Beruflich Dokumente
Kultur Dokumente
30/03/11
T.V.CUONG
D.V.HIEU
P.N.QUANG
11/03/11
T.V.CUONG
D.V.HIEU
N.H.QUAN
26/01/11
T.V.CUONG
N.V.BIEN
P.N.QUANG
D
C
B
10/01/11
18/11/10
29/10/10
REV
DATE
PREP.
CHKD
APPN
DESCRIPTION
OWNER
OWNERS CONSULTANT
VIETNAM MACHINERY
INSTALLATION CORPORATION (LILAMA)
PROJECT TITLE
222010/ LILAMA-LISEMCO
DRAWING TITLE:
FUNCTION
NAME
SIGN
PREPARED
TO VIET CUONG
30/03/11
CHECKED
30/03/11
APPROVED
30/03/11
SCALE
DATE
REV. 1
project
Item
location
Index
No
Title
Page
Project Director
Tel
: 031-3522496
Fax
: 031-3850120.
: vungangpj@lisemco.com.vn
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 4/19
LILAMA PMB
LISEMCO ltd,.
GENERAL DIRECTOR
Mr. TRAN VIET KHANH
Email: lisemco@hn.vnn.vn
PROJECT MANAGER
Mr.NGUYEN HONG QUAN
E-mail: quanhn.nd37@gmail.com
psb.lisemco@vnn.vn
PROJECT COORDINATOR
Mr. TO VIET CUONG
Mobi: 01696815187
E-mail: vietcuong.lisemco@gmail.com
MANUFACTURING MANAGER
Mr. NGUYEN VAN BIEN
Mobi: 0989126635
E-mail: Bienlisemco@yahoo.com.vn
RECEIVING EQUIPMENT
AND HAND MANAGER
OFFICE MANAGER
SAFETY&SECURITY MANAGER
TECHNICAL MANAGEMENT
MATERIALS MANAGEMENT
SAFETY&SE MANAGEMENT
ELECTRICIAN+
INSULATING+
COMMISSONING
TEAM 01
PEPLE 19
STEEL STRUCTURE
+MECHANIC
TEAM-02
PEPLE 30
PAINTER
TEAM - 01
PEPLE 8
WELDER
TEAM - 01
PEPLE 15
WORK-SHOP No1
WORK-SHOP No2
STEEL STRUCTURE
TEAM 02
PEOPLE 35
STEEL STRUCTURE
TEAM 02
PEOPLE 35
PAINTING
PACKING & SHIPPMENT
Mr.DOANVAN HA
PAINTING
TEAM-01
PEOPLE 12
Inspection unit- quality control has rights of suspending activities which not
comply with procedures , and has risk of bad influence on quality manufactured
products as well as installation leading bad effects on construction quality.
Inspection shall followed he details in lines with the approved ITP which are
completed by LILAMA.
Steel structure Fabrication Procedure
3. Reference:
- Specification of the project.
- FLS General Workshop instructions.
- Document No. VA1-LI-00100-M-G1-ITP-0002 INSPECTION AND TEST
PLAN FOR STEEL STRUCTURE SHOP FABRICATION
- Document No. VA1-LI-00100-QA-G1-ITP-0001 INSPECTION AND TEST
PLAN FOR PAINTING
- Standard: DIN.
4. Shop, fabrication teams
Fabrication teams are responsible for executing construction in accordance with
design, quality assurance and work progress and directly carry out at shop in
lisemco.
In case of unexpected problems in construction process exceeds the capacity of
fabrication units. They can request related parts supporting technology,
eqiupment, manpower. All the requirements of fabrication groups must be
presented in writen form system of Lisemco (in case the customers do not have
special
Content of
Work
-Check
input -Executing technology
materials.
-Material officer.
-Quality control
- Supervisor party A
- Original
- Number
- Dimension
- Visual inspection
Certificate
o- Certificates
Manufacturer.
- Comparing orders
- Accroding to Tape-measure,
order
caliper
- No wrapping, - By visual.
rust, blistery.
