Sie sind auf Seite 1von 20

DOCUMENT SUBMISSION STATUS: FC

30/03/11

ISSUED FOR CONSTRUCTION

T.V.CUONG

D.V.HIEU

P.N.QUANG

11/03/11

ISSUED FOR CONSTRUCTION

T.V.CUONG

D.V.HIEU

N.H.QUAN

26/01/11

ISSUED FOR APPROVAL

T.V.CUONG

N.V.BIEN

P.N.QUANG

D
C
B

10/01/11
18/11/10
29/10/10

ISSUED FOR APPROVAL


ISSUED FOR APPROVAL
ISSUED FOR APPROVAL

REV

DATE

PREP.

CHKD

APPN

DESCRIPTION

OWNER

OWNERS CONSULTANT

POYRY ENERGY LTD


VIETNAM OIL AND GAS GROUP (PVN)
EPC CONTRACTOR

EPC CONTRACTORS CONSULTANT

VIETNAM MACHINERY
INSTALLATION CORPORATION (LILAMA)
PROJECT TITLE

VUNG ANG 1 THERMAL POWER PLANT 2 x 600MW


PACKAGE: M8
CONTRACT No.

222010/ LILAMA-LISEMCO

DRAWING TITLE:

steel structure FABRICATION PROCEDURE


SUB-CONTRACTOR

HAIPHONG EQUIPMENT MANUFACTURE AND


SHIPBUILDING CO.LTD, (LISEMCO)
DOCUMENT No.VA1-LSC-00100-QA-M8-TPD-0006

FUNCTION

NAME

SIGN

PREPARED

TO VIET CUONG

30/03/11

CHECKED

DAM VAN HIEU

30/03/11

APPROVED

PHAM NGOC QUANG

30/03/11
SCALE

DATE

REV. 1

Hai phong equipment manufacture and


shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8

Mar. 30th, 2011


Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 1/19

Steel structure Fabrication


Procedure

project

Vung Ang1 Thermal Power Plant

Item

COAL HANDLING SYSTEM M8

location

Ky Loi commune - Ky Anh District-Ha Tinh province

Steel structure Fabrication Procedure

Hai phong equipment manufacture and


shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8

Mar. 30th, 2011


Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 2/19

Index

No

Title

Page

Chapter 1: General Introduction.

Chapter 2: Fabrication procedure.

Chapter 3: Fabrication method.

Chapter 1: General Introduction


I. General Introduction
1. Executing Organization Chart (As shown in page 4).
Hai phong Equipment Manufacture and Shipbuilding CO., LTD
a. Responsibilities and rights
Hai Phong Equipment Manufacture and Shipbuilding CO., LTD is a member
company belonging to Vietnam Machinery Installation Corporation (LILAMA).
With its big site plan (8ha), modern equipment, and the teams of experienced
engineer and equipped with knowledge and new executing technologies, a large
number of workers as well as skillful workers, Hai phong Equipment
Manufacture and Shipbuilding CO., LTD is responsible for providing materials
and installation of equipment for Vung Ang 1 thermal power plant 2x600 MWCoal handling plant M-lot 2
All steel structure will be fabricated in factory of Lisemco in Hai Phong to
ensure quality, error and convenience for installation process of steel structure.
The whole process of structural steel fabrication, company will carry out by
itself equipment and staff member.

Steel structure Fabrication Procedure

Hai phong equipment manufacture and


shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8

Mar. 30th, 2011


Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 3/19

b. The director of project


Full name: Nguyen Hong Quan
Position:

Project Director

Tel

: 031-3522496

Fax

: 031-3850120.

E-mail

: vungangpj@lisemco.com.vn

2. Inspection unit- quality control


Inspection unit quality control belonging to quality control Department which
is an independent organization with in manufacturing units operating under the
leaderships of the parent company, is responsible for quality control, checking to
ensure the steps of manufacturing technology and installation implemented
seriously for quality assurance of construction.

