Sie sind auf Seite 1von 4

Activity ID

Activity Name

PRIVATE CONCENTRATE HAUL ROAD - SMCV Rev B (

Original Start
Duration
298 26-Jun-14
Solid Rock
)

GENERAL
A8370 Indirect Labor and Supervision

PMA AND CIRA PERMITS - SMI


A8320 PMA AND CIRA PERMITS

PRELIMINAR WORKS
A8330 PRE - MOBILIZATION EQUIPMENT
A8360 TOPOGRAFHY AND GEOREFERENCING

CONTRACT MILESTONES

Finish

Schedule 90 days
Budgeted Labor
Units
26

July 2014
03

10

August 2014
17

25-Jun-15

61391

274 24-Jul-14

25-Jun-15

274 24-Jul-14

25-Jun-15

26-Jun-14

26-Jun-14, PMA AND CIRA PERMITS - SMI

PMA AND CIRA PERMITS, 26-Jun-14

0 26-Jun-14
0 26-Jun-14

24

31

07

14

24 26-Jun-14

23-Jul-14

19 26-Jun-14

17-Jul-14

5 18-Jul-14

23-Jul-14

0 24-Jul-14

24-Jul-14

24-Jul-14, CONTRACT MILESTONES

START CONSTRUCTION, 24-Jul-14

September 2014
21

28

REFERENCES MILESTONE

12-Sep-14

0 24-Jul-14

24-Jul-14

24-Jul-14, AREA 1.- PRIVATE CONCENTRATE HAUL ROAD

Start Task 1 - PCHR, 24-Jul-14

A1020
Star Task 2 - LA JOYA TRANSFER STATION

AREA 3.- LA JOYA STATION BY PASS


AREA 4.- MATARANI - PANAMERICANA CROSSING

0 24-Jul-14
0 12-Sep-14

12-Sep-14

12-Sep-14, REFEREN

12-Sep-14, AREA 2.- I

0 12-Sep-14

Star Task 2 - LA JOYA

82 26-Jun-14

02-Oct-14

61391

82 26-Jun-14

02-Oct-14

61083

51
51
33
4

24-Jul-14
24-Jul-14
24-Jul-14
24-Jul-14

24-Sep-14
24-Sep-14
03-Sep-14
30-Jul-14

31671
21444
1368
149

Excavation Km 15+000 - km 16+000

6 31-Jul-14

06-Aug-14

285

Excavation Km 16+000 - km 17+000

6 07-Aug-14

13-Aug-14

256

Excavation Km 17+000 - km 18+000

3 14-Aug-14

16-Aug-14

150

Excavation Km 18+000 - km 19+000

1 18-Aug-14

18-Aug-14

14

Excavation Km 19+000 - km 20+000

2 19-Aug-14

20-Aug-14

103

Excavation Km 20+000 - km 21+000

1 21-Aug-14

21-Aug-14

53

Excavation Km 21+000 - km 22+000

1 22-Aug-14

22-Aug-14

23

Excavation Km 22+000 - km 23+000

2 23-Aug-14

25-Aug-14

165

Excavation Km 23+000 - km 24+000

2 26-Aug-14

27-Aug-14

66

Excavation Km 24+000 - km 25+000

1 28-Aug-14

28-Aug-14

Excavation Km 25+000 - km 26+000

1 28-Aug-14

29-Aug-14

69

Excavation Km 25+000 - km 26+000

Excavation Km 26+000 - km 27+000

1 29-Aug-14

29-Aug-14

Excavation Km 26+000 - km 27+000

Excavation Km 27+000 - km 28+000

1 01-Sep-14

01-Sep-14

Excavation Km 28+000 - km 29+000

1 01-Sep-14

02-Sep-14

11

Excavation Km 28+000 - km 29+000

Excavation Km 29+000 - km 30+000

1 02-Sep-14

02-Sep-14

Excavation Km 29+000 - km 30+000

Excavation Km 30+000 - km 30+560

1 03-Sep-14

03-Sep-14

17

47 31-Jul-14
24-Sep-14
ENBANKMENT CONFORMATION WITH OWN MATERIAL -AND OWN MATERIAL
TERRA SQUARE
Enbakmebnt - Own Material Km 14+000 - km 15+000
6 31-Jul-14
06-Aug-14