Returni
Inspectio
False
Delivery for units
Cutting
Repairing
Inspectio
False
Tack welding
Repairing
Inspectio
False
Finish welding
Repairing
Inspectio
False
Assembly
Repairing
Inspectio
False
acceptance report
blast cleaning
Repairing
Inspectio
False
acceptance report
finish painting
Repairing
Inspectio
False
acceptance report
Packing
Complete payment
document
Steel structure Fabrication Procedure
HaiPhong equipment
Manufacture and
Shipbuilding CO., LTD
material department
inspection, correlation,storage
certificate of quality, quantity,
weight
A partys supervisor
inspect steel tag,
...
type of materials
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 11/19
Step 3: Welding
Welded connection executed according to welding procedure (WPS) which
Lisemco submitted to the Owner and supervisors, consultants. This procedure
performed by welders having valid certificates. Overall welding process strictly
inspected by welding QC about welding materials, the welders, quality of
welding jointsso as to restrict welding defects and avoid failures at the
beginning of the stage. All welding joints checked 100% external form
according to technical requirement of the project. The defected welding joints
shall be carried out to prepare following to repairing welding joint procedure
during inspection. .
Size of the parts inspected after finish welding ensuring to be in allowable
tolerance of the Project.
The weld should be inspection according to WELDING VISUAL RECORDS
No:
VA1-QCF-M-14
in
document
No:
VA1-LI-00100-M-GI-ITP-0002
in
the
document
No:
VA1-LI-00100-M-G1-ITP-0002
Step 4: Painting.
After checking according to STEEL STRUCTURE INSPECTION RECORD
BEFORE PAINTING No: VA1-QCF-M-012 in the document No: VA1-LI00100-M-G1-ITP-0002 (INSPECTION AND TEST PLAN FOR STEEL
STRUCTURE SHOP FABRICATION), products will be cleaned by abrasive
grain for blasting, boring machine for hard-to-handle, ensuring technical
requirements of this project. The quality control is ensured to move painting
stage and final acceptance for packing.
All the acceptance forms are made according to project requirements and after
the parties signed acceptance report to move the working stage, its time for
packing.
Due to design of parts with its own features, the construction part of work like
scraper, piler, unloader, tower of project have some different features.
III.1.The fabrication of Reclaimer: the fabrication of each unit
The cutting stage must carry out on CNC machine. After cutting, the plates are
connected together according to working drawing and finish welding for
connecting plates; check Nondectructive testing (NDT). If these results are
achived, conduct the assembly beam. The platform is used for assembly beam,
for example:
All units connecting together which are difficult to clean and paint, after
finishing, they are cleaned and painted with anticorrosive paint before
assembling.
The remains of Stacker will be completely fabricated, accepted and finish
painting at the LISEMCO Contractors shop, and then conduct to assembly and
install.
The remains of unloader will be made with the same way and cleaned and
painted at the LISEMCO Contractors shop, and then conduct to pack and
install.
+ The pillar, beam are cut by steel shape (I,V...) with right dimension, marked by
arrows directing position of gusset plate, attaching gusset plate after drilling
hole.
Code: VA1-LSC-00100-QA-M8-TPD-0006
Page: 19/19
>0.5
30
120
315
1000
2000
4000
8000
30
120
315
1000
2000
4000
8000
0.1
0.1
0.2
0.3
0.5
0.8
1.2
0.2
0.5
0.2
0.5
10
12
14
=3
0.8
1.2
3 < S = 50
1.5
1.5
2.5
3.5
50 < S = 100
2.5
2.5
3.5
4.5
L=10
10<L=50
50<L=120
120<L=315
1.8/100 mm
0.9/100 mm
0.6/100 mm
0.3/100 mm
2.6/100 mm
1.5/100 mm
0.7/100 mm
0.4/100 mm
5.2/100 mm
3.5/100 mm
1.8/100 mm
1.3/100 mm
315<L=1000
L>1000
0.9/100 mm
0.6/100 mm
16