Steel structure Fabrication Procedure

Hai phong equipment manufacture and


shipbuilding company limited

Mar. 30th, 2011


Rev: 1

Vung Ang 1 Thermal Power Plant

Code: VA1-LSC-00100-QA-M8-TPD-0006

Ky Loi commune, Ky Anh district, Ha Tinh province

Page: 4/19

ITEM: COAL HANDLING SYSTEM M8

ORGANIZATION CHART FOR LOT-M8


VUNG ANG 1.THERMALPOWER PLANT PROJECT

LILAMA PMB
LISEMCO ltd,.
GENERAL DIRECTOR
Mr. TRAN VIET KHANH
Email: lisemco@hn.vnn.vn

PROJECT MANAGER
Mr.NGUYEN HONG QUAN
E-mail: quanhn.nd37@gmail.com
psb.lisemco@vnn.vn

PROJECT COORDINATOR
Mr. TO VIET CUONG
Mobi: 01696815187
E-mail: vietcuong.lisemco@gmail.com

DEPUTY PROJECT MANAGER


& SITE MANAGER

MANUFACTURING MANAGER
Mr. NGUYEN VAN BIEN
Mobi: 0989126635
E-mail: Bienlisemco@yahoo.com.vn

Mr. PHAM NGOC QUANG


E-mail: ngocquang32id@gmail.com

RECEIVING EQUIPMENT
AND HAND MANAGER

OFFICE MANAGER

Mr. NGUYEN DINH QUYNH

Ms.TRUONG THI HUONG


Ms.HO THI KHANH HOA

SAFETY&SECURITY MANAGER

QC/QA PRJ. MANAGER

Mr.PHAN VAN HUNG


Ms: NGUYEN THI LAM

Mr. VU VAN QUANG


Mr MAI HUY CUONG
Mr.VU DUC THANH

TECHNICAL MANAGEMENT

MATERIALS MANAGEMENT

Mr. DO XUAN DUNG


Mobi: 0982592029

Mr. BUI DUC THIET


Mobi: 0904828298

SAFETY&SE MANAGEMENT

QC/QA PRJ. MANAGEMENT

Mr. PHAM VAN TUYEN


Mobi: 0934692591
E-mail: tuyen.lisemco@gmail.com

Mr. NGUYEN QUANG VINH

WORK SHOP SUPERVISOR


ENGINEERS

ELECTRICIAN+
INSULATING+
COMMISSONING
TEAM 01
PEPLE 19

STEEL STRUCTURE
+MECHANIC
TEAM-02
PEPLE 30

PAINTER
TEAM - 01
PEPLE 8

WELDER
TEAM - 01
PEPLE 15

WORK-SHOP No1

WORK-SHOP No2

Mr NGUYEN VAN DOANH

Mr. NGUYEN VAN HUNG

MECHANIC AND WELDER


TEAM - 25

MECHANIC AND WELDER


TEAM - 25

STEEL STRUCTURE
TEAM 02
PEOPLE 35

STEEL STRUCTURE
TEAM 02
PEOPLE 35

PAINTING
PACKING & SHIPPMENT
Mr.DOANVAN HA

PAINTING
TEAM-01
PEOPLE 12

PACKING & SHIPPMENT


TEAM -01
PEOPLE 06

Date of isuue: Otc 12th, 2010

Inspection unit- quality control has rights of suspending activities which not
comply with procedures , and has risk of bad influence on quality manufactured
products as well as installation leading bad effects on construction quality.
Inspection shall followed he details in lines with the approved ITP which are
completed by LILAMA.
Steel structure Fabrication Procedure

Hai phong equipment manufacture and


shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8

Mar. 30th, 2011


Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 5/19

3. Reference:
- Specification of the project.
- FLS General Workshop instructions.
- Document No. VA1-LI-00100-M-G1-ITP-0002 INSPECTION AND TEST
PLAN FOR STEEL STRUCTURE SHOP FABRICATION
- Document No. VA1-LI-00100-QA-G1-ITP-0001 INSPECTION AND TEST
PLAN FOR PAINTING
- Standard: DIN.
4. Shop, fabrication teams
Fabrication teams are responsible for executing construction in accordance with
design, quality assurance and work progress and directly carry out at shop in
lisemco.
In case of unexpected problems in construction process exceeds the capacity of
fabrication units. They can request related parts supporting technology,
eqiupment, manpower. All the requirements of fabrication groups must be
presented in writen form system of Lisemco (in case the customers do not have
special

