:48
DATA DATE 18JAN10 PAGE NO. 10
ALL QUANTITY FOR WEEKS TOTAL USAGE FOR WEEK

9NOV 16NOV 23NOV 30NOV 7DEC 14DEC 21DEC 28DEC 4JAN 11JAN 18JAN 25JAN 1FEB
ACT ID DESC TOTAL 2009 2009 2009 2009 2009 2009 2009 2009 2010 2010 2010 2010 2010

Pump House-52

TPAKPHB225 Installation of Hot Galvanized Steel Conductor


TPAKPHB230 Installation of Copper Earthing Bar
TPAKPHB235 Installation of Bare Copper Conductor
TPAKPHB240 Installation of Earthing Rods
TPAKPHB245 Construction of Earthing Pits
TPAKPHB250 Testing & Commissioning
TPAKPHB255 Installation of Sensors
TPAKPHB260 Installation of Actuators
TPAKPHB265 Installation of Control Cabinets
TPAKPHB270 Testing & Commissioning
TPAKPHB275 Conduiting 50 33 17
TPAKPHB280 Installation of Back Boxes 10 7 3
TPAKPHB285 Cable Laying
TPAKPHB290 Installation of Devices
TPAKPHB300 Termination of Cables
TPAKPHB305 Testing & Commissioning
TOTAL (N03 60 33 23 3

Solvent Building-53

TPAKSVB005 Conduiting
TPAKSVB010 Installation of Back Boxes
TPAKSVB020 Wiring
TPAKSVB025 Installation of Switches
TPAKSVB040 Installation of Light Fixtures
TPAKSVB045 Testing & Commissioning
TPAKSVB225 Installation of Hot Galvanized Steel Conductor
TPAKSVB230 Installation of Copper Earthing Bar
TPAKSVB235 Installation of Bare Copper Conductor
TPAKSVB240 Installation of Earthing Rods
TPAKSVB245 Construction of Earthing Pits
TPAKSVB250 Testing & Commissioning
TPAKSVB275 Conduiting 175 70 105
TPAKSVB280 Installation of Back Boxes 30 6 24
TPAKSVB285 Cable Laying
TPAKSVB290 Installation of Devices
TPAKSVB300 Termination of Cables
TPAKSVB305 Testing & Commissioning
TOTAL (N04 205 70 111 24

Guard House 51A & 51B

TPAKGDH005 Conduiting 30 30
TPAKGDH010 Installation of Back Boxes 5 5
TPAKGDH020 Wiring 30 30
TPAKGDH025 Installation of Switches 5 5
TPAKGDH035 Installation of Dimmers
TPAKGDH040 Installation of Light Fixtures

PRIMAVERA PROJECT PLANNER Tetra Pak Lahore-II

REPORT DATE 26JAN10 RUN NO. 972 RESOURCE LOADING REPORT START DATE 10NOV09 FIN DATE 15MAY10
09:48
DATA DATE 18JAN10 PAGE NO. 11
ALL QUANTITY FOR WEEKS TOTAL USAGE FOR WEEK

9NOV 16NOV 23NOV 30NOV 7DEC 14DEC 21DEC 28DEC 4JAN 11JAN 18JAN 25JAN 1FEB
ACT ID DESC TOTAL 2009 2009 2009 2009 2009 2009 2009 2009 2010 2010 2010 2010 2010

Guard House 51A & 51B

TPAKGDH045 Testing & Commissioning


TPAKGDH050 Conduiting 150 100 50
TPAKGDH055 Installation of Back Boxes 14 9 5
TPAKGDH057 Inst. of Front Line Cable Trunking on wall
TPAKGDH065 Installation of Steel Channels
TPAKGDH075 Wiring
TPAKGDH080 Installation of Sockets
TPAKGDH085 Installation of DBs
TPAKGDH100 LT Cable Laying
TPAKGDH105 Cable Terminations
TPAKGDH110 Testing & Commissioning
TPAKGDH115 Conduiting 75 75
TPAKGDH120 Installation of Back Boxes 5 5
TPAKGDH125 Installation of 4-pair RJ45 Outlet
TPAKGDH130 Cable Laying
TPAKGDH140 Installation of RJ45 Jack Patch Panel Sytems
TPAKGDH150 Installation of Patch Chords
TPAKGDH160 Termination of Cables
TPAKGDH165 Testing & Commissioning
TPAKGDH225 Installation of Hot Galvanized Steel Conductor
TPAKGDH230 Installation of Copper Earthing Bar
TPAKGDH235 Installation of Bare Copper Conductor
TPAKGDH240 Installation of Earthing Rods
TPAKGDH245 Construction of Earthing Pits
TPAKGDH250 Testing & Commissioning
TPAKGDH275 Conduiting 35 35
TPAKGDH280 Installation of Back Boxes 19 19
TPAKGDH285 Cable Laying
TPAKGDH290 Installation of Devices
TPAKGDH295 Installation of Panels
TPAKGDH300 Termination of Cables
TPAKGDH305 Testing & Commissioning
TOTAL (N05 368 240 88 40

Power Plant-57

TPAKPPB295 Installation of Panels


TOTAL (N06

Multiuse Building-59

TPAKMUB295 Installation of Panels


TOTAL (N07

Office Building-60

TPAKOFB295 Installation of Panels

PRIMAVERA PROJECT PLANNER Tetra Pak Lahore-II

REPORT DATE 26JAN10 RUN NO. 972 RESOURCE LOADING REPORT START DATE 10NOV09 FIN DATE 15MAY10
09:48
DATA DATE 18JAN10 PAGE NO. 12
ALL QUANTITY FOR WEEKS TOTAL USAGE FOR WEEK

9NOV 16NOV 23NOV 30NOV 7DEC 14DEC 21DEC 28DEC 4JAN 11JAN 18JAN 25JAN 1FEB
ACT ID DESC TOTAL 2009 2009 2009 2009 2009 2009 2009 2009 2010 2010 2010 2010 2010

Office Building-60

TOTAL (N08

Site Plan

TPAKSPL005 Excavation, Laying & Backfilling of Conduiting 3664 1078 1293 1293
TPAKSPL010 Construction of Manholes 23 7 8 8
TPAKSPL015 Installation of Cable Ladders
TPAKSPL018 Installation Bare Copper Conductor
TPAKSPL020 LT Cable Laying
TPAKSPL025 HT Cable Laying
TPAKSPL035 Installation of Light Poles with RCC base
TPAKSPL040 Installation of Light Fixtures
TPAKSPL042 Fire Alarm System Cable Laying
TPAKSPL044 Termination of Cables
TPAKSPL045 Testing & Commissioning
TPAKSPL350 Conduiting 4667 667 2000 2000
TPAKSPL355 Control & Power Cable Laying
TPAKSPL360 Installation of Monitors
TPAKSPL365 Installation of Digital Video Recordes
TPAKSPL370 Power Supply
TPAKSPL375 Installation of Cameras
TPAKSPL380 Installation of Infrared Intrusion Detectors
TPAKSPL390 Testing & Commissioning
TOTAL (N09 8353 1751 3301 3301

Project Completion Phase

TPAKPRC001 Miscellaneous Work


TPAKPRC002 Commissioning & Testing
TOTAL 50

REPORT TOTAL 134702 48768 34924 51010