MONTHLY REPORT

Summary of Activities
November 2014

1. Structural inspection at Raw Water Intake System (Weir, Collector Well, and
Infiltration Gallery), 230KV switchyard Transmission Tower (Bored piling),
Comprehensive pipe rocks and Chimney
a) Weir and Infiltration Gallery

Installation of gabion for erosion control at east side of the river


Extraction of blocked steel sheet pile on the river part
Installation of HDPE pipe skimmer on head wall

b) Collector Well

Inspection of rebar and monitoring of concrete pouring of pump


chamber wall at GL 3, 4 and 5/1-6 (Third and last lift)
Inspection of rebar and monitoring of concrete pouring of wall-2
GL 1-6/J-M (last lift)
Inspection of rebar at wall-1 GL 1-6/A-I (Last lift)
Concrete pouring of wall-1 GL 1-6/A-I (Last Lift)
Concrete pouring of wall-1 GL A/2-6 (Last Lift)
Inspection of rebar at Drywell wall GL 1-6/B (First, second, third
and last lift)
Concrete pouring of Drywell wall GL 1-6/B (First, second, third
and last lift)
Inspection of rebar, layout, elevation and monitoring of concrete
pouring of collector well pump house beams and installation of
trusses and roofings

c) 230KV switchyard Transmission Tower (Bored piling)

Concrete pouring of bored pile cap at pole 2, 3, 4 and 7


Erection of Steel transmission tower at pole 1-7

d) Comprehensive Pipe Rocks

Inspection of Layout, plumbness and elevation of steel


structures.

e) Chimney
Installation of hydraulic jack for chimney liner lifting at elevation
115m.
Erection of Chimney inner liner 1 and fitting up and welding of
connections

f) Transfer Tower 0 and Transfer Tower 1


Inspection of rebar, steel plates embedments, layout and
elevations of slabs..
g) Fly Ash Silo
Inspection of rebar, steel plates, and layout of silo wall.