requiremetns). These requirements are given Economy-Technology

Department, Lisemco. Economy-Technology Department must have answer in


writen form within 24 hours.
II. Objects, scopes and references.
1. Objects
The process of structural steel fabrication is to give a manufacturing scientific
plan, strict inspection system, ensuring quality to meet the quality control system
ISO 9001 : 2000 which company Lisemco is applying, also satifies the
customers requirements about product quality and construction progress.
2. Application scope

Steel structure Fabrication Procedure

Hai phong equipment manufacture and


shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8

Mar. 30th, 2011


Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 6/19

This process is applied to fabrication equipment and manufacturing of steel


structure.
3. References
Shop drawings, related technical documents and standards.
The technical standards are given by Owner.
4. Fabrication chart and inspection
o

Content of
Work

Implementation unit Inspection criteria Evaluation


criteria

-Check
input -Executing technology
materials.
-Material officer.
-Quality control
- Supervisor party A

- Original
- Number
- Dimension
- Visual inspection

Inspection tools Report form

Certificate
o- Certificates
Manufacturer.
- Comparing orders
- Accroding to Tape-measure,
order
caliper
- No wrapping, - By visual.
rust, blistery.

- Marking and - Workers


- Dimension, beveled - Design drawing. - Tape-measure.
cutting
- Executing technology angel.
-Inspections
- Quality control
- External insepction.
-Straightening - Workers
Dimension, - Design drawing Welding
joint
-Detailed
-Executing technology. straightness,
welding and error.
checking
tapeassembly
- Quality control.
joint prepared.
measure,
control
- External inspection.
-Inspection
wire,
- Assembly.
- Workers
- Straightness, square, -Design drawing - Meter, tape for
Assembly - Executing technogy
dimension...
and error
inspection of square
inspection
- Quality control
angle.
- Supervisor party A
- Welding beam, - Welder with valid - According to welding
pillar, accessory. certificates.
procedure system.
External -Executing technology. Welding
joint - According to - By visual, welding
inspection.
- Quality control.
surrounding.
welding procedure. joint tape inspection.
Checking
by
-Nondestructive - Supervisor party A.
-External inspection.
Tecnical testing.
- Subcontractor.
- Cheking welding joint requirement
of ultrasonic.
construction.
inside.
- Welders.
According
to - Accroding to - Grinder, welding
Repairingdefects - Subcontractor.
inspection results.
quality
machine.
.
-External inspection.
requirement
of - By visual, checking
-Checking and
- Cheking welding joint construction.
by ultrasonic.
fixing.
inside.
- Sanding blast, - Manufacturing unit.
paint.
- Executing technology
- Quality control.
Painting - Supervisor party A.
inspection.

- Surfaces preparation - According to - Checking by visual.


and paint.
technical
- Checking by gauge
- Painting inspection. requirement (see for
measuring
painting
thickness of paint.
procedure).

III. Construction organization design.


1 -Bases on the construction design.
- Basing on technical standards of designer.
- Basing on tecnical design document of construction.
Steel structure Fabrication Procedure

Hai phong equipment manufacture and


shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8

Mar. 30th, 2011


Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 7/19

- Basing on real condition of construction plan and construction work


quantity.
- Basing on rate canculating document for construction and construction
organization.
- Basing on material capacity, machinery, and manpower.
2 - Construction organization design.
Construction organization is very important task ensuring fast construction
process and achieved the best effect. The contractor will be responsible for this
task. They carry out the supported work like working platform, storage, yards of
materials gathered as well as products, water allocation system for construction.
The construction work quantity is mainly organized as follows:
In the shop of company
+ Fabrication of steel structure.
+ Cleaning, painting steel structure.
In the construction process, contractor is in full compliance with technical
procedures, rules and regulations of acceptance in accordance with designers
standard and owners requirement.
Basing on construction plan, the contractor carries out to clean ground, prepare
assembling platform, machinery for construction work.