15976
1474

CONSTRUCTIONS
AREA 1 .- PRIVATE CONCENTRATE HAUL ROAD ( PCHR )
EARTHWORK
WORK FRONT II ( KM 14+000 - KM 30+560. )
EXCAVATION FOR EARTHWORKS LOOSE MATERIAL AND LOOSE ROCK
Excavation Km 14+000 - km 15+000

25

TOPOGRAFHY AND GEOREFERENCING

0 24-Jul-14

A1000
Start Task 1 - PCHR

18

PRE - MOBILIZATION EQUIPMENT

40 24-Jul-14

AREA 2.- IMPROVEMENT TO LA JOYA TRANSFER STATION

11

23-Jul-14, PRELIMINAR WORKS

A8310 START CONSTRUCTION

AREA 1.- PRIVATE CONCENTRATE HAUL ROAD

04

2
2
03-Sep-14, EXCAVATION FOR EART
Excavation Km 14+000 - km 15+000
Excavation Km 15+000 - km 16+000
Excavation Km 16+000 - km 17+000
Excavation Km 17+000 - km 18+000
Excavation Km 18+000 - km 19+000
Excavation Km 19+000 - km 20+000
Excavation Km 20+000 - km 21+000
Excavation Km 21+000 - km 22+000
Excavation Km 22+000 - km 23+000
Excavation Km 23+000 - km 24+000
Excavation Km 24+000 - km 25+000

Excavation Km 27+000 - km 28+000

Excavation Km 30+000 - km 30+560


2
Enbakmebnt - Own Material Km 14+000 - km 15+000

Enbakmebnt - Own Material Km 15+000 - km 16+000 ( 1 )

6 07-Aug-14

13-Aug-14

331

Enbakmebnt - Own Material Km 15+000 - km 16+000 ( 2 )

6 14-Aug-14

20-Aug-14

332

Enbakmebnt - Own Material Km 15+000 - km 16+000 ( 1 )

Enbakmebnt - Own Material Km 16+000 - km 17+000 ( 1 )

6 07-Aug-14

13-Aug-14

689

Enbakmebnt - Own Material Km 16+000 - km 17+000 ( 2 )

6 14-Aug-14

20-Aug-14

199

Enbakmebnt - Own Material Km 16+000 - km 17+000 ( 2 )

Enbakmebnt - Own Material Km 17+000 - km 18+000 ( 1 )

6 14-Aug-14

20-Aug-14

1546

Enbakmebnt - Own Material Km 17+000 - km 18+000 ( 1 )

Enbakmebnt - Own Material Km 17+000 - km 18+000 ( 2 )

6 21-Aug-14

27-Aug-14

1688

Enbakmebnt - Own Material Km 17+000 - km 18+000 ( 2 )

Enbakmebnt - Own Material Km 18+000 - km 19+000 ( 1 )

6 21-Aug-14

27-Aug-14

1534

Enbakmebnt - Own Material Km 18+000 - km 19+000 ( 1 )

Enbakmebnt - Own Material Km 18+000 - km 19+000 ( 2 )

5 28-Aug-14

03-Sep-14

1534

Enbakmebnt - Own Material Km 15+000 - km 16+000 ( 2 )


Enbakmebnt - Own Material Km 16+000 - km 17+000 ( 1 )

Enbakmebnt - Own Material Km 18+0

Page 1 of 4

Activity ID

Activity Name

Original Start

Finish

Schedule 90 days
Budgeted Labor
Units
26

July 2014
03

10

August 2014
17

24

31

07

14

September 2014
21

28

04

11

18

25

Enbakmebnt - Own Material Km 19+000 - km 20+000

Duration
6 04-Sep-14

10-Sep-14

2598

Enbakmebnt - Own Material Km 20+000 - km 21+000

3 11-Sep-14

13-Sep-14

269

Enbakmebnt - Own

Enbakmebnt - Own Material Km 21+000 - km 22+000 ( 1 )

