Sie sind auf Seite 1von 9

Testing: Unit Testing / User Manual

Module: Production Planning

ENVIRONMENT
SYSTEM

: SAP R/3 ECC 6.0

CLIENT

: 200

UNIT TESTING SCENARIO


SCENARIO NUMBER

DESCRIPTION

: Production Version

PREPARED BY
NAME

DATE

TEAM

: Production Planning

APPROVED & TESTED BY


NAME

: Nanhe Babu (PwC)

DATE

TEAM

: Production Planning

Page 1 of 9

Testing: Unit Testing / User Manual

Module: Production Planning

1. Transaction Code/ Path

Menu Path

Logistics Materials Management Material Master Material Create


(General) MM02 Change - Immediately

T.Code

MM02

2. Input Data
1. Enter the Input parameters, which need to be given by the user during the testing of this
scenario.
2. Input the value for the fields and then if required, copy the screen shot of the input screen
after the table.
3. If the scenario has multiple screen inputs, which needs to be processed, repeat the step 2
for every screen.
2.1

Input Screen Name Change Material: Initial Screen

Production version is maintained in MRP 4 & Work Scheduling View. Below is the screen
shot

Page 2 of 9

Testing: Unit Testing / User Manual

Module: Production Planning

After selection of the views, provide the plant in which the material is maintained

Description of the
Field
Material
Plant

Press on
2.2

Nature of the
Field
Mandatory
Mandatory

Value of the Field


For which changes needs to be done
Against which Plant

Tab

Input Screen Name Change Material: Overview

Screen 1:

Click

button

Following window is displayed

Page 3 of 9

Testing: Unit Testing / User Manual

Module: Production Planning

For first time entry or creation of version click


2.3

Input Screen Name Create Production version

Page 4 of 9

Testing: Unit Testing / User Manual

Module: Production Planning

Description of the
Field
Version ID
Version Text
Valid from
Valid to
Detailed planning
Task List Type

Nature of the
Field
Mandatory
Mandatory
Mandatory
Mandatory

4 Char
40 Char
Date
Date

Optional

N Routing

Group

Optional

Group Counter

Optional

Alternative BOM

Optional

BOM usage

Optional

Value of the Field

Defined in Routing
Master
Defined in Routing
Master
Defined in BOM
Master
Defined in BOM
Master
Page 5 of 9

Testing: Unit Testing / User Manual

Module: Production Planning

Planning data
Group & Group counter are keys defined in the Routing Master for the Material in the Plant.
Use the same Group & Group Counter so that the Routing is selected in this Production
version '1000'
Bill of Material
Alternative BOM if there are no. of BOMs then specify which BOM needs to selected.
BOM usage depending upon usage, one can specify for particular Production version,
which usage needs to be used.
After entry of Routing & BOM details, we can check for errors, if any.
Please click
Check for Status

Page 6 of 9

Testing: Unit Testing / User Manual

Module: Production Planning

Status
The above status shows for error in relation to Routing & BOM details provided, such Group /
group counter / Alternative BOM / BOM usage.
Depending upon the correction in the above field, again do check
Following message will be displayed

The status will be updated as


After creation of production version, following screen will be displayed

Page 7 of 9

Testing: Unit Testing / User Manual

Module: Production Planning

After Clicking 'Continue', following screen will be displayed in Material Master.


If one needs to create one more production version for the same material, in material master, in
MRP 4 / Work Scheduling view, click on ProdVersions. Production version Overview screen is
displayed, click
It will again take to production version creation window.
One can have 'n' no of production versions for a material.

3. PROCESS GUIDELINES
While creation of Production order, one can specify which Production version needs to be selected,
so that correct BOM & Routing is assigned to Order
Follow procedure defined:In order creation screen, go to Functions Read PP master data

If there are no of production versions available, press F4

Page 8 of 9

Testing: Unit Testing / User Manual

Module: Production Planning

Select the appropriate Production version, in same order creation screen, Master data tab, the
selected version will appear.

Page 9 of 9