Steel structure Fabrication Procedure

Hai phong equipment manufacture and


shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8

Mar. 30th, 2011


Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 8/19

Chapter 2: Fabrication procedure


Material receiving

Returni

Inspectio
False
Delivery for units

Cutting

Repairing

Inspectio
False
Tack welding

Repairing

Inspectio
False
Finish welding

Repairing

Inspectio
False
Assembly

Repairing

Inspectio
False

acceptance report
blast cleaning

Repairing

Inspectio
False

acceptance report
finish painting

Repairing

Inspectio
False

acceptance report
Packing
Complete payment
document
Steel structure Fabrication Procedure

Hai phong equipment manufacture and


shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8

Mar. 30th, 2011


Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 9/19

Chapter 3: Fabricating methods


I. Check input materials of Work.
According to designers requirements, Contractor supply types of material
having clear origin, attaching material certificate.
Material inspection made as below requirement:
- Check material certificate of origin.
- Standard geometrical size: check by tape-measure, caliper
- Surface: convex, concave, void, crack, warping
- Technical characteristics of material:
- Physical-mechanical properties of steel: sampling, testing and certificating.
- Welding material properties according approved WPS & PQR.
- Components, properties of other materials.
- Control, inspection process of input materials for works following to designers
standard and the below diagram:
Materials
Delivering to company

HaiPhong equipment
Manufacture and
Shipbuilding CO., LTD

material department
inspection, correlation,storage
certificate of quality, quantity,
weight

Gim st cng ty (QC)


check size, type of materials...

A partys supervisor
inspect steel tag,
...
type of materials

Type of steel for fabrication works consist of:


1. Steel plate according to project standard, or appropriate
2. Steel shape according to project standard, or appropriate
3. Materials service for fabrication: welding material, painting material, the
other auxiliary materials

Steel structure Fabrication Procedure

Hai phong equipment manufacture and


shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8

Mar. 30th, 2011


Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 10/19

Entire above materials strictly controlled and monitored according to materials


summary tables including detailed data. After be imported to Company, the
materials delivered to executing units for fabrication
II. Construction ground preparing.
In order to service for fabrication as well as asembly all parts in Company,
Company perform arrangement the construction ground at units. Assemblying
platform for fabrication and inspection carefully prepared achieving standard
surface.
III. Products fabricating
Common fabricating steps:
Step 1: The parts shall be marked and cut according to marking and cutting dwgs
and design dwgs.
Marking and cutting according to the diagram shall be performed by assembly
group, parts marked and cut on the platform under the control, monitoring of
shop, group engineering staff, and QC of Company. The parts must be checked
the size, cleaness, beveled angle, hole welding, ... according to the Project
standard by Companys QC during marking and cutting process, when QC find
out that the parts achieving requirement, they shall be moved to the next stage.
Step 2: Assembly parts
After cutting, the parts shall be moved to assembling areas where assembling
work made by assembling group. Companys QC inspects the size, joint
clearance, tack welding, reinforced measure against deformationwhen these
achieve the Projects standard, the parts moved to the welding stage.
Before welding, structure should be inspected according to FIT-UP
INSPECTION FOR WELDING No: VA1-QCF-M-15 in document No: VA1-LI00100-M-GI-ITP-0002 (INSPECTION AND TEST PLAN FOR STEEL
STRUCTURE SHOP FABRICATION).

Steel structure Fabrication Procedure

Hai phong equipment manufacture and


shipbuilding company limited

Mar. 30th, 2011


Rev: 1

Vung Ang 1 Thermal Power Plant

Code: VA1-LSC-00100-QA-M8-TPD-0006

Ky Loi commune, Ky Anh district, Ha Tinh province

Page: 11/19

ITEM: COAL HANDLING SYSTEM M8

Step 3: Welding
Welded connection executed according to welding procedure (WPS) which
Lisemco submitted to the Owner and supervisors, consultants. This procedure
performed by welders having valid certificates. Overall welding process strictly
inspected by welding QC about welding materials, the welders, quality of
welding jointsso as to restrict welding defects and avoid failures at the
beginning of the stage. All welding joints checked 100% external form
according to technical requirement of the project. The defected welding joints
shall be carried out to prepare following to repairing welding joint procedure
during inspection. .
Size of the parts inspected after finish welding ensuring to be in allowable
tolerance of the Project.
The weld should be inspection according to WELDING VISUAL RECORDS
No:

VA1-QCF-M-14

in

document

No:

VA1-LI-00100-M-GI-ITP-0002

(INSPECTION AND TEST PLAN FOR STEEL STRUCTURE SHOP


FABRICATION).
After welding, the struture should be inspection according to STEEL
STRUCTURE FABRICATION FINAL INSPECTION REPORT No: VA1QCF-M-013

in

the

document

No:

VA1-LI-00100-M-G1-ITP-0002

(INSPECTION AND TEST PLAN FOR STEEL STRUCTURE SHOP


FABRICATION) before painting.
All of taking-over form made according to Projects requirements and after the
parties ( the Owner, TVGS, LISEMCO contractor) have finished signing the
acceptance certificate, then move to painting stage
*) Welding procedure specification, process welding, and NDT for welding
work of reclaimers, stackers, unloaders, and towers shall be completely followed
FLS General Workshop Instructions which was issued.

Steel structure Fabrication Procedure

Hai phong equipment manufacture and


shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8

Mar. 30th, 2011


Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 12/19

Step 4: Painting.
After checking according to STEEL STRUCTURE INSPECTION RECORD
BEFORE PAINTING No: VA1-QCF-M-012 in the document No: VA1-LI00100-M-G1-ITP-0002 (INSPECTION AND TEST PLAN FOR STEEL
STRUCTURE SHOP FABRICATION), products will be cleaned by abrasive
grain for blasting, boring machine for hard-to-handle, ensuring technical
requirements of this project. The quality control is ensured to move painting
stage and final acceptance for packing.
All the acceptance forms are made according to project requirements and after
the parties signed acceptance report to move the working stage, its time for
packing.
Due to design of parts with its own features, the construction part of work like
scraper, piler, unloader, tower of project have some different features.
III.1.The fabrication of Reclaimer: the fabrication of each unit
The cutting stage must carry out on CNC machine. After cutting, the plates are
connected together according to working drawing and finish welding for
connecting plates; check Nondectructive testing (NDT). If these results are
achived, conduct the assembly beam. The platform is used for assembly beam,
for example:

Steel structure Fabrication Procedure

Hai phong equipment manufacture and


shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8

Steel structure Fabrication Procedure

Mar. 30th, 2011


Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 13/19

Hai phong equipment manufacture and


shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8

Mar. 30th, 2011


Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 14/19

During beam assembling in three-sided process, each unit is connected


completely according to design set, bracing to avoid welding deformation; and
then weld the whole beam inside. After checking by visual about welding of
beam inside, cap the plate to control the dimension of the beam and conduct to
welding finish. Checking by visual the overall dimensions of welding seam; the
flatness of beam sides according to the length design of beam. If these results
achieved, conduct Nondestructive testing and acceptance to move for cleaning
and painting.

Steel structure Fabrication Procedure

Hai phong equipment manufacture and


shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8

Mar. 30th, 2011


Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 15/19

Roller support is made with the same way.


Dump bailer supports in fabricating procedure and inspection are skidded on the
platform.

Dump bailer will be fabricated and accepted in accordance with gauge.


All units connecting together which are difficult to clean and paint, after
finishing, they are cleaned and painted with anticorrosive paint before
assembling.
The remains of scraper will be completely fabricated, accepted and finish
painting at the LISEMCO Contractors shop, and then conduct to assembly and
install.
III.2. The fabrication of Stacker: the fabrication of each unit
The cutting stage must carry out on CNC machine. After cutting, the plates are
connected together according to working drawing and finish welding for
Steel structure Fabrication Procedure

Hai phong equipment manufacture and


shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8

Mar. 30th, 2011


Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 16/19

connecting plates; check Nondestructive testing (NDT). If these results are


achieved, conduct the assembly beam. The platform is used for assembly beam.
During beam assembling in three-sided process, each unit is connected
completely according to design set, bracing to avoid welding deformation; and
then weld the whole beam inside. After checking by visual about welding of
beam inside, cap the plate to control the dimension of the beam and conduct to
welding finish. Checking by visual the overall dimensions of welding seam; the
flatness of beam sides according to the length design of beam. If these results
achieved, conduct Nondestructive testing and acceptance to move for cleaning
and painting.