3 15-Sep-14

17-Sep-14

1891

Enbakmebnt

Enbakmebnt - Own Material Km 21+000 - km 22+000 ( 2 )

6 18-Sep-14

24-Sep-14

Enbakmebnt - Own Mater

1891

11 21-Aug-14
03-Sep-14
ENBANKMENT CONFORMATION WITH BORROWED MATERIAL AND CRUSHED
STONE - TERRA
SQUARE
Enbankment with borrowed material Km 15+000 - Km 16+000
6 21-Aug-14 27-Aug-14

2772
1565

03-Sep-14, ENBANKMENT CONFOR


Enbankment with borrowed material Km 15+000 -

Enbankment with borrowed material Km 16+000 - Km 17+000

03-Sep-14

1207

41 31-Jul-14
PROF. AND COMPAC. OF SUB-GRADE IN ZONES-CUT (ROAD, IMPROVEMENT,
CROSSING 17-Sep-14
Prof. and compac. of sub-grade Km 14+000 - km 15+000
6 31-Jul-14
06-Aug-14

1328
280

5 28-Aug-14

Enbankment with borrowed material


17-Sep-14, P
Prof. and compac. of sub-grade Km 14+000 - km 15+000

Prof. and compac. of sub-grade Km 15+000 - km 16+000 ( 1 )

6 07-Aug-14

13-Aug-14

292

Prof. and compac. of sub-grade Km 15+000 - km 16+000 ( 2 )

6 14-Aug-14

20-Aug-14

193

Prof. and compac. of sub-grade Km 16+000 - km 17+000

6 21-Aug-14

27-Aug-14

208

Prof. and compac. of sub-grade Km 17+000 - km 18+000

3 28-Aug-14

01-Sep-14

131

Prof. and compac. of sub-grade Km 17+0

Prof. and compac. of sub-grade Km 18+000 - km 19+000

2 02-Sep-14

03-Sep-14

28

Prof. and compac. of sub-grade Km 1

Prof. and compac. of sub-grade Km 19+000 - km 20+000

6 04-Sep-14

10-Sep-14

116

Prof. and compac. of sub-

Prof. and compac. of sub-grade Km 20+000 - km 21+000

6 11-Sep-14

17-Sep-14

80

Prof. and com

24-Sep-14
24-Sep-14
30-Jul-14

10226
2983
345

2
2

WORK FRONT I ( KM 00+000 - KM 14+000 )


EXCAVATION FOR EARTHWORKS LOOSE MATERIAL AND LOOSE ROCK
Excavation Km 14+000 - Km 13+000

51 24-Jul-14
51 24-Jul-14
4 24-Jul-14

Prof. and compac. of sub-grade Km 15+000 - km 16+000 ( 1 )


Prof. and compac. of sub-grade Km 15+000 - km 16+000 ( 2 )
Prof. and compac. of sub-grade Km 16+000 - km 17+000

Excavation Km 14+000 - Km 13+000

Excavation Km 13+000 - Km 12+000 ( 1 )

6 07-Aug-14

13-Aug-14

219

Excavation Km 13+000 - Km 12+000 ( 2 )

6 14-Aug-14

20-Aug-14

219

Excavation Km 13+000 - Km 12+000 ( 1 )

Excavation Km 13+000 - Km 12+000 ( 3 )

6 21-Aug-14

27-Aug-14

319

Excavation Km 12+000 - Km 11+000 ( 1 )

5 28-Aug-14

03-Sep-14

293

Excavation Km 12+000 - Km 11+000 ( 2 )

3 04-Sep-14

06-Sep-14

290

Excavation Km 12+000 - Km 11+000 ( 2 )