Roller support is made with the same way.

Band conveyor support in fabricating process and inspection is performed on


gauge support.

Steel structure Fabrication Procedure

Hai phong equipment manufacture and


shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8

Mar. 30th, 2011


Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 17/19

All units connecting together which are difficult to clean and paint, after
finishing, they are cleaned and painted with anticorrosive paint before
assembling.
The remains of Stacker will be completely fabricated, accepted and finish
painting at the LISEMCO Contractors shop, and then conduct to assembly and
install.

III.3. Unloader machine fabrication : execution with each unit.


Cutting stage performed by CNC machine. After pleteting , the plates connected
according to fabrication drawing and finishing welded, if NDT checking is
achieved, beam assembling will be implemented. Platform used for this work
During beam assembling in three-sided process, each unit is connected
completely according to design set, bracing to avoid welding deformation; and
then weld the whole beam inside. After checking by visual about welding of
beam inside, cap the plate to control the dimension of the beam and conduct to
welding finish. Checking by visual the overall dimensions of welding seam; the
flatness of beam sides according to the length design of beam. If these results
achieved, conduct Nondestructive testing and acceptance to move for cleaning
and painting.
Steel structure Fabrication Procedure

Hai phong equipment manufacture and


shipbuilding company limited
Vung Ang 1 Thermal Power Plant
Ky Loi commune, Ky Anh district, Ha Tinh province
ITEM: COAL HANDLING SYSTEM M8

Mar. 30th, 2011


Rev: 1
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 18/19

The remains of unloader will be made with the same way and cleaned and
painted at the LISEMCO Contractors shop, and then conduct to pack and
install.

III.4. Fabrication for direction turning tower: Because tower structure


coupling bolt, so fabrication process is process which fabricate loose parts , after
that testing assembly each unit.

+ The pillar, beam are cut by steel shape (I,V...) with right dimension, marked by
arrows directing position of gusset plate, attaching gusset plate after drilling
hole.

+ Bracing is performed with cutting dimension, attached gusset plate, welding,


dimension inspection after welding and flatness, then move to clean and paint.

Steel structure Fabrication Procedure

Hai phong equipment manufacture and


shipbuilding company limited

Mar. 30th, 2011


Rev: 1

Vung Ang 1 Thermal Power Plant

Code: VA1-LSC-00100-QA-M8-TPD-0006

Ky Loi commune, Ky Anh district, Ha Tinh province

Page: 19/19

ITEM: COAL HANDLING SYSTEM M8

+ Platform and ladder are fabricated with the same way.

+ After loose materials are checked, cleaned and painted.


+ Packing and installing in construction site.
IV. Inspection of dimensional tolerance
+ Measurement testing, tolerance in dimension acceptance inspection according
to project standards (Document no:VA1-FLS-00100-M-M2-DST-6040)
TOLERANCES

>0.5

30

120

315

1000

2000

4000

8000

12000 16000 20000

12000 16000 20000

30

120

315

1000

2000

4000

8000

0.1

0.1

0.2

0.3

0.5

0.8

1.2

0.2

0.5

0.2

0.5

10

12

14

=3

0.8

1.2

3 < S = 50

1.5

1.5

2.5

3.5

50 < S = 100

2.5

2.5

3.5

4.5

L=10

10<L=50

50<L=120

120<L=315

1.8/100 mm

0.9/100 mm

0.6/100 mm

0.3/100 mm

2.6/100 mm

1.5/100 mm

0.7/100 mm

0.4/100 mm

5.2/100 mm

3.5/100 mm

1.8/100 mm

1.3/100 mm

Steel structure Fabrication Procedure

315<L=1000

L>1000

0.9/100 mm

0.6/100 mm

16

Das könnte Ihnen auch gefallen