Excavation Km 11+000 - Km 10+000 ( 1 )

3 08-Sep-14

10-Sep-14

268

Excavation Km 11+000 - K

Excavation Km 11+000 - Km 10+000 ( 2 )

3 11-Sep-14

13-Sep-14

268

Excavation Km 10+000 - Km 09+000 ( 1 )

3 15-Sep-14

17-Sep-14

381

Excavation Km 10+000 - Km 09+000 ( 2 )

6 18-Sep-14

24-Sep-14

381

0
EXCAVATION IN SOLID ROCK ( DRILLING AND BLASTING )
41 07-Aug-14
24-Sep-14
ENBANKMENT CONFORMATION WITH OWN MATERIAL -AND OWN MATERIAL
TERRA SQUARE
Enbakmebnt - Own Material Km 14+000 - km 13+000 ( 1 )
6 07-Aug-14 13-Aug-14

0
6307
843

Excavation Km 13+000 - Km 12+000 ( 2 )


Excavation Km 13+000 - Km 12+000 ( 3 )
Excavation Km 12+000 - Km 11+000 ( 1 )

Excavation Km 11+0
Excavation Km
E
2
Enbakmebnt - Own Material Km 14+000 - km 13+000 ( 1 )

Enbakmebnt - Own Material Km 14+000 - km 13+000 ( 2 )

6 21-Aug-14

27-Aug-14

515

Enbakmebnt - Own Material Km 14+000 - km 13+000 ( 3 )

5 28-Aug-14

03-Sep-14

515

Enbakmebnt - Own Material Km 13+000 - km 12+000 ( 1 )

6 14-Aug-14

20-Aug-14

612

Enbakmebnt - Own Material Km 13+000 - km 12+000 ( 2 )

6 21-Aug-14

27-Aug-14

612

Enbakmebnt - Own Material Km 13+000 - km 12+000 ( 3 )

5 28-Aug-14

03-Sep-14

806

Enbakmebnt - Own Material Km 13+0

Enbakmebnt - Own Material Km 12+000 - km 11+000 ( 1 )

6 04-Sep-14

10-Sep-14

801

Enbakmebnt - Own Mater

Enbakmebnt - Own Material Km 12+000 - km 11+000 ( 2 )

6 11-Sep-14

17-Sep-14

801

Enbakmebnt - Own Material Km 12+000 - km 11+000 ( 3 )

6 18-Sep-14

24-Sep-14

801

0 STONE - TERRA SQUARE


ENBANKMENT CONFORMATION WITH BORROWED MATERIAL AND CRUSHED
35 07-Aug-14
PROF. AND COMPAC. OF SUB-GRADE IN ZONES-CUT (ROAD, IMPROVEMENT,
CROSSING 17-Sep-14
Prof. and compac. of sub-grade Km 14+000 - km 13+000 ( 1 )
6 07-Aug-14 13-Aug-14

0
937
182

17-Sep-14, P
Prof. and compac. of sub-grade Km 14+000 - km 13+000 ( 1 )

Prof. and compac. of sub-grade Km 14+000 - km 13+000 ( 2 )

6 14-Aug-14

20-Aug-14

182

Prof. and compac. of sub-grade Km 14+000 - km 13+000 ( 2 )

Prof. and compac. of sub-grade Km 13+000 - km 12+000 ( 1 )

6 21-Aug-14

27-Aug-14

155

Prof. and compac. of sub-grade Km 13+000 - km 12+000 ( 2 )

5 28-Aug-14

03-Sep-14

155

Prof. and compac. of sub-grade Km 1

Prof. and compac. of sub-grade Km 12+000 - km 11+000 ( 1 )

6 04-Sep-14

10-Sep-14

132

Prof. and compac. of sub-

Prof. and compac. of sub-grade Km 12+000 - km 11+000 ( 2 )

6 11-Sep-14

17-Sep-14

132

Prof. and com

07-Aug-14
28-Aug-14

02-Oct-14
02-Oct-14

28-Aug-14
28-Aug-14

15-Sep-14
15-Sep-14

20910
7774
0
2719
2719

15-Sep-14, REIN
Reinforced Soil W

ARTWORKS AND DRAINAGE


WORK FRONT I ( KM 0+000 - KM 14+000 )
RETAINING WALLS
REINFORCED SOIL WALLS
Reinforced Soil Wall 14 Km 12+960 - Km 13+121 ( L = 160.50m )

48
30
0
15
15

Enbakmebnt - Own Material Km 14+000 - km 13+000 ( 2 )


Enbakmebnt - Own Material Km 14+0
Enbakmebnt - Own Material Km 13+000 - km 12+000 ( 1 )
Enbakmebnt - Own Material Km 13+000 - km 12+000 ( 2 )

Enbakmebnt

Prof. and compac. of sub-grade Km 13+000 - km 1

Page 2 of 4

Activity ID

Activity Name
CULVERTS
Culvert 12 Km 10+655 ( L = 19.58m )

Original Start

Finish

Schedule 90 days
Budgeted Labor
Units
26

Duration
30 28-Aug-14
4 15-Sep-14

02-Oct-14
18-Sep-14

5055
543

30 28-Aug-14

02-Oct-14

4512

Culvert 13 Km 12+482 ( L = 156.60m )


DITCHES
WORK FRONT II ( KM 14+000 - KM 30+560 )
RETAINING WALLS
REINFORCED SOIL WALLS
Reinforced Soil Wall 15 Km 15+879 - Km 16+080 - CR ( L = 201.50m )

0
36 07-Aug-14
0
20 07-Aug-14
14 07-Aug-14

01-Sep-14
23-Aug-14

0
13136
0
4801
157

18-Sep-14

July 2014
03

10

August 2014
17

24

31

07

14

September 2014
21

28

04

11

18

25

Culvert 12 K

18-Sep-14,
01-Sep-14, REINFORCED SOIL WALLS
Reinforced Soil Wall 15 Km 15+879 - Km 16+080 - CR ( L

Reinforced Soil Wall 16 Km 15+879 - Km 16+081 ( L = 202.50m )

14 14-Aug-14

01-Sep-14

4644

Reinforced Soil Wall 16 Km 15+879 - Km

CULVERT
Culvert 14 Km 17+727 ( L = 78.30m )

27 18-Aug-14
12 18-Aug-14

18-Sep-14
01-Sep-14

8335
2334

18-Sep-14,
Culvert 14 Km 17+727 ( L = 78.30m )

Culvert 15 Km 20+784 ( L = 19.58m )

3 04-Sep-14

08-Sep-14

638

Culvert 16 Km 21+374 ( L = 36.25m )

4 05-Sep-14

09-Sep-14

986

Culvert 17 Km 21+924 ( L = 39.15m )

6 10-Sep-14

16-Sep-14

1121

Culvert 17 Km

Culvert 18 Km 22+254 ( L = 39.15m )

6 08-Sep-14

13-Sep-14

1015

Culvert 18 Km 22+2

Culvert 19 Km 22+514 ( L = 33.59m )

4 15-Sep-14

18-Sep-14

995

Culvert 20 Km 23+577 ( L = 44.69m )

8 28-Aug-14

06-Sep-14

1246

04-Sep-14
04-Sep-14
04-Sep-14
04-Sep-14

24-Sep-14
24-Sep-14
24-Sep-14
10-Sep-14

0
7786
7786
7786
2382

2
2
2
Granular sub base Km 14

Granular sub base Km 15+000 - km 16+000

6 11-Sep-14

17-Sep-14

2946

Granular sub

Granular sub base Km 16+000 - km 17+000

6 18-Sep-14

24-Sep-14

2458

DITCHES
GRANULAR SUB BASE AND BASE
WORK FRONT II ( KM 14+000 - KM 30+0560 .)
GRANULAR SUB BASE
Granular sub base Km 14+000 - km 15+000

GRANULAR BASE
WORK FRONT I ( KM 00+000 - KM 14+000 )
GRANULAR SUB BASE
GRANULAR BASE
PRIMER AND SAFETY BERM
WORK FRONT II ( KM 14+000 - KM 30+560. )
PRIMER
SAFETY BERM
Safety Berm Km 15+000 - Km 16+000
Safety Berm Km 20+000 - Km 21+000

0
18
18
18
6

0
0
0
0
69
17
0
17
3

26-Jun-14
28-Aug-14

17-Sep-14
17-Sep-14

28-Aug-14
28-Aug-14

17-Sep-14
01-Sep-14

0
0
0
0
717
478
0
478
239

Culvert 15 Km 20+784 ( L = 19.58m )


Culvert 16 Km 21+374 ( L = 36.25m )

Culvert 19 K
Culvert 20 Km 23+577 ( L = 44.69m )

17-Sep-14, P
17-Sep-14, W
17-Sep-14, S
Safety Berm Km 15+000 - Km 16+000

3 15-Sep-14

17-Sep-14

239

WORK FRONT I ( KM 00+000 - KM 14+000 )


PRIMER
SAFETY BERM
Safety Berm Km 10+000 - Km 11+000

3 26-Jun-14
0
3 26-Jun-14
3 26-Jun-14

28-Jun-14
28-Jun-14
28-Jun-14

239
0
239
239

PAVEMENTS
KM 00+000 - KM 30+560
HOT ASPHALTIC LAYER E=6 CM
SIGNAGE AND ENVIRONMENTAL PROTECTION
( KM 0+000 - KM 30+560 )

0
0
0
0
0
8 12-Sep-14

20-Sep-14

0
0
0
0
0
308

20-Sep-

8 12-Sep-14
4 12-Sep-14

20-Sep-14
16-Sep-14

308
140

20-SepBerms and side

4 17-Sep-14

20-Sep-14

168

AREA 2.- IMPROVEMENT TO LA JOYA TRANSFER STATION ENTRANCE


PRELIMINAR WORKS
Berms and sidewalks demolition
Existing pavement demolition
EARTHWORK
VARIOUS WORKS
ROWLOCK
SONOROUS STRIP
GRANULAR SUB BASE AND BASE
PAVEMENTS
SIGNALING AND ENVIRONMENTAL PROTECTION

0
0
0
0
0
0
0

Safety Berm
28-Jun-14, WORK FRONT I ( KM 00+000 - KM 14+000 )
28-Jun-14, SAFETY BERM
Safety Berm Km 10+000 - Km 11+000

Existing

0
0
0
0
0
0
0
Page 3 of 4

Activity ID

Activity Name

AREA 3.- LA JOYA STATION BY PASS


PRELIMINAR WORKS
EARTHWORK
VARIOUS WORKS
CROSS AT GRADE
GRANULAR SUB BASE AND BASE
PAVEMENTS
SIGNALING AND ENVIRONMENTAL PROTECTION

AREA 4.- MATARANI - PANAMERICANA CROSSING


PRELIMINAR WORKS
VARIOUS WORKS
EXISTING INSTALLATIONS BURIED
TELEFONICA - FIBER OPTIC NETWORK
TELMEX - FIBER OPTIC NETWORK
VIETTEL- FIBER OPTIC NETWORK
BRACING FOR EXISTING ELECTRICAL NETWORKS
REP - L1030
ELEVATION OF EXISTING ELECTRICAL NETWORKS
SEAL - SAN CAMILO CIRCUIT
EARTHWORKS
GRANULAR SUB BASE AND BASE
PAVEMENTS
SIGNALING AND ENVIROMENTAL PROTECTION

Original Start
Duration
0

Finish

Schedule 90 days
Budgeted Labor
Units
26

July 2014
03

10

August 2014
17

24

31

07

14

September 2014
21

28

04

0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 4 of 4

11

18

25

Das könnte Ihnen auch gefallen